Town Hall Meeting 12 March 2008
Carmichael Area Aerojet Groundwater
Remediation Progress Update
12 March 2008
Presentation Program
Carmichael Water District – Steve
Nugent General Manager
Regional Water Quality Control Board –
Alex MacDonald
GenCorp/Aerojet – Mike Girard
Acknowledgements
Congressman Dan Lungren
County Supervisor Susan Peters
Carmichael Water District Board
Members
March 2008 Update
Background on Carmichael Water District Involvement
Water Supply Reliability Improvements
Status of Bajamont Groundwater Extraction and
Treatment Plant Construction (GET L-B)
Status of Ancil Hoffman GET L-A Irrigation Reuse
Regional Objectives Going Forward
Questions and Answers
Regional Geology
CWD Service Area Wells and NDMA Plume
Water Supply Reliability
Expanding Surface Water Treatment
Plant from 16 MGD to 21 MGD New Membrane Treatment Modules Additional Treated Water Pumping Capacity Additional Chemical Treatment and Air
Handling
Expected Completion Plant Expansion
May 2008
Water Supply Reliability
Water Rights Permit Extension Filed
with Department of Water Resources
CEQA Process Underway to Support
Permit Extension Request
Expected Completion Late 2008
Water Supply Reliability
Participating in Regional Activities Briefings with Congressional Representative Briefings with State Government
Representatives Briefings with County and Local
Representatives Sacramento Groundwater Authority
Contamination Task Force ACWA Cap to Cap Outreach
GET “L-A” and “L-B” Remediation
GET “L-B” – Bajamont Site Operational
at 600 gpm and Discharging to the
American River
GET “L-A” – Design Underway with
Irrigation Reuse (1MGD) and Wet Weather
Discharge to American River
GET Treatment Process SummaryBajamont GET “L-B” Ancil Hoffman GET “L-A”
Initial Extraction Rate 325 gpm 600 gpm
Revised Extraction
Rate
600 gpm 800 gpm
Plant Design Capacity 1,000 gpm 2,000 gpm
Contaminants Present
Now
NDMA NDMA, Perchlorate, TCE
Contaminants
Expected
NDMA, Perchlorate,
TCE
NDMA, Perchlorate, TCE
Treatment Processes UV, GAC, (F) Ion
Exchange, (F) Peroxide
UV, Peroxide, (F) Ion
Exchange, (F) GAC
Bajamont GET “L-B” Update
Bajamont GET “L-B” Facility
Construction complete – Startup
Extraction Well September 7, 2007
Construction met date set by EPA
“Operational and Functional”
Certification by EPA Pending Completion
GET “L-A”
Bajamont GET “L-B” Facility
Bajamont GET “L-B” Facility
Bajamont GET “L-B” Facility
GET “L-B” Completed
Ancil Hoffman GET “L-A” Update
Design started at same time as GET L-B
but separated to allow public outreach
and siting process in Ancil Hoffman Park
to proceed at a slower pace
Milestone Achieved August 8, 2007:
Ancil Hoffman GET “L-A” Facility
location approved by County Board of
Supervisors
Ancil Hoffman GET “L-A” Update
CWD Participation includes Buried Reservoir and new Irrigation Pump Station for Golf Course
Reuse of Remediated Groundwater offsets surface water and maintains beneficial use of groundwater
Construction Buried Reservoir estimated to start Summer 2008
Strategic Goals
1. Early Detection & Identification of
Contaminants Near Our Water Supply Wells.
2. Expansion of the Bajamont Water Treatment
Plant.
3. Assist Aerojet in Locating, Permitting
Remediation Facilities.
4. Using Treated, Extracted Groundwater at
Ancil Hoffman Park.
Strategic Goals
5. Increased Conservation Efforts to Reduce Overall Demand.
6. Identify Potential Funding Sources for Projects.
7. Work Regionally to Enact Legislation to Increase Funding to Expedite Remediation Efforts.
8. Legal Representation.
March 2008 Town Hall Meeting
Questions