TK3333Software Management
Topic 8:Topic 8:Resource ConsiderationResource Consideration
ContentsContents• Learn how to take resource constraints into
account
• Determine the planned resource utilisation for a project
• Level the use of resources within the required time frame
• Determine the shortest project schedule with limited resources
Real World ExampleReal World Example• Vignette: Human Genome Project• In the 1980s, the US Department of Energy recommended a study to
define the entire human genome. • The US government began funding for scientists in the US to join the
Human Genome Project.• The project began with a $3 billion budget and a completion date of 2005.• Because of lack of technology in 1990, they spent the first few years
creating tools they might need. Once better technology was available, the scientists could work more efficiently.
• The Human Genome Project finished 2 years ahead of schedule, and $400 million under budget. Scientists were able to identify 99% of the human genome.
Real World ExampleReal World Example• Vignette: Indiana Road Construction Project• The state of Indiana decided to close a stretch of Interstate 65 and
Interstate 70 in Indianapolis for construction.• A total shutdown of the road would allow work crews to work through the
night to complete the project in 85 days. It would take 250 days without a total shutdown.
• The state knew that closing the highway would be an inconvenience- approximately 175,000 vehicles travel the highway each day. They decided to devise a communication campaign to inform the public about the highway closing.
• Construction began in May 2003 with no major problems. The public knew in advance about the project, so they were able to use alternate routes or public transportation.
Resource-Constrained PlanningResource-Constrained Planning• Nearly all projects have limits on available
resources.
• Project delays often occur due to certain resources being unavailable.
• A network diagram can be drawn to reflect the availability of a limited number of resources. – 1st: Arrange based on technically constrained activity
sequence.– 2nd: Arrange based on resource constraints, if any.
Resource-Constrained PlanningResource-Constrained Planning
Arrange Food
SetVenue
Invite Guests ....
Arrange Food Set
Venue
Invite Guests
....
With resource constraints
Without resource constraints
Planned Resource UtilisationPlanned Resource Utilisation
• It is necessary to indicate the amounts and types of resources needed to perform each activity.
• E.g.
Planned Resource UtilisationPlanned Resource Utilisation• Based on the information in the network diagram, a
resource utilisation chart is produced:
Source: pg. 244-245
No. of painters x No. of days
Total of painters for the day
Planned Resource UtilisationPlanned Resource Utilisation
• 2 alternatives to draw resource utilisation charts:
– Based on each activity’s earliest start time => as-soon-as-possible (ASAP) schedule.
– Based on each activity’s latest start time => as-late-as-possible (ALAP) schedule.
Planned Resource UtilisationPlanned Resource Utilisation• Based on the resource utilisation chart, a resource
profile is produced:
Uneven utilisation of painters
Source: pg. 244-245
Resource LevelingResource Leveling
• Resource leveling, or smoothing, is a method for developing a schedule that attempts to minimise the fluctuations in requirements for resources (i.e. uneven distribution).
• This method levels the resources so that they are applied as uniformly as possible without extending the project schedule beyond the required completion time.
Resource LevelingResource Leveling
• Critical path: Paint 1st Floor + Paint Stairs &Hall = 12 days => cannot be touched (if we don’t want to delay the project).
• “Basement” can delay 8 days (12-4 days); “Bedroom” can delay 6 days (12-6 days); “Bathroom” can delay 2 days (12-8-2 days)
• 2 alternatives:1) Delay the activity with the most +ve slack (i.e. “Basement” +8 days slack) by 6
days (i.e. it starts after “Bedroom” is finished) => can use the same person to do both.
2) Delay “Bedroom” by 4 days (i.e. it starts after “Basement” is finished).
Source: pg. 244
Resource LevelingResource Leveling
Source: pg. 246-247
If choose Alternative 1 :
More even utilisation of painters
Resource-Limited SchedulingResource-Limited Scheduling
• Resource-limited scheduling is a method for developing the shortest schedule when the number or amount of available resources is fixed and cannot be exceeded.
• This method will extend the project completion time if necessary in order to keep within the resource limits.
• It is an iterative method where resources are allocated based on the least slack.– Least slack has the higher priority.
Resource-Limited SchedulingResource-Limited Scheduling
Source: pg. 248-249
1st Priority
Presuming only 2 people are available:
Shifted to after Day 8 (when 2 painters are free)
1st iteration;1st Priority
2nd Priority, which one?
Resource-Limited SchedulingResource-Limited Scheduling
Source: pg. 251-252
2nd iteration1st Priority
Cannot touch - critical Has to be sacrificed
Shifted to after Day 12 (when 1 painter is free)
3rd iteration
Has to be sacrificed
Project Management SoftwareProject Management Software• Provides excellent features for handling resource
considerations within a project.
• Allows you to create and maintain a list of resources.
• Resources can be assigned to various tasks within a project.
• The user is informed if any resources have time conflicts or if they are over-allocated.
• Numerous resource allocation reports can be generated.
Some notes …Some notes …• During scheduling, assume unlimited resources. Or else, it
takes forever to work out the schedule.– If resources are unavailable, techniques such as resource leveling
and resource-limited scheduling can help.
• Software can only calculate, not decide.– We have to set the inputs i.e. duration, dependencies etc.
– “Garbage-in-Garbage-out”
– Don’t be too rigid about “must start/end” dates. Let the software calculates based on your inputs.
Some notes …Some notes …• Do not assume people to work more than 50-60% of the
time.– Knowledge workers (e.g. software engineers) are not like factory
workers (who are tied to their workstations).
– For knowledge work (i.e. engineering and programming), the maximum duration of an increment should be 1-3 weeks. Or else, it will reach 90% completion and stays forever. Why?
Time
% Complete100 Due to:
•Discovering “must-do but forgotten” things.
•Debugging => It’s common to find the solution after the deadline so that the work is completed in one simple step.D
EAD
LIN
E
Some notes …Some notes …• If duration of knowledge work is too long.
Discovering “must-do but forgotten” things
Time
% Complete100
DEA
DLI
NE
Time
% Complete100
Debugging
DEA
DLI
NE
Some notes …Some notes …• Major causes of reduced resource availability:
– Having people work on too many projects at the same time.• Every time a person “shifts gears”, it takes time for them to remember where they
were, get the momentum etc.
• No one should work more than 2-3 projects. Ideally, one project is enough.
– Overallocation of people to their work.• Queuing theory – if no “out”, no chance of “in”.
• No system should be loaded beyond 85% capacity for very long. 15% should be reserved to respond to “turbulence”.
• Estimating is guessing.– All activities are probabilistic, not deterministic.
– It is best done with past experience.
Some notes …Some notes …• Parkinson’s Law (1955):
– Work will always expand to take as long as has been allowed. Projects never finish early!
• Goldratt’s Principle (1997):– A project will accumulate delays but will never accumulate gains (i.e.
always costs more than necessary and takes longer than it should).
• Accept variations.– It is OK to have variations (i.e. allows dates to vary) as long as the
project finishes on time (i.e. some early, some late => variations will average out).
– Takes “typical values” for the estimates.
Some notes …Some notes …• What if, we have no past experience. How to estimate?
– Use consensual estimating.• Ask several individuals who know something about the task for an estimate.• Understand the variations among the estimates given by the individuals.• Choose a single realistic number that everyone agrees and can support.• May take time but it is worthwhile.
• When ask for estimates, ask both: actual working time & calendar time.– Why? We are always juggling tradeoffs between those times.– Actual working time => labour costs; calendar time => completion time.
Some notes …Some notes …• In many projects, we don’t own the resources; they are
provided by functional managers on a temporary basis.– The necessary signatures should be obtained in a project plan sign-off
meeting.
– The functional managers should be clear that their signatures indicate their commitment to provide resources when and in the quantities they say.
• If we have more than one project, prioritise them.– Ensure products are produced over time, rather than all at once.
Tota
l Sal
es R
even
ue
Gen
erat
ed
Time Time
Tota
l Sal
es R
even
ue
Gen
erat
ed
Thank YouThank You
• Question?
• Next (27/4) :– Cost Planning and Performance