• CLAS12 Project Description and Status
– Scope
– Science program & Collaboration
– Cost
– Schedule
– Summary
Thomas Jefferson National Accelerator FacilityStatus of the CLAS112 Project Page 3
A B C
Jefferson Lab Today
Two high-resolution 4 GeV spectrometers Large acceptance spectrometer
electron/photon beams
7 GeV spectrometer, 1.8 GeV spectrometer,
large installation experiments
Hall A Hall B
Hall C
Thomas Jefferson National Accelerator FacilityStatus of the CLAS112 Project Page 4
6 GeV CEBAF11
CHL-2CHL-2
12Upgrade magnets Upgrade magnets
and power and power suppliessupplies
Two 0.6 GV linacs1.1
Enhanced capabilities in existing Halls
Thomas Jefferson National Accelerator FacilityStatus of the CLAS112 Project Page 5
Scope of the 12 GeV Upgrade
12 GeVNew HallEnergy to Hall D
max ~85 µA combined
(higher at lower energy)
max ~180 µA combinedCurrent – Hall A & C
5.5New HallNumber of passes to Hall D
2.2 GeV1.2 GeVAccelerator energy per pass
5040# of cryomodules in LINACS
9 kW4.5 kWCentral Helium Liquefier (CHL)
(B, D) Up to ~5 µA max each
(B) Up to 5 µA maxCurrent – Hall B & D
up to ~11 GeVup to ~6 GeVMax Energy to Halls A/B/C
5 (for max energy)5 (for max energy)Number of passes Halls A/B/C
43Number of Halls
Upgraded JLabPresent JLabParameter
12 GeVNew HallEnergy to Hall D
max ~85 µA combined
(higher at lower energy)
max ~180 µA combinedCurrent – Hall A & C
5.5New HallNumber of passes to Hall D
2.2 GeV1.2 GeVAccelerator energy per pass
5040# of cryomodules in LINACS
9 kW4.5 kWCentral Helium Liquefier (CHL)
(B, D) Up to ~5 µA max each
(B) Up to 5 µA maxCurrent – Hall B & D
up to ~11 GeVup to ~6 GeVMax Energy to Halls A/B/C
5 (for max energy)5 (for max energy)Number of passes Halls A/B/C
43Number of Halls
Upgraded JLabPresent JLabParameter
Thomas Jefferson National Accelerator FacilityStatus of the CLAS112 Project Page 6
New Capabilities in Halls A, B, & C, and a New Hall D
9 GeV tagged polarized photons and a 4 hermetic detector
D
Super High Momentum Spectrometer (SHMS) at high luminosity and forward angles
C
High Resolution Spectrometer (HRS) Pair, and specialized large installation experiments
AB
CLAS12 high luminosity, large acceptance.
2/25/09 6Volker Burkert, CLAS12 Workshop, Genoa
Thomas Jefferson National Accelerator FacilityStatus of the CLAS112 Project Page 7
Overview of Upgrade Technical Performance Requirements
Hall D Hall B Hall C Hall A
excellent hermeticity
luminosity
1035
energy reach installation space
polarized photons hermeticity precision
EGeV 11 GeV beamline
108 photons/s target flexibility
good momentum/angle resolution excellent momentum resolution
high multiplicity reconstruction luminosity up to 1038
particle ID
B
.
Thomas Jefferson National Accelerator FacilityStatus of the CLAS112 Project Page 8
CLAS12
Lum > 1035cm-2s-1
• GPDs & TMDs• Nucleon Spin Structure • N* Form Factors• Baryon Spectroscopy • Hadron Formation
Central Detector
Forward Detector
CLAS12 CLAS12
2m
Initial Science ProgramInitial Science Program
Physics Focus Approved experiments
LOIs supported
GPD’s & exclusive Processes 3 1
TMDs & SIDIS 4 4
Parton Distribution Function & DIS 2 1
Elastic & resonance form factors 2
Hadronization & Color Transparency 2
Baryon Spectroscopy 1
Total 13 7
CLAS12CLAS12
Approved experiments correspond to about 5 years of scheduled beam operation .
Institution Focus AreaArizona State University (US) Beamline, Tagging SystemArgonne National Laboratory (US) Cerenkov Counter
California State University (US) Cerenkov CountersCatholic University of America (US) SoftwareCollege of William & Mary (US) Calorimetry, Magnet Mapping
Edinburgh University (UK) Software Fairfield University (US) Polarized TargetFlorida International University, Miami (US) Beamline/Moller polarimeter
Glasgow University (UK) Central Detector, DAQ, Forward Tagger, RICH Grenoble University/IN2P3 (France) Central Detector
Idaho State University (US) Drift chambers INFN –University Bari (Italy) tbd, interest in RICH INFN –University Catania (Italy) tbd
INFN – Frascati and Fermi Center (Italy) Central Neutron Detector+ interest show in RICHINFN –University Ferrara (Italy) (will join in 2010) tbd, interest in RICHINFN – University Genoa (Italy) Central Neutron Detector+ interest in Forward Tagger
INFN – ISS/Rome 1 (Italy) tbd, interest in RICHINFN – University of Rome Tor Vergata (Italy) Central Neutron Detector+ HD targetInstitute of Theoretical and Experimental Physics (Russia) SC. Magnets, Simulations
James Madison University (US) CalorimetryKyungpook National University (Republic of Korea) CD TOFLos Alamos National Laboratory (US) Silicon Tracker
Moscow State University, Skobeltsin Institute for Nuclear Physics (Russia) Software, SVT Moscow State University (High Energy Physics) (Russia) Silicon TrackerNorfolk State University (US) Preshower Calorimeter
Ohio University (US) Preshower Calorimeter Orsay University/IN2P3 (France) Central Neutron Detector
Old Dominion University (US) Drift ChambersRenselear Polytechnic Institute (US) Cerenkov Counters
Rice University Houston (US) CD TOFCEA Saclay (France) Central Tracker, Reconstruction softwareTemple University, Philadelphia (US) Cerenkov Counters
Thomas Jefferson National Accelerator Facility (US) Project coordination & oversightUniversity of Connecticut (US) Cerenkov CountersUniversity of New Hampshire (US) Central Tracker, Offline Software
University of Richmond (US) Offline SoftwareUniversity of South Carolina (US) Forward TOFUniversity of Virginia (US) Beamline/Polarized TargetsYerevan Physics Institute (Armenia) Calorimetry
CLAS12 Institutions
10
Thomas Jefferson National Accelerator FacilityStatus of the CLAS112 Project Page 11
12 GeV COST SUMMARY
• Accelerator and Hall equipment are roughly equal
• Hall B/C/D equipment cost averages ~$26M
• Civil split ~equally between Accelerator systems & Hall D
}
Thomas Jefferson National Accelerator FacilityStatus of the CLAS112 Project Page 12
12 GeV Upgrade Funding Profile
-
10,000
20,000
30,000
40,000
50,000
60,000
70,000
FY04 FY05 FY06 FY07 FY08 FY09 FY10 FY11 FY12 FY13 FY14 FY15
$K
12 GeV - $310M TPC - Jul-2008
Pre-Ops
Construction
PED
R&D
CDR/ACD
DOE Project Critical Decisions – 12 GeV Schedule
• CD-0 Approve Mission Need (Mar 2004)
• CD-1 Approve Alternative Selection and Cost Range (Feb 2006)• Permission to develop a Conceptual Design Report• Defines a range of cost, scope, and schedule options
• CD-2 Approve Performance Baseline (Nov 2007)• Fixes “baseline” for scope, cost, and schedule• Now develop design to 100%• Begin monthly Earned Value progress reporting to DOE• Permission for DOE-NP to request construction funds
• CD-3 Approve Start of Construction• DOE Office of Science CD-3 Approval: September 15, 2008
• CD-4 Approve Start of Operations or Project Close-out
DOE Generic Project Timeline
We are here
FEB 2006 NOV 2007 SEP 2008MAR 2004
12 GeV Upgrade – Approval dates
Thomas Jefferson National Accelerator FacilityStatus of the CLAS112 Project Page 15
DOE Critical Decision Schedule
CD-0 Mission Need MAR-2004 (A)
CD-1 Preliminary Baseline Range FEB-2006 (A)
CD-2 Performance Baseline NOV-2007 (A)
CD-3 Start of Construction SEP-2008
CD-4A Accelerator Project Completion and Start of Operations
DEC-2014
CD-4B Experimental Equipment Project Completion and Start of Operations
JUN-2015
(A) = Actual Approval Date
CD-4 split in two to ease transition into operations phase
Thomas Jefferson National Accelerator FacilityStatus of the CLAS112 Project Page 16
12 GeV Schedule
• May ’11 - Oct ‘11 6-month “down” for initial installations
•Nov ’11 - May ‘12 6-month run 6GeV
•Jun ’12 - May ‘13: 1-year “down” for major installation
• June ’13 - Sep ‘13: Accelerator commissioning
Thomas Jefferson National Accelerator FacilityStatus of the CLAS112 Project Page 17
12 GeV Schedule
•Oct ‘13: Hall A commissioning start
•Apr ‘14: Hall D commissioning start
•Oct ‘14: Hall B & C commissioning start
Thomas Jefferson National Accelerator FacilityStatus of the CLAS112 Project Page 18
2004-2005 Conceptual Design (CDR) - finished
2004-2008 Research and Development (R&D) – finished (but 1 task)
2006 Advanced Conceptual Design (ACD) - finished
2006-2009 Project Engineering & Design (PED) - ongoing
2009-2014 Construction – started !!Parasitic machine shutdown May 2011 through Oct. 2011
Accelerator shutdown start mid-May 2012
Accelerator commissioning start mid-May 2013
2013-2015 Pre-Ops (beam commissioning)
Hall A commissioning start October 2013
Hall D commissioning start April 2014
Halls B and C commissioning start October 2014
12 GeV Upgrade: Phases and Schedule(based on funding guidance provided by DOE-NP in June-2007)
Thomas Jefferson National Accelerator FacilityStatus of the CLAS112 Project Page 19
12 GeV Major Procurement Effort
Of the 29 Advanced Procurement Plans, 22 major procurements are being actively worked (~$65M Phased). A summary of their status is as follows:
3 Requests for information completed
3 Specifications completed
4 Open Solicitations (including CLAS12 Solenoid)
8 Bids Received (including CLAS12 TORUS)
1 Vendor Selected (Hall D Civil Construction Manager)
3 Awarded (Hall D B-Cal Fiber, CHL Civil, Hall D Civil)
22 Active Major Procurements
Of the 29 Advanced Procurement Plans, 22 major procurements are being actively worked (~$65M Phased). A summary of their status is as follows:
3 Requests for information completed
3 Specifications completed
4 Open Solicitations (including CLAS12 Solenoid)
8 Bids Received (including CLAS12 TORUS)
1 Vendor Selected (Hall D Civil Construction Manager)
3 Awarded (Hall D B-Cal Fiber, CHL Civil, Hall D Civil)
22 Active Major Procurements
Thomas Jefferson National Accelerator FacilityStatus of the CLAS112 Project Page 20
Future Upgrades to CLAS12 Base Equipment
• Micromegas (Saclay)– Detailed simulation and track reconstruction– Prototypes being tested, engineering design underway– Review will take place in May 2009
• RICH Detector (INFN, Argonne, UK )– Conceptual design with detailed simulations– PAC 34 approved 3 major experiments requiring RICH
• Neutron detector (IN2P3/INFN)– Detailed simulations, components being studied– PAC 34 gave high rating to the science presented in LOI
• HD-ice Polarized target (JLab/INFN)– Laboratory facility being designed
• Quasi real photon tagging facility (INFN, UK)– Feasibility study
2007 NSAC Long Range Plan (4 recommendations)2007 NSAC Long Range Plan (4 recommendations)
We recommend the completion of the 12 GeV Upgrade at We recommend the completion of the 12 GeV Upgrade at Jefferson Lab.Jefferson Lab.
- It will enable - It will enable three-dimensional imaging of the nucleonthree-dimensional imaging of the nucleon, revealing , revealing hidden aspects of its internal dynamics. hidden aspects of its internal dynamics.
- It will complete our understanding of the It will complete our understanding of the transition between the transition between the hadronic and quark/gluon descriptionshadronic and quark/gluon descriptions of nuclei. of nuclei.
- It will test definitively the It will test definitively the existence of exotic hadronsexistence of exotic hadrons, long-, long-predicted by QCD as arising from quark confinement. predicted by QCD as arising from quark confinement.
- It will provide It will provide low-energy probes of physics beyond the Standard low-energy probes of physics beyond the Standard ModelModel complementing anticipated measurements at the highest complementing anticipated measurements at the highest accessible energy scales.accessible energy scales.
Recommendation 1
Thomas Jefferson National Accelerator FacilityStatus of the CLAS112 Project Page 22
Message from JLab Director to CLAS12 Workshop
I had hoped to be with you for at least part of the workshop; unfortunately it became necessary for me to attend a conflicting meeting in Washington, DC, so although I believe my name appears in the participant list, I can claim only a virtual presence.
…. you can be assured that we are working hard to provide the resources both for the 12 GeV Upgrade project and for the running of the 6 GeV program. We were very pleased that recently we received 19 proposals for experiments in the 12 GeV era including some which seek to extend the scope of the currently planned equipment.
….. it is very important that we ensure the resources to provide the base capabilities, but it is also important to develop initiatives and momentum which will ensure an expanding program as we start to operate the machine in the new era.
Please convey my best wishes to all, and, especially to the collaboration, my hopes for a successful workshop.
Hugh Montgomery
Thomas Jefferson National Accelerator FacilityStatus of the CLAS112 Project Page 23
Summary
• The 12 GeV Upgrade is the NSAC #1 Recommendation
• The 12 GeV Upgrade is the highest priority at Jefferson Lab
• The project is in construction phase:
CLAS12 construction started with the first major procurements in progress: the superconducting magnets, the forward tracking detectors, and the pre-shower calorimeter.
This is a very exciting time for hadronic physics,
and the perfect time for new collaborators to make
significant contributions to the physics and
equipment of
CLAS12
Thomas Jefferson National Accelerator FacilityStatus of the CLAS112 Project Page 24
12 GeV Upgrade Summary
• R&D is essentially complete• PED (Engineering Design) finishes this year (18% remaining)• Construction has started !
• Significant progress:– Procurement planning and awards– MOU development– Installation planning– Space planning
Last 6 months – very exciting!
Next 6 months – lots of hard work ahead
Continued strong User participation is critical to success
Thomas Jefferson National Accelerator FacilityStatus of the CLAS112 Project Page 25
CLAS12 – Central Detector
Charged particle tracking in 5T field ΔT < 60psec in CTOF for particle id Vertex reconstruction Moller shield Polarized target operation ΔB/B < 10-4
in 3x5 cm cylinder around center
2/25/09
25
Extension may include Central Tracking w/ Micromegas Neutron Detector Bonus detector
Thomas Jefferson National Accelerator FacilityStatus of the CLAS112 Project Page 26
Hall B Upgrade Schedule
Thomas Jefferson National Accelerator FacilityStatus of the CLAS112 Project Page 27
Hall B
Construction12.5%PED
1.2%
Remainder of 12GeV
Upgrade TEC86.3%
Hall B 12 GeV Upgrade Cost
(FY07$K Direct)PED 2,313 Construction 24,584 TOTAL TEC $26,897
Beamline
InfrastructureComputing
PED
Magnets
Detectors
ElectronicsDOE Conveened review of Cost and Schedule External Independent Project Review September 2007
DOE Conveened review of Cost and Schedule External Independent Project Review September 2007
Thomas Jefferson National Accelerator FacilityStatus of the CLAS112 Project Page 28
Cost Profile
Thomas Jefferson National Accelerator FacilityStatus of the CLAS112 Project Page 29
Hall B 12 GeV Upgrade WBS Structure
1.4.2.1SC Magnet
1.4.2.1SC Magnet
1.4.2.1.1Torus
1.4.2.1.1Torus 1.4.2.1.2
Solenoid
1.4.2.1.2Solenoid 1.4.2.2.1
Tracking
1.4.2.2.1Tracking
1.4.2.2.1.1SVT
1.4.2.2.1.1SVT 1.4.2.2.3.1
CTOF
1.4.2.2.3.1 CTOF 1.4.2.2.3.2
FTOF
1.4.2.2.3.2FTOF
1.4.2.2.4Cherenkov
1.4.2.2.4Cherenkov
1.4.2.2.4.1HTCC
1.4.2.2.4.1HTCC 1.4.2.2.4.2
LTCC
1.4.2.2.4.2LTCC
1.4.2.6Infrastructure
1.4.2.6Infrastructure
1.4.2.3.2DAQ
1.4.2.3.2DAQ1.4.2.3.1
Trigger
1.4.2.3.1Trigger
1.4.2.3.3Online
1.4.2.3.3Online
1.4.2.3.5Slow Controls
1.4.2.3.5Slow Controls
1.4.2.4.2TDC
1.4.2.4.2TDC1.4.2.4.1
ADC
1.4.2.4.1ADC
1.4.2.4.3Scalers
1.4.2.4.3Scalers
1.4.2.4.7Crates, Racks
1.4.2.4.7Crates, Racks
1.4.2.5.2Moller Polarimeter
1.4.2.5.2Moller Polarimeter
1.4.2.5.1Faraday Cup
1.4.2.5.1Faraday Cup
1.4.2.5.4Components
1.4.2.5.4Components
1.4.2.2Detectors
1.4.2.2Detectors
1.4.2.2.1.3DC
1.4.2.2.1.3DC
1.4.2.2.2.3PCAL
1.4.2.2.2.3PCAL
1.4.2.2.2Calorimeter
1.4.2.2.2Calorimeter 1.4.2.2.3
Time of Flight
1.4.2.2.3Time of Flight
1.4.2.3.4 Offline
1.4.2.3.4 Offline
1.4.2.3Computing
1.4.2.3Computing 1.4.2.4
Electronics
1.4.2.4Electronics
1.4.2.4.4High Voltage
1.4.2.4.4High Voltage
1.4.2.5Beamline
1.4.2.5Beamline
1.4.2Hall B
1.4.2Hall B
1.4.2.6.1Utilities
1.4.2.6.1Utilities 1.4.2.6.2
Frames
1.4.2.6.2Frames
1.4.2.6.3Assembly
1.4.2.6.3Assembly 1.4.2.6.4
Installation
1.4.2.6.4Installation
Thomas Jefferson National Accelerator FacilityStatus of the CLAS112 Project Page 30
Hall B ProjectHall Leader Volker BurkertHall Lead Engineer Dave KashyControl Account Manager Latifa Elouadrhiri
CLAS12 Steering CommitteeGail Dodge (Chair), Ralf Gothe, Paul Stoler, Gunther Rosner, Michel Garcon
Technical Working Groups Hall B Staff CollabotatorsTracking Detectors M. Mestayer G. Dodge (ODU)Silicon Vertex Tracker A. Yegneswaran M. Merkin (MSU)Cerenkov counters Y. Sharabian P. Stoler (RPICalorimetry S. Stepanyan K. Giovanetti (JMU)FTOF detectors D. Carman R. Gothe (USC) CTOF detector V. Baturin W. Kim (KNU)Beamline A. Deur D. Crabb (Uva)Magnets V. Burkert O. Pogorelko (ITEP) Online/DAQ S. Boiarinov K. Livingston (Glasgow)Offline D. Weygand M. Holtrop (UNH)
Hall B Upgrade Project Organization
Top Related