“Standardize for Success”
Supporting flawless Work Planning and Execution through effective Scheduling
2017 Nuclear Primavera Users GroupConference
January 24th & 25, 2017
Hilton Garden Inn Palm Beach Gardens3505 Kyoto Gardens Dr, Palm Beach Gardens, FL
Special Thanks To our NPUG committee members &
their companies for their support
NPUG Chair – John Fisher of Arizona Public Service Company
NPUG Vice-Chair – Gordon Cashmore of Southern Nuclear Company
NPUG Secretary – Debra Ruiz of Pacific Gas & Electric
NPUG Treasurer – Sheila Jackson of Duke Energy
NPUG Steering Committee Members:
Bruce Gordon of Arizona Public Service Company
Sheri Zerkel of Arizona Public Service Company
Raeann Turpin of Exelon
Pam Schmid of Exelon
Tom Raymond of FirstEnergy
Todd Rozelle of Nextera Energy
Kent Vaughan of Southern Nuclear Company
Tami Nitsch of Wolfe Creek Nuclear Station
Mark Bode of PSEG Nuclear
Issues Resolution Committee Chairs:
Co-Chair - Pam Schmid of Exelon
Co-Chair - Tom Raymond of FirstEnergy
Oracle Primavera Representative:
Geoff Roberts - Director, Energy Industry Strategy
1
Conference Timetable
Monday, January 23, 2017
5:00 – 8:00 Welcome Reception, Hotel Reception Area
• Registration and Networking
Tuesday, January 24, 2017
7:00 – 8:00 Continental Breakfast, Gardens Ballroom
8:00 – 12:00 Group Sessions
12:00 – 1:00 Lunch & Networking, Gardens Ballroom
1:00 – 4:30 Breakout Training Sessions
4:45 – 5:00 Day 1 Wrap-up
5:00 – 7:00 Vendor night - Lake Terrace & Lobby area
Wednesday, January 25, 2017
7:00 – 8:00 Continental Breakfast, Gardens Ballroom
8:00 – 12:00 Group Sessions
12:00 – 1:00 Lunch & Networking, Gardens Ballroom
1:00 – 4:30 Breakout Training Sessions
4:45 – 5:00 Closing Comments, Workshop Wrap-up
2
0700-08000800-0815
Rooms
0815-0830
0830-0845
0845-0900
0900-0915
0915-0930
0930-0945
0945-1000
1000-1015
1015-1030
1030-1045
1045-1100
Rooms Garden Conf Room Gulfstream Conf Room Board Room Garden Conf Room Gulfstream Conf Room Board Room
1100-1115
1115-1130
1130-1145
1145-12001200-12151215-12301230-12451245-1300
Rooms Garden Conf Room Gulfstream Conf Room Board Room Garden Conf Room Gulfstream Conf Room Board Room
1300-1315
1315-1330
1330-1345
1345-1400
1400-14151415-1430
1430-1445
1445-1500
1500-1515
1515-1530
1530-1545
1545-1600
1600-1615
1615-1630
1630-1645
1645-1700
1700-18001800-1900
Day 1Tuesday 01/24/2017
Day 2Wednesday 01/25/2017
Continental Breakfast & NetworkingGardens Ballroom Conference Room
Continental Breakfast & NetworkingGardens Ballroom Conference Room
NPUG ACTIVITIES FOR THE WEEK OF JANUARY 24 through 25, 2017
BREAK & NETWORKING BREAK & NETWORKING
How to work with Visualizer
Karen Pilla, Oracle Primavera
Outage Solutions Accelerator
Geoff Roberts, Oracle Primavera
Open For NetworkingIssue Resolution Committee
Review Issues Status(Pam Schmid/Tom Raymond - IRC Committee Co-Chairs)
Opening Remarks/Day 1 Review: John Fisher, NPUG Chairperson Introduce of NPUG Officers & Steering Committees Members Day 2 Review of previous days open items and todays agenda: John Fisher, NPUG Chairperson
Garden Conf Room
Keynote Speaker - Dave GronekFleet Outage Manager
Southern Nuclear Company
Work arounds for the top 10 IRC issues
(Pam Schmid/Tom Raymond - IRC Committee Co-Chairs)Primavera Roadmap
Geoff Roberts - Director, Energy Industry Strategy
Garden Conf Room
Lunch and NetworkingGardens Conference Room
Lunch and NetworkingGardens Conference Room
Analytics / BICS
Adam Powell, Oracle Primavera &
Raeann Turpin, Exelon
Transition Transition
P6 Team Member
Justin Murphy, Oracle Primavera &
Todd Rozelle, NexEra Energy
AEP's Project Controls & Construction Earned Value
Management System
Charlie Blankenbiller, American Electric Power
Reserved for Capital Projects Networking
(Kelli Wulf-Stewart)
Visualizer Breakout Session
John Fisher, APS &
Karen Pilla, Oracle Primavera
Schedule Structures & EV Reporting for Large Refurb
Projects
Derek McAuley Ontario Power
Open For Networking
Duke Energy's Move to P6
Ellen Adelman,Duke Energy
Using UPK for P6 Training
Kristy Contreras, Exelon Corp
BI Report Development for P6
Adam Powell, Oracle Primavera
Baselining and cost loading tips
Dave Jordan, Energy Northwest
Southern Company Custom Admin and Maintenance Tool
Gordon Cashmore, Southern Company
Transition Transition
Scoping Outage Projects Round Table Session
Exelon
AP-928 Update
Mark Utz, Exelon
Projects Monthly Report & Departmental Metrics
Linda Ramseyer-Hamblin & Cathy Lindal, APS/PVNGS
Upgrading to P6r16.2
David Maynard, Dominion & Tom Raymond, Firstenergy
Open For Networking
Unifier
Justin MurphyOracle Primavera
Open For Networking
BREAK & NETWORKING BREAK & NETWORKING
Southern Company's Custom Reporting & Burndowns
Todd Craig,
Southern Company
Resource Library Maintenance (Structure, Settings,
Availability, Roll-ups) and Leveling
Karen Pilla,
Oracle Primavera
Using Syntempo for capital projects
Kelli Wulf-Stewart
How tech can support the Nuclear Promise
Geoff Reborts,
Oracle Primavera
Open For Networking
Transition Transition
Day 1 Wrap-up & Introduction to Day 2 (Fisher)and what to expect from the IRC sessionPam Schmid/Tom Raymond - IRC Chairs
Conference Workshop Wrap Up, and Location of 2018 WorkshopJohn Fisher - NPUG Chairperson
Vendor's Night 17:00-19:00Lake Terrace & Lobby area
3
2017 Nuclear Primavera Users Group Workshop
Tuesday, January 24, 2017 Time Location 8:00 – 8:15 (0800 – 0815) - Gardens Ballroom Session Title Opening Remarks
Presenter John Fisher, Business Systems Consultant, APS, and NPUG Chair
Time Location 8:15 - 8:45 (0815 – 0845) - Gardens Ballroom Session Title Keynote Speaker
Presenter Dave Gronek, Fleet Outage Manager, Southern Nuclear Company
Dave has been with SNC for about 2 years now. Before that he served as Plant Manager at TVA’s Watts Bar Station. Prior to that he worked for Exelon filling positions of Outage Manager, Director of Work Management, and Operations Director.
Time Location 08:45 – 09:30 (0845 – 0930) - Gardens Ballroom Session Title Theme Speaker: Primavera Roadmap
Presenters Geoff Roberts, Director, Energy Industry Strategy Description Primavera Products – The Road Ahead
15 Minute Break and Networking Time Location 09:45 – 10:45 (0945 – 1045) - Gardens Ballroom Session Title Issue Resolution Committee Review Issues Status Presenter Pam Schmid & Tom Raymond - IRC Committee Co-Chairs
Description Review the top 10 business & IT issues as selected that the Issues Resolution Committee members which is made up of representatives from each utility
Time Location 09:45 – 10:45 (0945 – 1045) - Gulfstream Ballroom Session Title Open for networking
Presenter Description
Time - Location 09:45 – 10:45 (0945 – 1045) – Board Room Session Title Open for networking
Presenter Description
15 Minute Break to change rooms
NPUG
4
2017 Nuclear Primavera Users Group Workshop
Tuesday, January 24, 2017 Time Location 11:00 – 12:00 (1100 – 1200) - Gardens Ballroom Session Title P6 Team Member
Presenter Justin Murphy, Oracle Primavera & Todd Rozelle, NexEra Energy Description Current version of the Team Member updater tool
Time Location 11:00 – 12:00 (1100 – 1200) - Gulfstream Ballroom Session Title AEP's Project Controls & Construction Earned Value Management System
Presenter Charlie Blankenbiller, American Electric Power Description
Time Location 11:00 – 12:00 (1100 – 1200) – Board Room Session Title Reserved for Capital Projects Networking
Presenter Kelli Wulf-Stewart Description
60 Minute Lunch and Networking Time Location 1:00 – 2:00 (1300 – 1400) - Gardens Ballroom Session Title Using UPK for P6 Training
Presenter Kristy Contreras, Exelon Corp Description Exelon’s incorporation of the User Productivity Software for their training Time Location 1:00 – 2:00 (1300 – 1400) - Gulfstream Ballroom Session Title BI Report Development for P6
Presenter Adam Powell, Oracle Primavera Description Time Location 1:00 – 2:00 (1300 – 1400) – Board Room Session Title Baselining and cost loading tips
Presenter Dave Jordan, Energy Northwest Description
15 Minute Break and Networking
NPUG
5
2017 Nuclear Primavera Users Group Workshop
Tuesday, January 24, 2017 Time Location 2:15 – 3:15 (1415 – 1515) - Gardens Ballroom Session Title Scoping Outage Projects Round Table Session
Presenter Exelon Description
Time Location 2:15 – 3:15 (1415 – 1515) - Gulfstream Ballroom Session Title AP-928 Update
Presenter Mark Utz, Exelon Description An Overview of the changes to AP-928
Time Location 2:15 – 3:15 (1415 – 1515) – Board Room Session Title Projects Monthly Report & Departmental Metrics
Presenter Linda Ramseyer-Hamblin & Cathy Lindal, APS/PVNGS
Description How to establish Project Management metrics and reports to promote behavior changes and focus on forward looking indicators.
15 Minute Break and Networking
Time Location 3:30 - 4:30 (1530 – 1630) - Gardens Ballroom Session Title Southern Company's Custom Reporting & Burndowns
Presenters Todd Craig, Southern Company Description
Time - Location 3:30 - 4:30 (1530 – 1630) - Gulfstream Ballroom Session Title Resource Library Maintenance
Presenter Karen Pilla, Oracle Primavera Description Structure, Settings, Availability, Roll-ups, and Leveling
Time - Location 3:30 - 4:30 (1530 – 1630) – Board Room Session Title Using Syntempo for capital projects
Presenter Kelli Wulf-Stewart Description 15 Minute Break to change rooms
Time Location 4:45 - 5:00 (1645 – 1700) - Gardens Ballroom
Session Title Day 1 wrap-up & Introduction to Day 2 Presenter John Fisher, NPUG Chair Description Intro into Day 2 of the Workshop and What to expect from the IRC session End Day 1
Vendor's Night 17:00-19:00 - Lake Terrace & Lobby area
NPUG
6
2017 Nuclear Primavera Users Group Workshop
Wednesday, January 25, 2017 Time Location 8:00 – 8:15 (0800 – 0815) - Gardens Ballroom Session Title Day 2 Review of previous days open items and todays agenda
Presenter John Fisher, NPUG Chair
Time Location 8:15 – 9:30 (0815 – 0930) - Gardens Ballroom Session Title Work arounds for the top 10 IRC issues
Presenter Pam Schmid/Tom Raymond - IRC Committee Co-Chairs Description Discussion on the “Work Arounds” that various sites have for the top 10 IRC issues.
Time - Location 8:15 – 9:30 (0815 – 0930) - Gulfstream Ballroom Session Title Open For Networking
Presenter Description
Time - Location 8:15 – 9:30 (0815 – 0930) – Board Room Session Title Open For Networking
Presenter Description
15 Minute Break and Networking Time Location 9:45 – 10:45 (0945 – 1045) - Gardens Ballroom Session Title How to work with Visualizer
Presenter Karen Pilla, Oracle Primavera Description
Time - Location 9:45 – 10:45 (0945 – 1045) - Gulfstream Ballroom Session Title Outage Solutions Accelerator
Presenter Geoff Reborts, Oracle Primavera Description
Time - Location 9:45 – 10:45 (0945 – 1045) – Board Room Session Title Open For Networking
Presenter Description
15 Minute Break and Networking
NPUG
7
2017 Nuclear Primavera Users Group Workshop
Wednesday, January 25, 2017 Time Location 11:00 – 12:00 (1100 – 1200) - Gardens Ballroom Session Title Visualizer Breakout Session
Presenters John Fisher, APS & Karen Pilla, Oracle Primavera
Description Time Location 11:00 – 12:00 (1100 – 1200) - Gulfstream Ballroom
Session Title Schedule Structures & EV Reporting for Large Refurb Projects Presenter Derek McAuley, Ontario Power
Description Time Location 11:00 – 12:00 (1100 – 1200) – Board Room
Session Title Open For Networking Presenter
Description
60 Minute Lunch and Networking Time Location 1:00 – 2:00 (1300 – 1400) - Gardens Ballroom
Session Title Southern Company Custom Admin and Maintenance Tool Presenter Gordon Cashmore, Southern Company
Description This session will demonstration a custom P6 Administration and Maintenance tool to help with day to day user maintenance, interface maintenance, cleanup maintenance and monitoring of Primavera.
Time Location 1:00 – 2:00 (1300 – 1400) - Gulfstream Ballroom
Session Title Analytics / BICS Presenter Adam Powell, Oracle Primavera Description Time Location 1:00 – 2:00 (1300 – 1400) – Board Room
Session Title Duke Energy’s Move to P6 Presenter Ellen Adelman, Duke Energy
Description It’s more than converting from ProjectView to P6, it’s also migrating our Major Projects group from P6 on Loadspring to in-house P6.
15 Minute Break and Networking
NPUG
8
2017 Nuclear Primavera Users Group Workshop
Wednesday, January 25, 2017 Time - Location 2:15 – 3:15 (1415 – 1515) - Gardens Ballroom Session Title Upgrading to P6r16.2
Presenter David Maynard, Dominion & Tom Raymond, Firstenergy Description
Time Location 2:15 – 3:15 (1415 – 1515) - Gulfstream Ballroom Session Title Unifier
Presenter Justin Murphy, Oracle Primavera Description
Time Location 2:15 – 3:15 (1415 – 1515) – Board Room Session Title Open For Networking
Presenter Description
15 Minute Break and Networking Time - Location 3:30 - 4:30 (1530 – 1630) - Gardens Ballroom
Session Title How tech can support the Nuclear Promise Presenter Geoff Reborts, Oracle Primavera Description Time - Location 3:30 - 4:30 (1530 – 1630) - Gulfstream Ballroom Session Title Open For Networking
Presenter
Description Time - Location 3:30 - 4:30 (1530 – 1630) – Board Room Session Title Open For Networking
Presenter
Description
10 Minute Break to change rooms Time - Location 4:45 – 5:00 (1615 – 1700) - Gardens Ballroom Session Title Conference Workshop Wrap Up Presenter John Fisher, NPUG Chair Description Overview of the past two days - 2018 Workshop Location Announcement
NPUG
9
NUCLEAR PRIMAVERA USERS' GROUP (NPUG) CHARTER Revision 2
August 12, 2013
The Nuclear Primavera Users' Group (NPUG), hereafter referred to as the Users' Group, is a not for profit group formed for the development and exchange of technical information on the testing and use of Primavera products in the utility industry for increased reliability of operation and safety of nuclear power plants and standardization of best practices. A. MEMBERSHIP
1. Membership Requirements a. Any plant site or utility having an operating license or construction permit for a nuclear power plant and using or
planning to use Primavera may be a member of the Users' Group. b. Representatives should actively participate in committee and User Group activities as permitted by the
individual's work load. c. All members may be requested to provide technical information as necessary in response to generic efforts by the
group. d. "Utility" is defined as an entity having an operating license or construction permit for a nuclear power plant.
2. Associate Membership Requirements a. Any non-utility organization having a legitimate interest in the application of Primavera products in the nuclear
power industry may be an Associate Member of the Users' Group. b. Associate members shall refrain from direct marketing of related activities during the conduct of general sessions
and activities outside of vendor exhibits and hospitality periods. c. Associated members shall have no formal voting privileges.
3. Administration of Membership a. Each plant site or utility shall designate a primary and alternate (secondary) representative who shall have voting
privileges as outlined in Section E – Voting. b. A roster shall be established and maintained that identifies the member plant sites and the primary and alternate
representatives. c. A roster shall be established and maintained that identifies the Associate Members. d. Guest participants/speakers may attend meetings at the discretion of the Steering Committee (for example, invited
Keynote Speaker). B. FUNCTION
• Discuss and establish mechanisms to ensure that use of Primavera is continuously improving and the business processes are optimized
• Benchmark best business practices and processes • Provide consolidated input to Primavera for improvements that support the industry • Establish standardized performance indicators and targets • Optimize Primavera operational performance within nuclear • Ensure that self-assessment activities are effective in identifying Primavera scheduling application and process
weaknesses • Ensure that internal and external operating experience is built into the use of Primavera products. • Monitor Primavera costs (OM&A, capital and project) and evaluating return on investment versus best industry
practices • Identify and assess business risk from application changes. Develop risk management strategies • Identify needed Information Technology support for infrastructure • Benchmark program performance against others in the nuclear industry and in industries outside of the nuclear
business where relevant • Establish partnerships with other User Groups as possible. • Design common configuration structures to support Primavera use within Nuclear • Ensure relevant regulatory and licensing requirements are considered in the design of the Primavera
C. ORGANIZATION
1. Users' Group a. The Users' Group shall be a non-profit organization directing activities through a membership elected Steering
Committee.
10
NUCLEAR PRIMAVERA USERS' GROUP (NPUG) CHARTER Revision 2
August 12, 2013
b. The utility members shall elect a Users' Group Chairperson to serve a term of 2 years and may serve a maximum of 2 consecutive terms.
c. The utility members shall elect a Users' Group Vice Chairperson to serve a term of 2 years and may serve a maximum of 2 consecutive terms,.
d. The Users' Group Chairperson and Vice Chairperson shall be elected by a majority vote of the attending utility members.
e. Elections for Chairperson and Vice Chairperson should not be held in the same year, goal is to stagger elections for leadership continuity.
f. The term of elected officials shall begin at the conclusion of the meeting at which the vote was taken. g. Any vacancy occurring in any elected office shall be filled at the meeting following the occurrence of such
vacancy, except for the position of Chairperson, which shall be filled by the Vice Chairperson. Interim appointments to working committees can be made as discussed in Section D "DUTIES AND RESPONSIBILITIES" Paragraph 4 "Steering Committee."
h. The Chairperson will appoint a treasurer, if necessary, who shall maintain responsibility for all accounting and financial activities.
i. In the event that the Vice Chairperson is elected as the new Chairperson, the new Chairperson will select a NPUG member to fill the Vice Chairperson position until the next Vice Chairperson Election is held the following year.
2. Steering Committee a. The Steering Committee shall consist of the Users' Group Chairperson and Vice Chairperson and a minimum of
three additional utility members. b. The additional members to the Steering Committee shall be elected by a majority vote of the attending utility
members. c. The Steering Committee members, other than the Users' Group Chairperson and Vice Chairperson, shall serve a
term of 2 years and may serve any number of consecutive terms. d. In the event that the NPUG Steering Committee falls below the minimum of three additional utility members, the
remaining Steering Committee members shall select additional members to reach the minimum required. This will be done by majority vote of the remaining Steering Committee members. Should a tie in the voting exist, the NPUG Chairperson will have the deciding vote. These will be interim members of the Steering Committee until elections can be held at the next NPUG meeting where a vote by members can be held.
3. Committees a. Committees shall be established, as determined by the membership, to address issues relating to the Users' Group. b. A Chairperson and Alternate shall be elected for each committee and can serve for the life of the committee. c. Committee membership, including duly elected chairperson and alternate, can include both utility and associate
members. D. DUTIES AND RESPONSIBILITIES
1. Users' Group Representatives a. Meet as deemed appropriate by the Steering Committee. b. Establish committees for specific issues. c. Vote on recommended actions.
2. Users' Group Chairperson a. Preside at Users' Group and Steering Committee meetings. b. Arrange the order of business at all Users' Group and Steering Committee meetings. c. Act as the Users' Group spokesperson during meetings with other organizations. The chairperson may delegate
this responsibility for certain issues (e.g., Vice Chairperson, Steering Committee member, or committee Chairperson).
d. Conduct the official correspondence of the Users' Group, unless delegated. e. Notify the Users' Group members and the Steering Committee members of the time and place of meetings. f. Facilitate communications between the Steering Committee, the Users' Group members, and the various working
committees. 3. Users' Group Vice Chairperson
a. Perform the duties of the Users' Group Chairperson in the absence of the Chairperson. b. Serve as member and Vice Chairperson of the Steering Committee. c. Ensure that accurate minutes of the proceedings of all Users' Group and Steering Committee meetings are taken,
recorded, and distributed. Provide the coordination of recording and distribution services, if delegated. d. Maintain a current roster of all members.
4. Steering Committee
11
NUCLEAR PRIMAVERA USERS' GROUP (NPUG) CHARTER Revision 2
August 12, 2013
a. Direct the activities of the Users' Group. b. Collectively set the agenda for the Users' Group meetings. c. Review and/or recommend issues to be presented to the Users' Group. d. Recommend projects with outside agencies when considered in the best interest of the Users' Group. e. Ensure arrangements are made for the Users' Group meetings. f. Review the findings of committees of the Users' Group and ensure the Users' Group members are kept informed. g. The Steering Committee may appoint interim chairpersons to working committees upon loss of an existing
elected chairperson. The interim chairperson will serve until an opportunity for a committee election occurs. 5. Committees
a. Each committee shall elect a committee Chairperson from the committee members. b. Each committee shall develop a program plan with clear objectives and supporting schedule. The program plan
shall be submitted to the Steering Committee for review and approval. c. Committees shall report progress of their activities to the Users' Group. d. Minutes of committees meetings shall be prepared and transmitted to committee members.
E. MEETINGS
1. The Users' Group shall meet at a minimum of annually at a time and place designated by the Chairperson and approved by the Steering Committee. The agenda for the meetings will be determined by the Steering Committee
2. Attendance at some portions of general meetings or working committee meetings may be limited. The Steering Committee or the working committee Chairperson/Vice Chairperson, as appropriate, shall determine when the attendance shall be limited.
3. Written or electronic notice of each meeting should be sent to utility representatives and associate members at least thirty (30) days prior to the scheduled meeting. The notice should include a tentative agenda for the meetings.
4. Meeting minutes summarizing the presentations made at each User’s Group meeting shall be prepared and distributed. F. VOTING
1. Each nuclear plant site shall have one vote, to be cast by the primary representative or in his absence, the alternate representative.
2. In the absence of both the designated primary and alternate representative, a plant representative shall notify a Steering Committee member with the name of a designated person with voting authority for the plant site.
3. A vote will be presented on an approval or denial basis (yes/no) and can be requested by "voice", "show of hands" or ballot.
4. A two-thirds majority vote is required for approval of formal Users' Group actions. 5. When requested by the Steering Committee, a vote can be conducted by roll call, mail ballot, email, or telephone, and
shall require a two-thirds majority for approval. 6. A majority vote of Steering Committee members is required for approval of Steering Committee actions. 7. A majority vote of the attending committee members is required for approval of committee actions. 8. Associate members shall have no voting privileges.
G. FUNDING REQUIREMENTS
1. At no time shall a member utility or associate member be required to participate in funding requirements. 2. Expenses incurred for reproduction and postage of other correspondence or documents shall be at the expense of the
initiator(s). 3. In the event that activities of the Users' Group go beyond administrative needs, the Users' Group membership shall
determine the need for additional funding and the methods to be utilized to satisfy the requirement. 4. The Users' Group shall not receive or disburse funds without appropriate controls in place. 5. Clerical and/or Accounting services may be delegated by the Steering Committee on a contracted basis. All such
contracts will be reviewed and approved by a two-thirds majority vote of the Steering Committee membership. 6. At least two Steering Committee members – the Vice Chairperson and one other member will have access to account
information at all times. 7. Any and all monies collected for NPUG will be held in a separate account. An annual financial report shall be
prepared each year and reviewed by the Steering Committee.
12
NUCLEAR PRIMAVERA USERS' GROUP (NPUG) CHARTER Revision 2
August 12, 2013
H. USERS' GROUP TECHNICAL POSITIONS
1. Position statements issued by the Users' Group are not to be considered binding on the utilities and do not necessarily represent the position of member utilities. Under no circumstances shall positions adopted by the Users' Group be interpreted or considered to be commitments by member utilities toward any course of action.
2. If a Users' Group representative feels that the Users' Group position lacks merit, or an alternate position needs to be presented, alternate positions will be acknowledged by the Steering Committee and provided with the issuance of the Users' Group position, upon written request of the presenter.
3. Reports or position statements of the various working committees shall be presented to the Steering Committee by the committee Chairperson. If a committee member feels that the committee position lacks merit, or that an alternative position should be presented, the alternate position will be acknowledged by the committee Chairperson and provided with the committee position to the Steering Committee.
I. CHANGES TO CHARTER OR PRINCIPLES OF OPERATION
1. Requests for changes to the Charter or Principles of Operation shall be presented to the Steering Committee. 2. Changes to the Charter shall be approved by a unanimous vote of the Steering Committee. Quorum for the Steering
Committee shall be a minimum of four members. 3. In the event of non-unanimous votes of the Steering Committee, or at the discretion of the Users' Group Chairperson,
changes to the Charter shall be approved by two-thirds majority roll call vote of all the attending plant/utility representatives.
13
Nuclear Primavera Users Group
ISSUES RESOLUTION COMMITTEE
Member List
Name Company Email Phone Business / IT
Fisher, John Arizona Public Service [email protected] 623-393-6202 Business
Gordon, Bruce Arizona Public Service [email protected] 623-393-6155 Honorary
Seaton, Don Arizona Public Service [email protected] 623-393-4029 IT
Zerkel, Sherri Arizona Public Service [email protected] 623-393-3846 Business
Elyea, Adrien Bruce Power [email protected] Business
Lisi, Tony Bruce Power [email protected] IT
Malik, Ghulam Bruce Power [email protected] IT
Perry, Jeff Callaway [email protected] 573-676-4080 Business
Maynard, David Dominion [email protected] 804-263-2014 Business
Unbehagen, Paul Dominion [email protected] 540-894-2840 Business
Laskey, Vickie DTE (Fermi) [email protected] 734-586-5974 Business
Adelman, Ellen Duke Energy [email protected] 919-546-2406 Business
Burnett, Debbie Duke Energy [email protected] 980-373-2269 Business
Jackson, Sheila Duke Energy [email protected] 704-382-4726 IT
Wulf-Stewart, Kelli Entergy [email protected] 269-369-3061 Business
Campbell, Larry Exelon [email protected] 309-227-3135 Business
Forster, Jim Exelon [email protected] 610-765-5642 IT
Gomulka, Stephen Exelon [email protected] 609-971-4329 Business
Schmid, Pam Exelon Nuclear [email protected] 315-349-1556 Business
Turpin, Raeann Exelon Nuclear [email protected] 410-495-4178 IT
Ellis, Dolores FirstEnergy [email protected] 330-436-2844 IT
Raymond, Tom FirstEnergy [email protected] 330-436-1483 Business
Bremer, Lesli Nebraska Public Power [email protected] 402-825-5808 Business
Parrish, Kyle Nebraska Public Power [email protected] 402-825-2715 IT
Stramel, Barbara Nebraska Public Power [email protected] 402-825-2792 Business
Lawrence, Christina NextEra Energy [email protected] 603-773-7201 IT
14
Nuclear Primavera Users Group
ISSUES RESOLUTION COMMITTEE
Member List
Name Company Email Phone Business / IT
Rozelle, Todd NextEra Energy [email protected] 603-773-7603 Business
Spindler, Faye NextEra Energy [email protected] 920-755-6599 Business
Cuhtenco, Melissa Ontario Power [email protected]
Ext. 5409Business
Khan, Muneeb Ontario Power [email protected] 647-333-5426 IT
Baker, Dennis Pacific Gas & Electric [email protected] 805-545-3205 IT
Johnson, David Pacific Gas & Electric [email protected] 805-545-4717 Business
Ruiz, Debbie Pacific Gas & Electric [email protected] 805-801-3730 Business
Schucker, Christina PPL Susquehanna [email protected] 484-225-0664 IT
Zakarian, Adam PPL Susquehanna [email protected]
Alfieri, Jim PSEG Nuclear [email protected] 856-339-2125 IT
Bode, Mark PSEG Nuclear [email protected] 856-339-2739 Business
Sullivan, Penny SCANA [email protected] 803-941-9633 Business
Cashmore, Gordon Southern Co. [email protected] 205-992-6707 IT
Vaughan, Kent Southern Co. [email protected] 205-992-6540 Business
Smith, Stevan TVA [email protected] 423-751-2354 IT
Marcotte, Austin Wolf Creek Nuclear [email protected]
Ext. 8229IT
Nitsch, Tami Wolf Creek Nuclear [email protected]
Ext. 8206Business
Ellingson, Brian Xcel Energy [email protected] 612-321-3221 Business
Ernesti, Justin Xcel Energy [email protected] 612-330-7569 IT
Peterson, Wendy Xcel Energy [email protected] 651-267-6631 Business
15
Nuclear Primavera Users GroupIssues / Enhancement Requests (Business)
(Includes 2016 NPUG Meeting Updates)
Item # Description Ranking Primavera Response / Status Platform/Version Contact add date Bug # / SR # Oracle Comment
01 Additional Security around scheduling options
and users preferences
Need to address both Project and User
Security
Top 10 On roadmap for future
release.
7 SP1 K. Vaughan
rkvaugha@southernc
o.com
2013 SR 3-9877244491
Scheduling Options ER:
20046647
User Preferences ER:
20046595
02 Additional limit line on resources - needed for
resource leveling and for printed output
Top 10 Currently not planned. We
can explore this. Potentially
BI Pub workaround
7 SP1 K. Vaughan
rkvaugha@southernc
o.com
2013 3-6998059502
ER: 16581296
03 Make a new task type "isolated" (ie does not
need pred or succ)
Top 10 On roadmap for future
release
v8.3 F. Spindler
faye.spindler@nexter
aenergy.com
Pre-2013 SR#3-10194556721
3-7016757141;
Bug 16732193
04 Auto reorganize does not stay disabled - BUG Closed Bug 15949233
Fixed in P6R8.2.2 Pro
8.2 B. Stramel
Pre-2013 ER: 15949233 Todd Rozelle verified fixed in 8.3.1 and
15.2. Fixed in Release 16.1 D. Burnett
11/11/16
05 Use actual durations times update to calculate
actual hours used
Top 10 Currently not planned K. Vaughan
rkvaugha@southernc
o.com
Pre-2013 3-6998524321
ER: 11711290
06 Code tab for UDFs (like activity codes, so don't
have to add columns)
Top 10 Currently not planned. We
can explore this. Kpilla
22JAN15
P. Schmid
pamela.schmid@exelo
ncorp.com
Pre-2013 SR#3-13623993931
07 Batch report - resource histograms Top 10 This is possible in BI
Publisher. Enhancement for a
future release (KP)
All versions D. Burnett
Debbie.Burnett@duke-
energy.com
K. Vaughan,
Pam Schmid,
Todd Rozelle,
Debbie Burnett,
Tom Raymond
2013 SR# 3-8334705788
08 Ability to have a User Defined Relationship
Code (on Predecessors and Successors)
Top 10 J. Perry
2015 SR #3-10160780151
SR #3-10194990231
Bug 20441862
09 Level of Effort (LOE) Activities are being
actualized even though their Predecessors
and/or Successors have not started and/or
finished.
Closed T. Rozelle:
Todd.Rozelle@nextera
energy.com
2015 SR#3-8716553271 No longer seeing this issue. T.Rozelle
11/11/16
10 Compare two fields such as two date fields in
a UDF field. (filter critical dates in a UDF to the
current start date.)
Top 10 Enhancement for a future
release (KP)
v8.2.1 Larry Campbell,
Larry.Campbell@exelo
ncorp.com
2015 SR# 3-313623840411
11 Enhance Filter criteria - add "is not under", "is
within range", "Contains", "Greater than / less
than", "Does not contain" for activity codes
(similar to UDFs)
Closed On roadmap for future
release for EPPM and PRO
EPPM & Client M. Bode:
m
Pre-2013 Need SR# Added "contains", and "does not
contain".
16
Nuclear Primavera Users GroupIssues / Enhancement Requests (Business)
(Includes 2016 NPUG Meeting Updates)
Item # Description Ranking Primavera Response / Status Platform/Version Contact add date Bug # / SR # Oracle Comment
12 Resource histogram - be able to save a
resource with the layout (so don't have to re-
select resource every time you re-open
layout) Resource spreadsheet - cannot save
as a layout
Closed On roadmap for future
release
Client K. Vaughan
rkvaugha@southernc
o.com
Pre-2013 3-6998059471
ER: 16664788
Resource selections are now saved with
layout. T.Rozelle 11/11/16.
13 Export XERs and XML and copy of projects in
the background. From Pam Schmid (Item 34):
We need the ability to use job services to do
COPY project. On demand or scheduled
times.
Open Included in P6 8.4, 15.2 (KP)
for P6 web only
7.0 sp5 R. Vaughn
rkvaugha@southernc
o.com
2013 3-6762829951
ER 9073723
Is there a plan to have the ability to
schedule these jobs to run in the
background?
14 To be able to type in Activity ID of pred or
succ name instead of dialog box
Open Already in P6R8.X Client,
added to P6R8.4 (KP)
8.3 E. Adelman
ellen.adelman@duke-
energy.com
2014 Enhancement bug
18187855
Working in web but not in client per E.
Adelman 11/11/16
Enhancement was only added to P6
Web. Still an open enhancement for
client (KP 12/21/2016).
15 Missing columns in ver 8.2 pred / succ tabs in
web - i.e. need to see status of pred
Testing Added to P6R8.4 EPPM 6.2 J. Fisher
2013 S/R# 3-7972456571;
E/R# 17635820 submitted
to Oracle Product Strategy.
Included in P6 8.4 (KP)
John Fisher to verify
16 Page setup always resets to default settings
would be nice to have it save with project or
layout.
Testing Addressed in Visualizer in 8.3
(KP)
S. Hellriegel
om
Pre-2013 Need SR# Included in Visualizer 8.3 (KP)
17 Able to create an XER and attach baselines Closed Adding baselines to XML
exports is on the roadmap for
early 2015. We will not be
enhancing XER
import/export. Kpilla
22JAN15
7.0 sp5 S. Smith
2013 3-6762502763
Bug 12948511
.xml allow for mutiple baselines in 16.1
per S. Smith 11/11/16
18 Vertical sight lines - Need to be able to adjust.
Want to be able to specify when site lines
start
Closed Addressed in Visualizer in 8.3 J. Fisher
Pre-2013 Need SR# Included in Visualizer 8.3 (KP)
19 Using data date calculation in an excel filter
export produce no results.
UPDATE: Update from Development is this
Bug will be addressed in the next Service Pack.
Update date - 12/4/13
Closed Closed, Code/Hardware fix
verified Fixed in Product
Version 8.3.5.0
T. Rozelle:
Todd.Rozelle@nextera
energy.com
2013 SR 2-7138920, prim30081
UPDATE - 3-8134696691
Bug 9230617 Status 74 -
Confirmed fixed in 8.4.1 (T. Rozelle)
20 TSLD will not save bar colors for specific code
values
Open Addressed in P6 Visualizer J. Daws
TVA
2014 3-8071314641 TSLD bar colors are saved but not
always printed. Expecting patch from
Oracle. S. Smith 11/11/16
21 VISUALIZER: Ability to import/export layouts. Testing 23 - Scheduled for Future
Release
B. Normile
m
2015 18306151
3-10158884642
Included in P6 15.1 (KP)
17
Nuclear Primavera Users GroupIssues / Enhancement Requests (Business)
(Includes 2016 NPUG Meeting Updates)
Item # Description Ranking Primavera Response / Status Platform/Version Contact add date Bug # / SR # Oracle Comment
22 Ability to filter on Data Date (DD) or Current
Date (CD) in P6 Web.
Open Included in P6 15.2 (KP) Version 8 K. Vaughan
rkvaugha@southernc
o.com
2015 Idea #3662 Per T.Rozelle, I don't see either of these
options in the web DD or CD
Verified that this is working as design.
Filter is not on those fields but as a
criteria. Ex: Start Date is within range
of the DD to DD+2W (KP 12/21/2016).
23 Secure codes in copy projects - Need the
ability to retain secure codes when copying
/pasting or adding from a template.
Closed E/R# 16409848 6.2 J. Fisher
2013 E/R# 16409848;
S/R#3-7016470451;
Bug 16409848
T. Rozelle: Secure Codes including
Secure Project Codes are now copied
with the Project (Project Copy). I've
asked Oracle when this happened and
they were not sure SR 3-13167740981
Secure codes were included in Project
Copy in version 8.4. If the user has
access to view the codes, they will be
copied. If the user does not have access
to view the codes, they will not be
copied (KP 12/21/2016).
24 Use of F5 key does not refresh data in v15.1.6
Hot key to refresh filter
High Currently not planned. We
can explore this. Kpilla
22JAN15
v8.3 F. Spindler
faye.spindler@nexter
aenergy.com
Anna Nicholson
Anna.NICHOLSON@br
ucepower.com
2014 SR#3-11323205581
SR#3-10194230761
BUG#20481115
Originally identified in 2014. Still an
issue in 2015 and 2016.
Duplicate of IT #10 (KP 12/21/2016).
25 P6 EPPM 8.3 email for team member not
working (receiving connection time out), and
it's extremely slow to display assigned
activities **Improve filter capabilities for
team member (i.e. time filter)
Closed Is this still an issue? SR was
never completed. - kpilla
22JAN15
8.3 T. Raymond
tjraymond@firstenerg
ycorp.com
2014 SR 3-8224610521 Is this still an issue? SR was never
completed. - kpilla 22JAN15
Closed for now; FirstEnergy will test P6
Team Member again, following their
upgrade from P6R8.3 to P6R16.2, in July
2017. We will generate a new SR, if
necessary (TR 01/05/2017).
18
Nuclear Primavera Users GroupIssues / Enhancement Requests (Business)
(Includes 2016 NPUG Meeting Updates)
Item # Description Ranking Primavera Response / Status Platform/Version Contact add date Bug # / SR # Oracle Comment
26 P6 v7 SP4: When closing a P6 Project and
immediately opening a different project, the
closed project's Project Layouts are displayed.
The only way to see the current Project's
Project Layouts is to completely close P6 and
log back in.
High On roadmap for future
release. By Design: When
working with a project layout
and then open a different
project, the open layout
should remain. When the
user chooses to save the
layout, only the Save As
option should be available.
The Save option should not
be available, because this
layout was not saved for this
project before and would not
appear in the available layout
list when doing an Open
layout. - kpilla 22JAN15
6.7 SP4 K. Vaughan
rkvaugha@southernc
o.com
2014 SR 3-8263270183
27 Resource name not displayed when printing
resource usage profile
High On roadmap for future
release. Kpilla 22JAN15
8.3 B. Stramel
2014 Need SR#
Bug #?
This was addressed in version 16.2. If
more than 10 names need to appear,
the filter name will be used to address
readability concerns (KP 12/21/2016).
28 Scheduling log needs selectable options High On roadmap for future
release. Kpilla 22JAN15
J. Fisher
2014 S/R# 3-8383598741;
E/R# 18097367
29 Loop report does not display when loops are
present (SSFII-0822-6)
High v8.3.8 K. Vaughan
rkvaugha@southernc
o.com
2015 Bug #2056667.1 The bug number listed is not correct.
Can we get an update on this one (KP
12/21/2016)?
30 Run Layouts in batch format High All versions Todd Rozelle, Pam
Schmid,
2015 Enhancement for a future release (KP)
31 P6 EPPM 8.3 hotfix visualizer has stopped
working message. Works only with smaller
projects / Primavera response - memory
issues. Service pack 8.2 & 8.3. High priority
for 8.4.
Med Rewriting code for 64-bit
architecture; should be
addressed in P6R15.1
8.3 T. Raymond
tjraymond@firstenerg
ycorp.com
2014 SR 3-8187586261
Bug # 18078971
Improvements were made with 64 bit
Visualizer in 15.1 and additional
improvements are coming in 16.1. (KP)
Tom Raymond to test.
32 Users are unable to delete/modify layout
filters from project layouts unless given a
global profile option.
Med Issue has not yet been
addressed.
T. Rozelle:
Todd.Rozelle@nextera
energy.com
2013 Bug 8949912, defect
14014223
SR 3-6468513661 Type B -
Bug Status 52 - Pending
approval by PL
From Item #20: 3-
6762502741
Bug 16324777
Bug 16324777 is an enhancement for a
future release. (KP)
19
Nuclear Primavera Users GroupIssues / Enhancement Requests (Business)
(Includes 2016 NPUG Meeting Updates)
Item # Description Ranking Primavera Response / Status Platform/Version Contact add date Bug # / SR # Oracle Comment
33 User Interface View security does not prevent
updating of Activity Codes -
Description: Setting up User Interface Views
to manage field level security in Primavera
Web 8.2.1 does not prevent a user from
updating Activity Codes by going to the
"Codes" Tab in the Activity View. I want the
user to have access to update specific Activity
Codes so I only select specific codes in the
User Interface View. This work fine when
looking at the available columns in the activity
window. They only have access to update the
activity codes as defined in the User Interface
View. However the user can select the
"Codes" tab on the bottom of the activity
window and have full access to update any of
the Activity Codes and can even insert new
ones. The only Project Security Profile setting
that is active is "Add/Edit Activities Except
Relationships". Update from B. Gordon on
11/17/2014: "Tested in 8.3.5 and it is not
fixed."
Med Scheduled for an upcoming
8.2 Patch set. Kpilla 22JAN15
8.2.1 B. Gordon
m
2014 SR 3-8007038091
Bug: 17702966
Tested in version 15.2 and this issue has
been corrected. (KP)
Tested in 15.2.5 and this is still an issue.
User Interface View does not grant
access to “Chrg Type” as evidence
below by the gray column. Yet when
the user goes to the Codes tab they are
able to update the Chrg Type value
(Bruce Gordon 01/03/2017).
KP: Tested in 16.2 and can duplicate the
problem. I cannot added a new code
value to an activity but I can edit an
existing value. Waiting on new Defect
ID. (1/5/2017)
34 Ability to hide logic ties in the gantt chart for
specific activities (right click on the
relationship tie and select hide) (available in
V8)
Med By code to select which ones
not to show. Would have to
be implemented in Visualizer
for the future. Kpilla 22JAN15
6.2 K. Westbrook
Kim.Westbrook@bruc
epower.com
2014 3-8252080219
Bug 17968549 - ABILITY TO
HIDE RELATIONSHIP LINES
IN THE GANTT CHART FOR
SPECIFIC ACTIVITIES
35 Ability to line share in pert chart view Med On roadmap for future
release. Kpilla 22JAN15
8.3 E. Adelman
ellen.adelman@duke-
energy.com
2014 Need SR#
36 Desk top client view be able to optimize pert
chart across a chosen page size.
Med On roadmap for future
release. Kpilla 22JAN15
8.3 E. Adelman
ellen.adelman@duke-
energy.com
2014 Need SR#
37 Ability (user preference) to disable auto sort
function when clicking on column heading
(avoid unintentional re-sorting when moving a
column)
Med Currently not planned. K. Westbrook
Kim.Westbrook@bruc
epower.com
Pre-2013 BUG#: 16316865;
S/R# 3-6796378341
38 Be able to modify the "schedule risk" to
include On Line risk for example PRA,
Industrial Safety, Radiological Risk,Production
Risk
Closed On roadmap for future
release
M. Bode
m
Pre-2013 Need SR# No longer needed M. Bode 11/11/16
20
Nuclear Primavera Users GroupIssues / Enhancement Requests (Business)
(Includes 2016 NPUG Meeting Updates)
Item # Description Ranking Primavera Response / Status Platform/Version Contact add date Bug # / SR # Oracle Comment
39 Resource ID is not available for filtering in web Med Currently not planned. We
can consider for future. This
can be filtered in the
resource assignments screen.
P6 R8 now has a Resource
Assignments view that
features robust filtering
options
7.0 sp5 R. Lewis
Pre-2013 Doc ID 912007.1
40 Display budgeted quantity in a column Closed Please provide more
information.
7.2 C. Buckley:
m
2013 Need SR# No longer needed M. Bode 11/11/16
41 Admin functions back in client Closed The following items will be
available in the next release
of P6 Client: EPS, OBS, Project
Codes, Activity Step
Templates, Cost Accounts,
Funding Sources. Kpilla
22JAN15
M. Davis
2013 Need SR# The following items are available in P6
15.1: EPS, OBS, Project Codes, Activity
Step Templates, Cost Accounts, Funding
Sources. (KP)
All of the items lists are available in P6
client now (this is in 16.1). I can’t
confirm if they were in 15.1 or 15.2, but
certainly in 16.1 which is the version we
at Duke are implementing (from Ellen
Adelman 12/21/2016).
42 Creation of target dates in a project. Med Currently not planned. We
can explore this.
J. Fisher
2013 3-7016998631
Bug 16725638
43 Ability to kick people out of project Med On roadmap for future
release. Version 8.4 Web
added the ability to see users
logged into a project and
email them. Kpilla 22JAN15
6.2 J. Fisher
2013 Need SR#
44 Edit MS project templates - Security similar in
excel
Med On roadmap for future
release. Kpilla 22JAN15
K. Westbrook
Kim.Westbrook@bruc
epower.com
2013 3-6796378356
SR 3-1984677521;
enhancement req 9965302
21
Nuclear Primavera Users GroupIssues / Enhancement Requests (Business)
(Includes 2016 NPUG Meeting Updates)
Item # Description Ranking Primavera Response / Status Platform/Version Contact add date Bug # / SR # Oracle Comment
45 EPS Code assignments are not being present
after import of an XER due to inter-project
ties
Med This functionality currently
exists with XML
Import/Export. We do not
have
any plans to enhance the XER
Import/Export feature.
kpilla22JAN15
T. Rozelle:
Todd.Rozelle@nextera
energy.com
2013 SR 3-5883209591;
bug 14250335 Status 97
*** 08/18/14 07:24 am ***
T. Rozelle recommends removing from
list based on the future of XER's.
Suggestion Rejected This functionality
currently exists with XML
Import/Export. We do not have
any plans to enhance the XER
Import/Export feature.
46 Update baseline feature not working properly Closed Per SR, this issue was
resolved. Kpilla 22JAN15
T. Rozelle:
Todd.Rozelle@nextera
energy.com
2013 SR 3-5037851591 Per SR, this issue was resolved. Kpilla
22JAN15. Close per T. Rozelle
11/11/16.
47 Copy project based on filter activities only Closed This is not planned. T. Rozelle:
Todd.Rozelle@nextera
energy.com
2013 Need SR# T. Rozelle recommends removing from
list. Close per T. Rozelle 11/11/16
48 Time scale on web - need to be able to select
day/hr
Med On roadmap for future
release
2013 Need SR# Team Usage in P6 16.1 will include a
daily timescale, other resource charts
will be changed in future releases. (KP)
All resource charts in P6 Web now
support a week/day timescale in
version 16.2 (KP 12/21/2016).
49 Compare two projects without converting to
baseline
Closed On roadmap for future
release
D. Howard
m
2013 Need SR# T. Rozelle recommends removing from
list. Close per T. Rozelle 11/11/16
50 Add time/date of activities to Loop Report Med On roadmap for future
release
v8.3 F. Spindler
faye.spindler@nexter
aenergy.com
2015 SR#3-10194556736
BUG#14738935
51 Provide a way to select which notebook topics
to copy in a Project Copy or during an XML
export
Med T. Rozelle:
Todd.Rozelle@nextera
energy.com
2015 SR 3-11230735801
52 Display logic and resource histograms at the
same time
Med v8.2.1 Larry Campbell,
Larry.Campbell@exelo
ncorp.com
2015 Need SR# Need more information (KP)
53 Activity code hirearchy prints even though UP
start up filter select to current project radial
Low Need more information 8.3 L. McClure
om
2014 Need SR#
22
Nuclear Primavera Users GroupIssues / Enhancement Requests (Business)
(Includes 2016 NPUG Meeting Updates)
Item # Description Ranking Primavera Response / Status Platform/Version Contact add date Bug # / SR # Oracle Comment
54 If using grouping bands and an activity code is
not assigned do not show that grouping band.
(Provide a show or hide exception box)
Closed P6 Web and Client have the
ability to hide if a group band
is empty. Kpilla 22JAN15
J. Fisher
Pre-2013 Need SR# P6 Web and Client have the ability to
hide if a group band is empty. (KP)
Yes, this can be addressed by a filter.
The original request I believe was to
add a check box that would
automatically reject the group “No
XXX” from reports when printing.
But the right thing to do is to reject
them when filtering your selection
(John Fisher 12/21/2016).
55 Time sheet selection to not allow tasks to pull
forward
Low V. Laskey
Vickie.Laskey@dteene
rgy.com
2014 Need SR#
56 Dissolve activity relationship feature to work
for more then one activity at a time (available
in V8)
Low On roadmap for future
release. Kpilla 22JAN15
6.2 K. Westbrook
Kim.Westbrook@bruc
epower.com
2014 3-8252080211
Bug 8951053 :
P6E_CTEB503-P6E:
DISSOLVE FEATURE TO
WORK WITH MULTIPLE
ACTIVITIES
57 P6 v7 SP4: When setting up WBS security
end users who should have the ability to
copy/paste tasks cannot. They can edit other
fields but cannot copy/paste.
Low Is this still an issue? SR was
never completed. Kpilla
22JAN15
K. Vaughan
rkvaugha@southernc
o.com
2014 SR 3-8263440041
58 Primavera/Time scale logic diagrams -
problems after upgrading to Windows 7
Low Two issues were reported:
13801882 - P6 DIALOGS TO
RESIZE WITH LARGER
WINDOWS DISPLAY SETTINGS
- Enhancement
17553297 - TSLD 'SHOW TILE
BLOCKS' CHECK BOX IS
HIDDEN WHEN USING
WINDOWS 7 THEME - issue
was not resolved, customer
did not respond to Support
kpilla 22JAN15
K. Vaughan
rkvaugha@southernc
o.com
2014 SR 3-8359323311
59 Export resource to spread table to CSV Low Please provide more
information.
D. Burnett
Debbie.Burnett@duke-
energy.com
2013 Need SR#
60 Display lag in a column Low This is not planned, but lag
can be displayed on
relationship lines in Visualizer
in 8.3
NGH
M. Davis
2013 Need SR# Will be included in P6 16.1 (KP)
Reference email dated 11/9 from Karen
with a proposed solution. Check to see
if she needs additional information.
Included in 16.1 (KP 12/21/2016).
23
Nuclear Primavera Users GroupIssues / Enhancement Requests (Business)
(Includes 2016 NPUG Meeting Updates)
Item # Description Ranking Primavera Response / Status Platform/Version Contact add date Bug # / SR # Oracle Comment
61 Auto messaging out of P6 Low Please provide more
information.
6.2 J. Fisher
2013 Need SR#
62 P6 Claim Digger has no selection capability:
Description - P6 Claim Digger runs on the
entire project. This may work for smaller
projects, but for larger projects the user needs
to be able to select a subset of the project
(like a WBS or other codes).
Low No future enhancements are
planned
J. Fisher
2014 SR #3-8220843651
enhancement request
BugDB:17933884
Claim Digger is being re-written for
version 16.1 and will be included in
Visualizer as a new report. After the re-
write, we may have the ability to add
new functionality in the future. (KP)
63 Claim Digger shows new relationships on
activities with multiple pred and succ
Low Addressed in P6R8.1.3 7 SP5 J. Daws
TVA
2014 8949555
64 Baselines don't finish Low B. Stramel
2015 Need SR# 8.3.1
65 Attaching a baseline causes extended Refresh
times for other users in the project.
Low P. Schmid
pamela.schmid@exelo
ncorp.com
2015 SR #3-13623840427 SR # was provided 12/21/2016 (TR
01/05/2017).
KP: Customer Support is working on
this. (1/5/2017)
66 Find feature in P6EPPM does not work well;
needs enhancement
Low B. Gordon
m
2015 Need SR#
67 VISUALIZER: Ability to set ordinal date start. Low 15 - Enhancement Req.
Internal (Oracle) Review
B. Normile
m
2015 20455815
3-10158884564
8.3.2
68 VISUALIZER: Ability to have curtains for
resource shifts.
Low 15 - Enhancement Req.
Internal (Oracle) Review
B. Normile
m
2015 20448149
3-10158884501
8.3.2
69 VISUALIZER: Custom date in timescale tab of
visualizer foes not allow 24 hr clock.
Low 15 - Enhancement Req.
Internal (Oracle) Review
B. Normile
m
2015 20447407
3-10159293804
8.3.2
70 VISUALIZER: Ability to use a find feature to go
to an activity on diagram.
Low 15 - Enhancement Req.
Internal (Oracle) Review
B. Normile
m
2015 20445419 8.3.2
71 VISUALIZER: Ability to set text colors for each
bar.
Low 15 - Enhancement Req.
Internal (Oracle) Review
B. Normile
m
2015 20440657
3-10158884518
8.3.2
72 VISUALIZER: Ability to switch layouts without
closing project.
Low 22 - Approved for Future
Release
B. Normile
m
2015 20403941
3-10158884608
8.3.2
73 Ability to share a filter to a list of users
grouped by profile.
Low v8.3 A. Marcotte
m
2015 SR#3-10194556736
BUG#20480040
Enhancement for a future release (KP)
74 Loop Report in P6 Web is not userful to
diagnose loops
Low v8.3.8 K. Vaughan
rkvaugha@southernc
o.com
2015 SR#3-11549395181
SR#3-11435129041
Enhancement for a future release (KP)
24
Nuclear Primavera Users GroupIssues / Enhancement Requests (Business)
(Includes 2016 NPUG Meeting Updates)
Item # Description Ranking Primavera Response / Status Platform/Version Contact add date Bug # / SR # Oracle Comment
75 Change the sort order on the relationship tab
to provide multiple sorting
Low v8.2.1 Larry Campbell,
Larry.Campbell@exelo
ncorp.com
2015 Need SR# Enhancement for a future release (KP)
76 Project Layouts are no longer copied. Since
going to job services when a Project is copied
it’s Project level layouts are not copied. Oracle
says it will put back in a major release 2017
New v15.2 T. Rozelle:
Todd.Rozelle@nextera
energy.com
2016 Bug 23074946 Planned for next on premise release –
version 17 (KP 12/21/2016).
77 When a Project is copied some scheduling
options change. If you change the default
settings in Scheduling options, some of them
will revert back to the defaults in a copy. E.g.
progress override will change back to retained
logic in the copy
New v15.2 T. Rozelle:
Todd.Rozelle@nextera
energy.com
2016 SR 3-13266512841; Bug
24666700
KP: Scheduled to be fixed in an
upcoming 16.2.4 patch set. (1/5/2017)
78 Copy of Project appears before copy is
complete. One of the first steps in the Copy
process appears to be copying the Project
ID/Name. For a Copy that might take 15
minute to complete i.e. receive the job service
complete notification, the Project is already
visible in the client, typically within a minute.
New v15.2.9 T. Rozelle:
Todd.Rozelle@nextera
energy.com
2016 SR 3-13201681031, Bug
24500309
KP: Scheduled to be fixed in an
upcoming 16.2.4 patch set. (1/5/2017)
79 This release seems more sensitive to
orphaned records. We thought it was the root
of all evil for a while. Still not clear how bad
the impact is but be prepared to occasionally
clean them up
New v15.2.7 J. Fisher
2016
80 Float values don’t calculate correctly when
using a constraint type = ALAP. (Client)
New v15.2.7 J. Fisher
2016 Bug: 24906866 KP: Scheduled to be fixed in an
upcoming 15.2.13 patch set. (1/5/2017)
81 Hide if empty in grouping band option is
disabled (Web)
New v15.2.7 J. Fisher
2016 Bug #23008333 KP: Fixed in 15.2.6 (1/5/2017)
82 Calculate function (F9) is not recalculating
total float for certain activities.
New v15.2.7 J. Fisher
2016 SR# 3-13476511291 KP: Duplicate of Row 80
83 Can’t schedule projects in the P6 Web. It
updates (changes) the DataDate in unrelated,
unopened Projects
Closed 11/11 - Confirmed fixed in
version 15.2.11 by J Fisher
v15.2.7 J. Fisher
2016 various
84 Focus bar is dark blue and checkbox is black.
(Client) Cannot see whether the checkbox is
selected
Closed 11/11 - Confirmed fixed in
version 15.2.11 by J Fisher
v15.2.7 J. Fisher
2016 various
25
Nuclear Primavera Users GroupIssues / Enhancement Requests (Business)
(Includes 2016 NPUG Meeting Updates)
Item # Description Ranking Primavera Response / Status Platform/Version Contact add date Bug # / SR # Oracle Comment
85 WBS Groupings in the Projects view auto
expand and will not stay compressed (Client)
Closed 11/11 - Confirmed fixed in
version 15.2.11 by J Fisher
v15.2.7 J. Fisher
2016 various
86 Unable to save settings for Reports. Time
Distributed Data checkbox will not save with
the report
Closed 11/11 - Confirmed fixed in
version 15.2.11 by J Fisher
v15.2.7 J. Fisher
2016 various
87 Cannot delete a Project from the Web Closed 11/11 - Confirmed fixed in
version 15.2.11 by J Fisher
v15.2.7 J. Fisher
2016 various
88 Cannot open a report in a CSV (Client). Get an
error “Windows cannot open this file”
Closed 11/11 - Confirmed fixed in
version 15.2.11 by J Fisher
v15.2.7 J. Fisher
2016 various
89 Unable to Add Variables to Layout Headers
And Footers in P6 Professional Client
Closed 11/11 - Confirmed fixed in
version 15.2.11 by J Fisher
v15.2.7 J. Fisher
2016 various
90 Buttons partly hidden in bottom layout.
(Client)
Closed 11/11 - Confirmed fixed in
version 15.2.11 by J Fisher
v15.2.7 J. Fisher
2016 various
91 PRINTING TO PDF IN VISUALIZER CUTS OFF
RIGHT SIDE (INCOMPLETE PRINT JOB) on E
Size Printout
New R16.2 D. Maynard
David.Maynard@dom.
com
12/20/2016 SR 3-13663235221 BUG
24567242
Our teams are actively working on a
solution for this. Testing with Dominion
(KP 12/21/2016).
92 Header/footer did not show on several
layouts (letter/landscape & legal/landscape).
New R16.2 D. Maynard
David.Maynard@dom.
com
12/20/2016 SR 3-13848796731 Support is actively working on this (KP
12/21/2016).
93 Primavera Visualizer Draw and Print Preview
Do Not Match
New R16.2 D. Maynard
David.Maynard@dom.
com
12/20/2016 SR 3-13500205541 Appears to be related to Item #91
(KP12/21/2016).
94 Primavera Visualizer R16.2 On Citrix Crashes
When Doing Print Preview
New R16.2 D. Maynard
David.Maynard@dom.
com
12/20/2016 SR 3-13541343951 SR was closed due to inactivity. If this is
still an issue, please reopen (KP
12/21/2016).
95 Confusing Bar Text Layout New R16.2 D. Maynard
David.Maynard@dom.
com
12/20/2016 SR 3-13554426771 Enhancement Idea #16114: Bar Labels
Drawn Next to Each Bar Rather Than
the Right-Most Bar (KP 12/21/2016).
96 P6 Exception when committing changes New R16.2 D. Maynard
David.Maynard@dom.
com
12/20/2016 SR 3-13793067261 Support is actively working on this (KP
12/21/2016).
97 P6 Projects Only New R16.2 D. Maynard
David.Maynard@dom.
com
12/20/2016 SR 3-13781443891 Support is actively working on this (KP
12/21/2016).
26
Nuclear Primavera Users GroupIssues / Enhancement Requests (Business)
(Includes 2016 NPUG Meeting Updates)
Item # Description Ranking Primavera Response / Status Platform/Version Contact add date Bug # / SR # Oracle Comment
98 Visualizer Print Preview Crashes App New R16.2 D. Maynard
David.Maynard@dom.
com
12/20/2016 SR 3-13332886401 SR is closed with a resolution. Is this
still an issue (KP 12/21/2016)?
99 (P6 App Issue) Can't edit or copy Activity IDs in
Pred/Succ columns.
New R16.2 D. Maynard
David.Maynard@dom.
com
12/20/2016 SR 3-13564888781 Duplicate of Item #14 (KP 12/21/2016).
100 (P6 App Issue) Baseline copy function failed New R16.2 D. Maynard
David.Maynard@dom.
com
12/20/2016 SR 3-13536215071 SR was closed due to inactivity. If this is
still an issue, please reopen (KP
12/21/2016).
101 In Client: When opening a Project, the
previously saved layout for the Project should
open, instead of the layout from a previously
opened different Project. At least the option
should be provided for the User.
New R8.4 D. Maynard
David.Maynard@dom.
com
12/20/2016 EVALUATE Duplicate of Item #27 (KP 12/21/2016).
102 In Client & Web: Predecessor & Successor
columns in "Layout View", should also provide
"Completed" indication with the ID#. User
should be allowed to turn this feature on or
off.
New R8.4 D. Maynard
David.Maynard@dom.
com
12/20/2016 EVALUATE
103 In Client & Web: Predecessor & Successor
columns in "Layout View" should also provide
the Lag Type & Lag duration with the ID#.
User should be allowed to turn this feature on
or off.
New R8.4 D. Maynard
David.Maynard@dom.
com
12/20/2016 EVALUATE
104 In Client: A "Multi-select" icon should be
provided to assign a specific WBS (similar to
the icons for Activity Codes, Steps, Pred's,
succ's, etc.)
New R8.4 D. Maynard
David.Maynard@dom.
com
12/20/2016 EVALUATE
105 In Client: Notebook: should contain an "auto-
fit" option in the Gantt Chart. (Manual sizing
of Notebook topic text is time-consuming)
New R8.4 D. Maynard
David.Maynard@dom.
com
12/20/2016 EVALUATE
106 In Client & Web: Steps: In Layout View, Steps
should be displayed under each assigned Task,
in an indented fashion. The attributes (Status,
%, Weight, etc.) of each step should also be
displayed.
New R8.4 D. Maynard
David.Maynard@dom.
com
12/20/2016 EVALUATE
107 In Client & Web: Steps: "Auto-numbering" of
Steps should be provided as each (additional)
Step is added to a task. Step ID is useful when
numerous steps are assigned to each task.
New R8.4 D. Maynard
David.Maynard@dom.
com
12/20/2016 EVALUATE
27
Nuclear Primavera Users GroupIssues / Enhancement Requests (Business)
(Includes 2016 NPUG Meeting Updates)
Item # Description Ranking Primavera Response / Status Platform/Version Contact add date Bug # / SR # Oracle Comment
108 In Client & Web: Predecessors & Successors:
On "Customize Activity Details" Activity Code
columns should be added, as display options.
New R8.4 D. Maynard
David.Maynard@dom.
com
12/20/2016 EVALUATE
109 In Client: Timescale: When 3 lines are selected
in timescale format, the Date Format Type
should display 3 levels of options instead of
just 2 (i.e. Year/Month/Week)
New R8.4 D. Maynard
David.Maynard@dom.
com
12/20/2016 EVALUATE
110 In Client & Web: Predecessors & Successors:
When selecting "Assign" the window displays
1 of 3 "Column" options (Status, Date,
Resource). Add Activity Codes as an Option &
allow User to select which code fields to be
displayed as columns in the "Assign" window.
New R8.4 D. Maynard
David.Maynard@dom.
com
12/20/2016 EVALUATE
111 In Client & Web: Shared Mode message:
When attempting to calculated the Schedule,
on occasion, a "Shared Mode message will
appear. The message should be enhanced to
include the Name or ID of the other User(s)
who are in the Project.
New R8.4 D. Maynard
David.Maynard@dom.
com
12/20/2016 EVALUATE
112 In Client & Web: Shared Mode message:
When attempting to calculated the Schedule,
on occasion, a "Shared Mode message will
appear. If the same user is the only User in
both the Client & Web Project, there should
be no reason for the message.
New R8.4 D. Maynard
David.Maynard@dom.
com
12/20/2016 EVALUATE
113 In Client & Web: Filters: A report should be
provided which identifies the criteria used for
each filter.
New R8.4 D. Maynard
David.Maynard@dom.
com
12/20/2016 EVALUATE
114 In Client & Web: Filters: If 2 or more filters
contain identical criteria (except title), they
should be identified so that Users can
minimize duplicate Filters.
New R8.4 D. Maynard
David.Maynard@dom.
com
12/20/2016 EVALUATE
115 In Client & Web: Filters: The ID (name) & date
a Filter is created or modified should be
displayed, along with the Filter name in the
Filter list.
New R8.4 D. Maynard
David.Maynard@dom.
com
12/20/2016 EVALUATE
116 In Client & Web: Group & Sort By: Along with
Color & Font editing, "Pattern" should be
added as an option for background.
New R8.4 D. Maynard
David.Maynard@dom.
com
12/20/2016 EVALUATE
28
Nuclear Primavera Users GroupIssues / Enhancement Requests (Business)
(Includes 2016 NPUG Meeting Updates)
Item # Description Ranking Primavera Response / Status Platform/Version Contact add date Bug # / SR # Oracle Comment
117 In Web: Activities View: Columns only display
Activity Code Value descriptions. Need the
ability to select Code Value ID as an option.
New R8.4 D. Maynard
David.Maynard@dom.
com
12/20/2016 EVALUATE
118 In Web: ALL Column Views: Need "Auto-fit"
option, so that each column does NOT need to
be manually expanded or compressed.
New R8.4 D. Maynard
David.Maynard@dom.
com
12/20/2016 EVALUATE
119 In Web: Activities View: Add "Curtain" option
in Timescale. (Client has it)
New R8.4 D. Maynard
David.Maynard@dom.
com
12/20/2016 EVALUATE
120 In Web: Sometimes Web actions are
extremely slow & there is no indication that
the system is proceding to the next selected
option. Need an enhancement here.
New R8.4 D. Maynard
David.Maynard@dom.
com
12/20/2016 EVALUATE
121 The ability to set defaults for the User
Preferences is not available in P6. This
actually created a problem with our Asset
Suite to P6 interface for downloading Work
Order resources.
New R16.1 E. Adelman
Ellen.Adelman@duke-
energy.com
01/05/2017 Bug 11784737
29
This page was intentionally left blank as a spacer.
Use for notes.
30
Nuclear Primavera Users GroupIssues / Enhancement Requests (IT)
(Includes 2016 NPUG Meeting Updates)
Item # Description Ranking Primavera Response / Status Platform/Version Contact add date Bug # / SR # Oracle Comment
1 Need a user function (admin function) in order
to mark users for delete to end their session
so they can get back in to the application (web
and client sessions)
Top 10 On roadmap for future
release
8.2 / Oracle R. Turpin
Raeann.Turpin@exelo
ncorp.com
2013 Bug 8951196
Doc ID 8913288.1 - for sql
but is not a user function
2 Need a way for an admin application user to
reset a default web and/or client view when a
view has locked up a user profile.
Top 10 On roadmap for future
release
8.2 / Oracle R. Turpin
Raeann.Turpin@exelo
ncorp.com
2013 Doc ID 894279.1 - for sql
but is not a user function
3 Printing in the web is not easy without getting
the gantt chart
Top 10 This was fixed in 8.3, but
broken again in 8.4
8.2 SP2 /Oracle B. Gordon
m
2014 Doc ID 912490.1 - needs to
be tested
This is fixed in P6 15.2 (KP)
4 There is a 'memory leak' in Job Services
(Weblogic).
Top 10 Oracle reported this was fixed
in 8.3 but the issue is still
being seen in 8.3
If still an issue, please re-open
SR. kpilla 22JAN15
Marcotte Austin L
m
2015 3-10044707061 - Per SR,
settings were changed and
issue has not repappeared.
3-9133241241 - Bug
18833580, fixed in 8.2.4,
Bug 17854592, fixed in
8.3.1.5.
3-8246020979 - SR was
closed due to note that the
customer worked around
the issue.
3-8226243791 - SR notes
state the customer resolved
by deleting a hung
publication.
SR3.11255320611 (new SR)
Note 1357440.1 - need to 5 Provide a method for users to identify UDF's
and Activity Codes , where they are used, and
who uses them
Top 10 This should be addressed In a
future release; after P6R15.2
6.2.1 / Oracle C. Lawrence
Christina.Lawrence@n
ee.com
2013 Doc ID 1391703.1
6 Visulizer - Project opens but a layout can take
up to 20 mins to open
Top 10 Oracle says fixed in 16.1 15.1 G. Cashmore 2015 SR# ?
Oracle says it is based on
the number of activity
codes in the DB and needs
to be indexed
7 Make delete project and delete baseline an
option for scheduled jobs
Top 10 15.2 R. Turpin
Raeann.Turpin@exelo
ncorp.com
2015 Need SR#
8 Logs no key' as a message in the log file when
a job fails and this message is worthless. Need
a better message that provides more
information
Top 10 15.2 G. Cashmore
gfcashmo@southernc
o.com
2015 SR# 3-11697545551 KP: SR indicates that this issue is closed.
(1/5/2017)
9 Neet to be able to re-open an SR after it has
been closed
Top 10 - R. Turpin
Raeann.Turpin@exelo
ncorp.com
2015 Need SR#
31
Nuclear Primavera Users GroupIssues / Enhancement Requests (IT)
(Includes 2016 NPUG Meeting Updates)
Item # Description Ranking Primavera Response / Status Platform/Version Contact add date Bug # / SR # Oracle Comment
10 Data not refreshing for other users after
committing to database
Multiple reports of users not seeing changes
made in projects when opened by
other users.
Top 10 Is anyone not using an Oracle
database for 8.3.1, had
problems with data not
refreshing for multiple users
after changes are committed
to the database. We have
reported it to Oracle Bug
17904646 and their answer
for now is to get out of the
project and out of the
software and then get back
in. It does work but very time
consuming in an outage. I’m
not sure if they are actively
working to resolve it.
Oracle - Fixed in 15.2.3 but
Oracle has not found the
exact cause
8.3.1 L. Bremer:
2014 SR 3-9753305851
Bug 17904646
Workaround (Ctrl+Shift+F5) was added
in the following versions: 8.3.9.0,
8.4.6.0, and 15.1.3.0, 15.2.1.
Still investigating root cause (KP)
Is this still an issue? In April, our lead
P6 Developer worked closely with
Southern Co. and found that this issue
could related to a process to clean the
REFRDEL table. Their process was to
clean out this table every 2 hours,
during worktime. This would explain
why a user that tries to refresh might
never pick up all of the relationship
deletions, if the REFRDEL deletion
occurred before the user refreshed. At
that time, we recommended that they
set the REFRDEL cleanup settings to
always keep the last 4 hours worth of
deletion data. They did not want to set
the keep interval to anything longer as
they said that they would run into
performance issues if REFRDEL got too
big (KP 12/21/2016).
11 Memory Leak eventually causes PM.exe to
crash. In the 32 bit version, successive F9’s use
memory that is not released eventually
causing out of memory error. Closing the
Project does not regain the memory. You have
to close P6.
New 11/17 - Oralce will fix in
15.2.12.0 due out the in first
week of December T Rozelle
v15.2 T. Rozelle:
Todd.Rozelle@nextera
energy.com
2016 SR 3-13334020841
12 Can’t auto schedule Projects using Job
Services. It updates (changes) the DataDate in
unrelated, unopened Projects
New v15.2.7 J. Fisher
2016 SR# 3-12948334941 Fixed in 15.2.11 (KP 12/21/2016).
13 Cannot copy large Projects (Client) New v15.2.7 J. Fisher
2016 SR# 3-12893435876 SR is closed. Issue seemed to be
related to orphan records. If this is still
an issue, please reopen SR (KP
12/21/2016).
14 Cannot run Baselines in large projects (Client) New v15.2.7 J. Fisher
2016 Bug #22926325 Fixed in 15.2.8.1 (KP 12/21/2016).
15 Security gets corrupted and you have to
rebuild the OBS table to correct it (Client)
Closed 11/17 - Confirmed fixed in
15.2.9 by R Turpin and Oracle
v15.2.7 J. Fisher
2016 Bug #23028727
32
Nuclear Primavera Users GroupIssues / Enhancement Requests (IT)
(Includes 2016 NPUG Meeting Updates)
Item # Description Ranking Primavera Response / Status Platform/Version Contact add date Bug # / SR # Oracle Comment
16 Cannot copy a Project in the Web Closed 11/17 - Confirmed fixed in
15.2.11 by J Fisher
v15.2.7 J. Fisher
2016
17 Significant number of AVAA0 errors when
users are trying to print layouts in the Client
New v15.2.7 J. Fisher
2016 SR# 3-13367760245 Support is attempting to reproduce and
is waiting for APS database (KP
12/21/2016).
18 Installed Firefox as the browser for the P6
Web. Couldn’t overcome java conflicts with
IE11.
New v15.2.7 J. Fisher
2016
33
NPUG Issues and Enhancements 'Recommended for Removal'
Item # Description Primavera Response Platform Version
Contact Bug # / SR #
1 Put exports and batch reporting back in job services. They need to be ran from a command line starting in 8.1. Update from D. Ellis on 11/14/2014: "Hi Tom, I got a response from Oracle regarding my SR you can delete it from the list or you can put resolved with version 8.4 here is the information https://docs.oracle.com/cd/E54700_01/client_help/en-us/index.html. If you go to tools you will see that job services is back in guess I have to load 8.4 on the new dev to check it out!"
On roadmap for future release 8.1 / Oracle D. Ellis SR 3-9875894231 (provided by D. Ellis on 11/14/2014).
23 Gantt chart bar labels to stay on printable part of sheet as opposed to running off the page. Recommendation from B. Gordon on 11/17/2014: "Remove, Addressed in Visualizer".
Addressed in Visualizer in 8.3 E. Adelman 3-8334589851 BUG 13714539
41 Display notebook topics on bar chart (format text or memo). Limit on row or width
Addressed in Visualizer in 8.3. Additional feedback from B. Gordon on 12/02/2014: "Item 41 should be closed. Fixed in Visualizer. As an alternative you can use "Notes to Resources" instead of Notebook Topics and it displays in the Gantt chart area."
K. Vaughan 3-6998524337Closed to below bugs:Bug 9553164Bug 8950831
36 Auto row height / Optimize row height Addressed in Visualizer in 8.3 & available in BI Publisher. This is on the roadmap for the web.
K. Wulf-Stewart
72 Allow EPS and Project level UDFs We have project level UDFs. EPS UDFs are on the roadmap for a future release.
J. Fisher
34
NPUG Issues and Enhancements 'Recommended for Removal'
Item # Description Primavera Response Platform Version
Contact Bug # / SR #
74 In the web you have to select ID or Activity Description as first column. (Monty Clark has additional input)
On roadmap for future release J. Fisher
43 In Layout Header / Footer , dialog parameters for example data date + number of days or a specific date
This is on the Visualizer roadmap post R8.3
A. Powell
45 Team usage in the web - there is no way to filter to projects or protfolios. It shows rexource usage for every project unless it is a "what if" project
On roadmap for future releaseTeam Usage only displays usage for the currently open and selected project. The Resource Analysis view allows you to filter on projects. (KP)
J. Fisher
8 Would like to have a way to pull down the database with global data (EPS structure with calendars, codes, etc), but not projects. In order to create another database environment for users to test.
On roadmap for future releaseThis is addressed in P6R8.4 via Gateway
C. Lawrence
11 When coping a project have options. (for example, not copy UDF's, notebook topics, activity codes, etc)
These options are now available 8.x and beyond when using XML
6.2.1 / Oracle
C. Lawrence
21 JAVA incompatibility issues resulting from all the variuos versions. Goal is to get JAVA out of the mix and use HTML.
This is being done by Oracle but will be a long process. Some java components have been removed in 15.1 and more in 15.2 and will continue on future releases
R. Turpin
35
NPUG Issues and Enhancements 'Recommended for Removal'
Item # Description Primavera Response Platform Version
Contact Bug # / SR #
7 When turning on auditing at the table level in the settings able the audit table will actually track tables that are not in the list. (Turned on the resource table and prmaudit was showing audits for users and udfvalue). This in turn will cause the audit tables to fill up and affect performance.
On roadmap for future release 8.2 /Oracle R. Turpin Doc ID 913176.1 - states this has been fixed in 7.0 and above, but problem still exists in 8.2
9 Automatically delete baselines - ability to flag a baseline to be deleted or have a service that runs to clean up baselines (available in V8)
Enhancement request 17969143 has been submitted to Oracle Product Strategy for consideration as new functionality in a future releaseThis should be addressed In a future release; after P6R15.2 .
6.2 K. Westbrook 3-8252051071Enhancement request 17969143
14 Ldap configurations change automatically without user intervention
Bug?Reportedly fixed in P6R8.2.3 Issue not repeatable in 15.1.3 - confirmed by G.Cashmore
8.2 SP2 HF1/Oracle
G. Cashmore SR 3-8368335411Bug 13965737Doc ID 1592843.1
15Copy Paste from Screen Layouts extremely slow. Not efficient enough to perform duties
Issue: Development working on it. Not knows if will be HF or Bug fixReportedly fixed in P6R8.1.3.4
8.2 SP2 HF1/Oracle
G. Cashmore SR 3-8052905331 Bug 17921571Doc ID 1501639.1
13 Need to see better performance when coping large projects
Coming to P6 EPPM in a future release, can run as a Background Job in P6R8.4 web Confirmed it runs as a background job in 15.1, but no performance improvement - confirmed by G.Cashmore
8.2 / Oracle R. Turpin Doc ID 2057235.1 - runs as on-demand but can not be scheduled
36
NPUG Company Software List
Company Name Sites# of Sites
# of Units
Current Version
Client, Web or Both
Upgrade Plans in Next 12 Mths
Analytics BI PublisherTeam
MemberVisualizer
Other Products(Earned Value Mgmt, Unifier, Risk Analysis,
etc.)
DBMS Oracle or SQL
Server
Largest Project Activity Count
Work Management Tool
WM Scheduling Interface
Risk Management Tool
Tagging Permitry
Other Software Last UpdatedUpdated Provided
By
Ameren UE Callaway (1) PWR 1 1 P6r8.3.12 both none work in progress yes yes Oracle 14000 EMPRV homegrown manual or P6 web EMPRV 9/1/2016 Jeff Perry
Arizona Public Service Co. Palo Verde (3) PWR 1 3 P6r15.2.5 BothP6v15.2.11 +
patchesno
Yes (Implementing)
Yes, limited access
yes no Oracle 24,000 SWMS Homegrown EOOS/Paragon SWMSKnowledge Relay, Business Objects, Acumen Fuse, QlikView, Hard Dollar, Syntempo
11/3/2016 John Fisher
Bruce PowerBruce A (4) CANDU, Bruce B (4) CANDU
1 8 P6r15.1 Both Yes Oracle 54,000 Passport V10 NextAxiom ARM/EOOS Passport Cognos 9/6/2016Angela Gowan
Exelon NE(ex Constellation)
Calvert Cliffs (2) PWRGinna (1) PWRNine Mile Point (2) BWR
3 5 P6r8.2 Both P6v8.3.1 SP1 Testing Installed Oracle 20,000 Maximo Homegrown EOOS eSOMS None 12/19/2014Pam
Schmid
Indiana/Michigan Power Co. D.C. Cook (2) PWR 1 2 P3r3.1 SP3 Passport Safety Monitor V‐3.5
Detroit Edison Co. Fermi (1) BWR 1 1 P6r7.0 SP3 Both Possible No No Yes No Unifier Installed Oracle 18‐20,000 SAP ‐ Maximo IBM /Homegrown EOOS Home Grown none 12/17/2014Vickie Laskey
Dominion Resources
Business Development Generation Construction\Corporate Nuclear Engineering
NA NA P6r8.4 BothR16.2
(1st Qtr 2016) Yes Yes Evaluating Unifier Oracle Maximo EOOS eSOMS 11/9/2016David
Maynard
Dominion Resources
Kewaunee (1) PWRMillstone (2) PWRNorth Anna (2) PWRSurry (2) PWR
4 7R16.2 (1/2016)
Both TBD Yes Yes Oracle Maximo EOOS eSOMS 11/9/2016David
Maynard
Duke Energy Power Company
Catawba (2) PWRMcGuire (2) PWROconee (3) PWRBrunswick (2) BWRCrystal River (1) PWRRobinson (1) PWRShearon Harris (1) PWR
7 12 P3 BothP6v16.1 (2017)
With 16.1 Upgrade
Oracle 50,000Passport Ventyx Asset Suite 8
HomeGrown NextAxiom with Asset Suite 8 and P6v8.3
Paragon ‐ Legacy DukeEOOS ‐ Legacy Progress
Safety Tagging ‐ Legacy Duke eSOMS with Ventyx Asset Suite 8 Upgrade
11/3/2016Sheila Jackson
Energy NorthwestColumbia Generating Station (1) BWR
1 1 P6 Passport ORAM ‐Sentinel
Entergy Nuclear Operations
Arkansas Nuclear (2) PWRFitzPatrick (1) BWRGrand Gulf (1) BWRIndian Point (2) PWRPalisades (1) PWRPilgrim (1) BWRRiver Bend (1) BWRVermont Yankee (1) BWRWaterford (1) PWR
9 11 P6r6.2 SP1 BothP6v16.2 (2017)
P6v16.2 Upgrade
UPK P6v16.2 Upgrade
Oracle Ventyx Asset Suite 7 EOOS eSOMS Knowledge Relay 11/3/2016Kelli Wulf‐Stewart
Exelon
Limerick (2) BWROyster Creek (1) BWRPeach Bottom (2) BWRThree Mile Island (1) PWRBraidwood (2) PWRBryon (2) PWRClinton (1) BWRDesden (2) BWRLa Salle (2) BWRQuad Cities (2) BWR
10 17 P6r8.2 SP1Both Client &
Webnone Oracle 40,000 PIMS / Passport 10 Maxavera Paragon Knowledge Relay 12/19/2014
Pam Schmid
FirstEnergy Nuclear Operating Co. (FENOC)
Beaver Valley (2) PWRDavis‐Besse (1) PWRPerry (1) BWR
3 4 P6r8.3.1 BothP6r16.2
(Aug 2017)No Yes (in P6R8.3.1)
Yes (in P6R8.3.1)
Yes (in P6R8.3.1)
No Oracle 35,000 SAP Release 740 Maxavera Safety Monitor eSOMS 3.8 Knowledge Relay 3.9.02, Cognos 9/1/2016Tom
Raymond
TXU Generating Company LP ‐ Luminant Generation Co.
Comanche Peak (2) PWR 1 2 Project X Maximo Safety Monitor eSOMS
Nebraska Public Power District Cooper (1) BWR 1 1 P6r15.2 Both P6r16.2 yes SQL 14,000 SAP Maxavera Paragon eSOMSSyntempo, Sentinel (dose tracking) linked by Maxavera
9/1/2016Lesli J. Bremer
NextEra Energy
Duane Arnold (1) BWRPoint Beach (2) PWRSeabrook (1) PWRSaint Lucie (2) PWRTurkey Point (2) PWR
5 8 P6r15.2.9 both P6r15.2.12 Testing Oracle 45,000 Ventyx Asset Suite Homegrown Safety Monitor eSOMS Knowledge Relay 12/6/2016Todd Rozelle
Omaha Public Power District Fort Calhoun (1) PWR 1 1 P5.2 Passport EOOS
Ontario Power Generation (OPG)Pickering (6) CANDUDarlington (4) CANDU
2 10
P6r8.3 Refurb,P6r15.1.2 Stns, P5r15.2.3 IMS
BothBoth P6v16.x
64 bit for Refurb no no no Yes none Oracle 70,000 Asset Suite 7Homegrown SWMS SCC (Scheduling Control Centre)
EOOS ‐ 3.4 ESMII (OPG) Homegrown metrics 9/6/2016Jean
Normand
Pacific Gas & Electric Co. Diablo Canyon (2) PWR 1 2 P6r8.2.2 Mostly Client 2019 Yes Oracle 21,000 SAP Maxavera Outage‐ Safety MonitorOnline‐Phoenix RM
ESOMsSyntempo, Knowledge Relay, Crystal Reports
9/1/2016 Debbie Ruiz
Pennsylvania Power & Light (PPL) Susquehanna (2) BWR 1 2 P6r8.3.1 Both Implementing Oracle 30,000 NIMS, Asset SuiteHomegrown (using API)
EOOS eSOMS
PSEG NuclearHope Creek (1) BWRSalem (2) PWR
2 3 P6r7 Both P6v7 SQL SAP Maxavera EOOS eSoms 1/3/2017 Mark Bode
South Carolina Electric & Gas Co. VC Summer (1) PWR 1 1 P5 Champs ‐CMMS EOOS Champs LOTO
Southern California Edison Co. San Onofre SONGS (2) PWR 1 2 P6r7 SP1 Client Possible Oracle 30,000 SAP Maxavera Safety Monitor Knowledge Relay, Syntempo
Southern Nuclear Operating Co.Farley (2) PWRHatch (2) BWRVogtle (2) PWR
3 6 P6r8.3.8 BothP6r16.22017
no no no little success Oracle 40,000 Maximo Homegrown EOOS eSOMSNORAD (homegrown database),
11/3/2016R. Kent Vaughan
STP Nuclear Operating Co South Texas (2) PWR 1 2Artimus‐Projectview 2013
Oracle 31,000 In House Developed In House DevelopedIn House Developed
Knowledge Relay IV3 9/1/2016 Darrel Barr
Tennessee Valley Authority (TVA)Browns Ferry (3) BWRSequoyah (2) PWRWatts Bar (2) PWR
3 8 P6r7 SP5 Both P6r16.1 Risk Analysis Oracle 40,000 MPAC→MaximoMaxavera/ Homegrown
Sentinel eSOMS
Knowledge Relay,CASSI ‐ (Online KPI & AP‐928 reporting), Tableau ‐ (Outage KPI indicators and dashboards)
9/1/2016Stevan Smith
Wolf Creek Nuclear Operating Corp.
Wolf Creek (1) PWR 1 1 P6r8.3.1.6 Both None NoOwned ‐ not
usedOwned ‐ not
usedYes Oracle 15,000 MPAC (Ventyx) Homegrown Safety Monitor eSOMS Cassi 11/3/2016 Tami Nitsch
Xcel EnergyMonticello (1) BWRPrairie Island (2) PWR
2 3 P6r8.3.2 Both Unknown No 42036 Yes Yes Oracle 30000Passport 10.0.6 Asset Suite 5.0.6
Homegrown using DB triggers
EOOS ‐ 3.4 Passport 12/9/2014George Bowen
PRIMAVERA VERSIONS SUPPORTING PRIMAVERA PRODUCTS USEDCOMPANY INFO OTHER WORK MANAGEMENT TOOLS UPDATE BY ‐ ON DATE
Company Software List.xlsx
37
Hilton Garden Inn Palm Beach Gardens3505 Kyoto Gardens Drive, Palm Beach Gardens, Florida, 33410 TEL: 1-561-694-5833 FAX: 1-561-694-5829
How to Get Here From the Airport
Palm Beach International Airport
DirectionsNorth on I-95 to PGA Blvd East exit 79A Follow PGA Blvd to FairchildsNorth on I-95 to PGA Blvd East exit 79A. Follow PGA Blvd to FairchildsGardens Drive and turn left (north); Hotel sits one block on the left at 3505 Kyoto Gardens Drive
Distance from Hotel: 11 mi. Drive Time: 11 min.
TRANSPORTATION TO AND FROM AIRPORT : Type Typical Minimum ChargeRental Car 39.00 USD Taxi 49.00 USD
Parking:Self Parking : Complimentary
38
West Palm Beach Walking TourHistorical Mansions, Fashion Boulevards, Sandy Beaches, and everything in between
Rating: 5 out of 5 by EveryTrail membersDifficulty: EasyLength: 3.4 miles Duration: 1-3 hoursOverview: This guide will take you past some of the most famous spots in West Palm Beach (or just "West Palm"). You will quickly learn why everything seems to be named after Henry Flagler after you see the park, bridge, statue, and mansion.
Finish the tour off by walking down Royal Palm Way, along the beach, and down the famous upscale shopping street of Worth Ave to get a taste of the more lavish lifestyles of some of this area's residents.
Send feedback on this guide
Points of Interest1. Flagler Park
Flagler Park is a nice open area at the end of Clematis Street with an in-ground fountain (great for kids who want to run through it) as well as a number of tables, benches, and open grass area. When you are done, walk towards to water and turn right and walk towards the Flagler Memorial Bridge.
The plaque reads: "Flagler Park, formerly known as City Park, has been an important public space in West Palm Beach since the founding of the community. The town site for West Palm Beach was laid out in 1893 as a grid pattern of streets running north-south and east-west. The only variation was at the eastern end of Clematis Street, where two angled, short streets branched off to create a triangular public common area.
Over the years, the site has seen a variety of uses. Downtown merchants organized impromptu ball games on the park-like grounds when business was slow. In 1900 a two-story frame building was donated for use as a reading room and transported across Lake Worth from Palm Beach. It was placed on the southeastern portion of the parcel.
The Woman's Christian Temperance Union dedicated a drinking fountain in the Park in 1907. In 1915, a Woman's club was placed on the parcel. Other amenities were also added to the park including a shuffleboard court and a bandstand for outdoor concerts.
As the city's population expended during the 1920s the facilities of the Reading Room were outgrown and a library was built in 1923. It opened in January 1924 as the Memorial Library, named to honor the dead of World War I. It too was outgrown and was replaced by another library in 1962. In 1994 the library was remodeled and the plaza in front of the library was redesigned, incorporating a triangular in-ground fountain. This forecourt has become the center of downtown activities, continuing the traditional use of this important civic space."
2500 feet 500 m
© 2013 Microsoft Corporation © 2013 Nokia
N
West Palm Beach Walking Tour - TripAdvisor
8/4/2013http://www.tripadvisor.com/Guide-g34731-i2353-a_Mode.print-West_Palm_Beach_Florida...39
2. Harbor and Flagler Memorial Bridge
From the bridge you can see all of the sailboats, yachts, and tour boats at the dock. Many of the boats are too tall to fit under this bridge, which is why the Flagler Memorial Bridge is a draw bridge. If you wait long enough, you will see traffic stop and the
bridge opening up in the middle to let boats through.
3. Statue of Flagler
After the bridge you will see a prominent status of Henry Flagler on the island in the middle of the large thoroughfare. You will learn all about the life and legacy of Henry Flagler at his mansion and museum.
4. Flagler Mansion
The Flagler Mansion is a stunning work or architecture and a visit is most definitely worth it. Inside you can follow a docent-led tour or listen to a free audio guide to learn about how Henry Flagler paved the way for modern-day Florida to grow into what it has today.
Flagler became one of the wealthiest men in the world after founding Standard Oil and built and furnished a very impressive mansion. After taking the tour you will no longer be surprised that anything and everything in Florida seems to be named after this man.
5. Sea Gull Cottage
The Sea Gull Cottage is Palm Beach's oldest house.
From the sign:"Constructed in 1886 by R.R. McCormick, a Denver railroad developer, Sea Gull cottage was purchased by Henry Flagler in 1893 and became Flagler's first winter residence in Palm Beach. The Royal Poinciana, Flagler's first resort hotel in Palm Beach, was located next to the Sea Gull. In 1984 Sea Gull was moved and restored by the Preservation Foundation of Palm Beach. It is now the Parish House of the Royal Poinciana Chapel."
6. Society of the Four Arts
The Society of the Four Arts hosts art exhibits, concerts, films, lectures and much more, and is home to the King Library and the philip Hulitar Sculpture Gardens.
7. Royal Palm Way
While walking down Royal Palm Way you may suddenly realize why the area is called West Palm Beach--you are surrounded by enormous palm trees, and may feel like you are in a movie. Walk east along the road until you arrive at the beach.
8. Palm Beach
Spend as much time as you like at the beach. It is hard to resist the call of the warm waters and the bright white sand. When you have had enough, walk south along the path next to the beach until you arrive at Worth Ave where you will find the highest density of upscale shopping.
9. Worth Avenue
For those of you familiar with Los Angeles, just think Rodeo Drive. Worth Ave is a famous upscale shopping district where you are likely to find some of the most expensive stores, cars, and restaurants you have ever seen.
Some examples are: Armani, Meiman Marcus, Cartier, Louis Vuitton, Tiffany & Co, Gucci, Ralph Lauren, Chanel, Brooks Brothers, Lacoste, and much, much more. You may want to leave your wallet in your pocket, but window shopping is always free.
West Palm Beach Walking Tour - TripAdvisor
8/4/2013http://www.tripadvisor.com/Guide-g34731-i2353-a_Mode.print-West_Palm_Beach_Florida...40
Name: ________________________________ Email: _____________________________________
Company: _____________________________ Plant: _____________________________________
What went well? ________________________________________________________________
________________________________________________________________________________
________________________________________________________________________________
________________________________________________________________________________
How can we improve? ___________________________________________________________
________________________________________________________________________________
________________________________________________________________________________
________________________________________________________________________________
Presentation or roundtable recommendations: _______________________________________
________________________________________________________________________________
________________________________________________________________________________
________________________________________________________________________________
Are you interested in presenting in 2018? ____________________________________________
________________________________________________________________________________ 41
This page was intentionally left blank as a spacer.
Use for notes.
42
Questions? / Concerns?
Or just need to be pointed in the right direction
Name:
Concern / Question:
Technical? or Functional?
Application: Current Software Version:
Company: IRC Representative:
Are you planning an upgrade in the near future? Y N Version
Is there an Oracle Service Request (SR) associated? Y N SR#
Date Raised Priority Date Resolved
43