• 6:00 pm – Open House • 6:30 pm – Presentation
• Introduction – Kristin Hoffman, Station Project Manager
• Construction Update – Kristin Hoffman – Ellen Blair, Community Outreach Specialist
• Next Steps • Questions and Answers
• 7:30 pm – Return to Open House • 8:00 pm – Close
Tonight’s Agenda
1
Roosevelt Station Construction Open House October 23, 2013
2
Link Light Rail System • 16 miles of light rail with 13
stations currently in service • University Link and Angle Lake
Station under construction; open 2016
• ST2 Plan funded extensions to Overlake, South King County, and Lynnwood
• 54 mile system
3
• 4.3-mile light rail extension • Stations at U District, Roosevelt,
and Northgate • Completion: 2021 • 62,000 daily boardings added to
system by 2030
Northgate Link (University District to Northgate)
4
Roosevelt Station Key Features
• Station platform 70’-90’ underground
• Elevators, escalators and stairs at both entrances
• Bicycle parking
• Connections to buses on NE 65th St, 12th Ave NE and Roosevelt Way NE
• 8,000 daily boardings (2030)
5
Roosevelt Station Schedule
6
Construction Work Done Salvage & Demolition
• Building fixtures & materials, Standard Radio façade salvaged
• Townhouses – sold and relocated
• Buildings on site removed • Site graded and paved
7
Construction Work Done
8
Overhead Utility Relocation Gas Line Work
Construction Site Current
9
Construction Wall Photo Simulations
10 Corner of NE 65th St & 12th Ave NE looking north
Corner of NE 65th St & 12th Ave NE looking northwest
Construction Wall Photo Simulation
11
NE 67th St looking east
Upcoming Work Now to Spring 2014
12
• Jet Grouting – Approximately 3
months of work – Daytime work only – No parking in this
area during this work
Upcoming Work Now to Spring 2014
13
• 12th Ave NE, NE 65th St & NE 66th St – Lane closures – Traffic maintained – Detours for turns
Upcoming Work Spring to Summer 2014
14
• Weedin Place – Second quarter 2014
start; lasts 3-4 months – Temporary sidewalk,
parking, or lane closures
– Traffic will be maintained
• Slurry wall installation – Some equipment may operate at
night; will comply with noise variance
• Station excavation – starts in mid-2014
Upcoming Work Now to End of 2014
15
Truck Route (from north)
• Trucks enter site southbound from Roosevelt Way NE
• Trucks leave site northbound on 12th Avenue NE
16
Truck Route (from south)
• Trucks enter site southbound from Roosevelt Way NE
• Trucks leave site northbound on 12th Avenue NE
17
ST Standard Construction Procedures • Standard provisions written
into contracts • Promote the local business
district • Full-time community outreach
staff for neighborhood • 24-hour construction hotline
(888-298-2395)
18
Noise Mitigation • Solid plywood construction wall • Stationary equipment (compressors,
generators) enclosed as needed • Truck operations
– No beeping alarms – Engine idle limit of 5 minutes – No compression brakes – Muck haul bins lined with noise dampening material – No nighttime hauling of “muck” (also known as
“spoils”) unless approved by ST • Monitoring • Contractor incentive to reduce noise
19
Contractor Parking • Contractor workers not allowed
to park on city streets • Contractor responsible for
finding parking lot(s) to accommodate all the workers
• ST leasing spaces from Diamond Parking at Calvary church for ST employee parking
20
Business Mitigation Marketing Program • Roosevelt neighborhood banners hung
on construction fencing • Installed Roosevelt neighborhood
street pole banners • Roosevelt business map – November • Install wayfinding kiosks – soon
21
Project Next Steps • Hold neighborhood construction
update meetings • Station 90% design open house –
fourth quarter 2014 • Surface work along tunnel route
starts in 2015 • Sign up for construction alerts
22
Questions?
23
Get Involved and Stay Informed • Sign Up to Receive Email Updates
– www.soundtransit.org/subscribe • Sound Transit Website
– www.soundtransit.org/northlink • Contact Ellen Blair:
– 206.398.5300 – [email protected]