SPS 10-YearTransmission Plan/20-Year Strategic Vision
May 2009This report contains transmission planning data that may be conceptual in nature and is subject to change. The transmission projects listed may change scope, in-service dates or may not be constructed.
2
Purpose
Summarize various planning efforts across SPP and SPSDocument 10 year plan based on current snapshotsMeet FERC Order 890 requirementsProvide roadmap that evolves to changing business and regulatory environment
3
Key Points to Take Away
SPS transmission system has expansive projectsForecasts showing increasing load growth Customer demand may vary due to economic conditions, but transmission system demand will likely continue to increase due to renewable energy production
4
Key Messages10-Year Plan Key Messages• Plan is primarily load serving and reliability based• Plan developed in coordination with SPP STEP processes• Five year capital budget created with ten year construction
identified • No speculative transmission proposed for wind energy
development• ~17,000 MW of generation interconnection requests in SPP
queue20-Year Vision Key Messages• 20 Year Vision is a conceptual plan• Three scenarios evaluated, focused on load serving • 345 kV Transmission construction expected, not 765 kV• No major transmission initiatives ( SPP EHV Plan, etc.)
5
SPS 10-Year Transmission Plan/20-Year Vision
OverviewSPS System CharacteristicsTransmission Planning Zones10 Year Transmission Plan• By Zone
20 Year Transmission Vision
6
SPS System CharacteristicsSystem Control Center -Amarillo, TexasRTO/RRO - Southwest Power Pool (SPP)Transmission Line Miles -6,336 miles (345kV-69kV ) 304 Transmission and distribution stations served2008 Summer Peak Load -5,502 MWGenerators Served/ Connected - 47Wind/Solar Interconnection Points/MW - 7/920 10 Wholesale Customers
14 Interconnected Major UtilitiesEnergy Sales Class Breakdown• 12% residential, 47 %
commercial/industrial, 39% wholesale
• Remainder public authorities and lighting
Service territory - 52,000 square milesBoundary of three electrical grids: East, West & ERCOT
7
SPS Service Territory
N E W M E X IC O
C O L O R A D O
O K L A H O M A
S p rin g e r
T u c u m c a ri
R o s e b u d
J a l
H o b b s
P e a rlL e e
O c h o a
H e re fo rd
B la c kw a te r
L o v ing to n
L a s V e g a s
B la c k L a ke
L ib e ra l
G uym o n B e a v e r
P e rry to nW o o d w a rd
S tra ffo rd
D a lh a rt S p e a rm a nP ring le
M o o re C o .
R iv e rv ie w
B o rg e r P a m p a
R a n d a llB u s h la n d
C a n yo n
S w is h e r
M u le s h o e
L ittle f ie ld
H a leC o .
T u c o
H o llis
R u s s e ll A ltu s
S h a m ro c k
W h ite fa c e
S n yd e r
E lk C ity
F t. S u p p ly
G le n w o o d
W o o d rin g
H e n n e s s e y
O ke e n e
A lv a
W e a th e rfo rdJ c t. E l R e n o
N o rth w e s t
C im a rro n
C o rnv ille
C lin to n
L a w to n B a s e lin eD u n c a n
C o m a n c h e
V e rno nO k la u n io n
D e nv e rC ity
M id la n d
Y o a ku m
S e a g ra v e s
A rte s ia
M a lja m a r
E u n ic e
T e a g u e
S un d o w n
L u b b o c k E .
L u b b o c k S o .
O K L A H O M A C IT Y
M U S T A N G
L U B B O C K
J O N E S
P L A N T X
C U N N IN G H A M
M A D D O X
C O M A N C H E
A N A D A R K OS O U T H W E S T E R N
M O O R E L A N D
T O L K
H o b a rt
P A U L IN E
C o x
S m ithD e a f
S u lp hu r S p rin g s
T e rry
T a o s
E d d y L e a C o .
G ra s s la n d
B o rd e n
L yn n G ra h a m
S a y re
B o w e rs
K irb y
G ra p e v in e
M U S T A N G
P o tte r
S o 4 th
D U K E
S e v e nR iv e rs
P e c o s
T E X A S
F lo yd
C ro s b y
S . L ib e ra lE lkh a rt
H A R R IN G T O N& N IC H O L S
K A N S A S
A M A R IL L O
C A R L S B A D
R O S W E L L
C L O V IS
P O R T A L E S
M a jo r G e n e ra tio n
M a jo r L o a d A re a sG e n e ra tio n b y O th e rs
T e x a s C o .
3 4 5 k V T ra n s m is s io n2 3 0 k V T ra n s m is s io n1 1 5 -1 6 1 k V T ra n s m is s io n
N
S
EW
8
NEW M EXICO
COLORADO
OKLAHOMA
Springer
Tucumcari
Rosebud
HOBBS
PearlLee
Ochoa
Hereford
Blackwater HVDC
Lovington
Las Vegas
Black Lake
Liberal
Guymon Beaver
PerrytonW oodward
Strafford
Dalhart SpearmanPringle
Moore Co.
Riverview
Borger Pampa
RandallBushland
Canyon
Swisher
Muleshoe
Littlefield
HaleCo.
Tuco
Hollis
Russell Altus
Shamrock
W hiteface
Snyder
Elk City
Ft. Supply
Glenwood
W oodring
Hennessey
Okeene
Alva
W eatherfordJct. El Reno
Northwest
Cimarron
Cornville
Clinton
Lawton BaselineDuncan
Comanche
VernonOklaunion
DenverCity
Yoakum
Seagraves
Artesia
Maljamar
Eunice
Teague
Sundown
Lubbock E.
Lubbock So.
OKLAHOMA CITY
MUSTANG
LUBBOCK
JONES
PLANT X
CUNNINGHAMMADDOX
COMANCHE
ANADARKOSOUTHW ESTERN
MOORELAND
HOLCOMB
LA JUNTA
TOLK
Lamar
Hobart
PAULINE
Cox
SmithDeaf
Sulphur Springs
Terry
Taos
Eddy Co.
Lea Co.
Grassland
Borden
Lynn Graham
W alsenburg
BurroCanyon
Sayre
Bowers
Kirby
Grapevine
(2004)
MUSTANG
Potter
So4th
DUKE
SevenRivers
Pecos
TEXAS
Floyd
Crosby
Finney
S. LiberalElkhart
HARRINGTONNICHOLS
KANSAS
AMARILLO
CARLSBAD
ROSW ELL
CLOVIS
PORTALES
LINE ITUCO - OKLAUNION
345kV
LINE DGRAPEVINE - ELK CITY
230 kV
LINE HEDDY CO.
HVDC
LINE EBLACKWATER
HVDC
LINE CTEXAS CO. - LIBERAL
115 kV
LINE GKIRBY - SHAMROCK
115 kV
LINE AFINNEY - LAMAR HVDC
345 kV
LINE BFINNEY - HOLCOMB
345 kV
Texas Co.
Jericho
LINE FKIRBY - JERICHO
115 kV
Line A FINNEY - LAMAR HVDC 345 kVLine B FINNEY - HOLCOMB 345 kVLine C TEXAS CO. - LIBERAL 115 kVLine D GRAPEVINE - ELK CITY 230 kVLine E BLACKW ATER HVDCLine F KIRBY - JERICHO 115 kVLine G KIRBY - SHAMROCK 115 kVLine H EDDY CO. HVDCLine I TUCO - OKLAUNION 345kV
SPS TIE-LINE SUMMARY
N
S
EW
345kV Transmission230kV Transmission115-161kV Transmission
Tie Lines, Interconnections
9
Planning ProcessSPP STEP• Annual Process• Focus is overall reliability of entire SPP region• SPP conducts the studies for 10 years out• SPP invites participation in process• Study synopsis
– SPP uses various models to test system under different flow conditions
– Purpose is to determine upgrades to support increasing loads, sold transmission service
– Results are “Notices to Construct” (“NTC”) to Transmission Owners each February - letters are on the SPP website
10
Planning Process
SPS FERC 890 - Local Planning Process • Primarily aimed at 69 KV systems• Sub-regional load serving focus• Minimum of one annual meeting per year• All stakeholders invited to participate• Integrates with SPP’s FERC Order 890 process
SPP EHV Planning Process• Long-range 20-year horizon 345 kV, 765 kV plans• Coordinated with other RRCs and regions
11
Transmission
Planning DriversLoad Growth RateRegional Economic ConditionsWholesale and Retail Load Interconnections• Heavy industrial and commercial development• Currently 20 requests in study queue, 200-300 MW
SPP STEP Planning ProcessTransmission Service Studies - SPP Aggregate Study processSPP Generator Interconnection Queue - 17,000 MW, mostly windRegulatory/Environmental Considerations• State Mandates• Wind Rich Area
12
Transmission
Planning DriversStakeholder Concerns• Cooperatives - GSEC, NM Cooperatives• Munis - WTMPA• Neighboring Utilities - Caprock, WECC (PNM, EPE,
PSCo), AEPW, Sunflower• IPPs - wind developers and fossil developers
–PURPA and QFs - large issue!
13
Transmission
Planning DriversLoad Forecasts
SPS BA Coincident Peaks (to August 5, 2008)
5500
50485168
4835
4673
433843004400450046004700480049005000510052005300540055005600
2003
2004
2005
2006
2007
2008
MW
14
Transmission
Planning DriversLoad Forecasts
SPS BA Forecast Peak, MW
4,000
4,500
5,000
5,500
6,000
6,500
7,000
7,500
8,000
2008 2010 2012 2014 2016 2018 2020
Peak Load (MW)
New Forecast Loads Used in Studies Previous Forecast ($70 oil)
15
ImplicationsProject delay – CCN process may not go forward if transmission needs changeForecast Rebound – if project is delayed, load picks up, the transmission is behind scheduleLower forecast – slower build-out, not necessarily canceled projectsLoad forecast – may not be the most significant driver as compared to generation interconnections and transmission service sold by SPP
17
Planning CriteriaSPP CriteriaSPS Criteria - filed as part of FERC 715• Minimally restrictive• Primary focus in interconnection reliability
NERC Planning Standards
19
Zone 1, 2, and 3 Projects
Texas North Upgrades
W.P
.EW.T.U.
Amarillo
Liberal EnglewoodElkhart
GateKnowles
Forgan
Beaver
Tyrone
Hooker
Hardesty
Optima
Guymon
Goodwell
Keyes
Boise City
Texhoma
Dalhart
Stratford
Cactus
Sunray
Dumas
Gruver
Spearman
Perryton
Booker Darrouzett Follett
Higgins
Canadian
Channing
Vega
Adrian
Fritch Borger
Stinnett
Sanford
Panhandle
White Deer
Claude
Groom
Pampa
Mclean
Miami
Mobeetie
Wheller
Shamrock
Valero
T.C.
T. C.
T.C.
T.C.
T.C.
T.C.
T.C.
T.C.
T.C.
T. C.
T.C.
T.C.
T.C.
T.C.
T.C.
T.C.
T. C.
T.C.
Ochiltree Co.Interchange
N.P.N. P.N.P.
N.P.N.P.N.P.
N.P. N.P.
N.P.
N.P.
N. P.
N.P.
SpearmanInterchange
N.P.
N.P.
PringleInterchange
Moore Co.Interchange
Sherman Co.Interchange
DalhartInterchange
DallamInterchange
Etter
Dumas19th St .
Potter Co.Interchange
Bushland Interchange Randall Co.
Interchange
Coulter Interchange
Amarillo South
East Plant
Nichols Sta.
Harrington Sta
.
Kirby Sw. Sta.
Grapevine Interchange
Bowers Interchange
Kingsmill Interchange
G.B. G.B.
N. P.
Gray Co . Interchange
Grave Substation
Riverview
Excell Sub
ColeInterchange
OKLAHOMA
KANSAS
TEXAS
R.B.
TC- Whiting Texas Co. Interchange
Wildorado
.
Hutchinson Co. Interchange
Blackhawk
N
S
EWLEGEND
230 kV LINE115 kV LINE69 kV LINE
SUBSTATION or INTERCHANGE
Texas
Amarillo
HitchlandInterchange
20
Zone 1, 2 and 3 ProjectsYear Project Descriptions Issues Cost $
Hitchland Interchange: New 345/230/115 kV interchange.Hitchland - Texas Co 115 kV lines: 2 lines, intercepting existing 115 kV linesHitchland - Spearman 115 kV line: 1 line, intercepting existing lineHitchland - Perryton 115 kV line: 1 line, intercepting existing line
Provide new source to the Texas and Oklahoma Panhandle area; to serve load growth during system intact conditions and contingencies.
NW Intg - Channing-Dallam 115kV Line: Construct 230 kV operated at 115 kV
Provide relief to growing reliability problems on 69 kV serving Channing and Tascosa subs
2011 Texas North Upgrade
Hitchland - Moore Co 230 kV line: 230 kV line to existing Moore Co Interchange
Provide second 230 kV source to Moore Co. Area and provides voltage support for Potter-Moore 230 kV Line contingency
Hitchland - Pringle 230 kV line: 230 kV line to existing Pringle Interchange
Provide another 230 kV source to Pringle Sub to enhance reliability in the area.
93.9M2010 Texas North Upgrade
21
Zone 1, 2 and 3 ProjectsYear Project Descriptions Issues Cost $
2009 Nichols Auto Upgrade
Change out 150 MVA units (2) with 252 MVA units
Required for firm transmission service service for Mustang GT’s and Wildorado Wind.
6.2M
2010 Wheeler Project New 230/115 kV Interchange; new 115 kV line to Grave Substation; new 115/69 kV transformer and new distribution Sub
Required to serve addition wholesale and retail loads in E. Panhandle area. Area need stronger source - current transmission is only 69 kV.
9.1M
2011 Texas North Upgrade-Phase 2
Hitchland -Ochiltree 230 kV line. New 230 kV Line to Ochiltree Intg ( 230/115 kV) near Perryton
Provides source to developing load area which has insufficient transmission. Mitigate contingency overload and voltage problems.
8.5M
2016 S. Georgia Intg -Osage Switching Station 115kV line
Upgrade 115 kV Line ratings to 100 deg. C.
Provide system reinforcement for the Nichols-Amarillo South 230 kV line contingency. SPP compliance required project.
1.3M
2018 Van Buren Tap-Hastings –Northwest 69 kV Line re-conductor
Re-conductor existing 69kV line
Contingency overload based on current conductor rating. Needs larger conductor
2.4M
22
Zone 1, 2 and 3 ProjectsYear Project Descriptions Issues Cost $
2009 GSEC Deaf Smith #6
Install 3-way switch to serve new cooperative load
Coop adding new load near Hereford
0.3M
2010 GSEC Deaf Smith #24
Install 3-way switch to serve new cooperative load and 14.4 MVAr Cap Bank at Parmer Co
Cap bank will provide voltage support for the Curry Co. Interchange- Deaf Smith #20 115kV line segment contingency
0.9M
2010 Curry Co-Roosevelt Co. 115 kV line
Re-rate 115 kV Line from 90°C to 125 °C temp design.
Line upgrade will provide system reinforcement for outage of the 230/115kV auto at Oasis Intg.
0.2M
2010 North Clovis project
Upgrade from 69 kV to 115 kV service and upgrade Curry County line terminal
Prevents overload of Curry 115/69 KV autos by converting 69 kV dist transformers. Line terminal’s low rated equipment needed upgrade
0.8M
2016 Deaf Smith Co. Interchange
Upgrade existing 230/115 KV Auto-transformer #1 to 252 MVA
Provide system reinforcement for Deaf Smith Interchange Autotransformer #2 contingency.
3.5M
23
Zone 4 - Projects
HALECO.
FLOYDCO .
Plainview
Lockney
Floydada
Petersburg
LHE -Plainview
NorthPlainview
LHE-Finney
EastPlainviewPlainview City
WestPlainview
Westridge
South Plainview
CoxInterchange
LHE -Providence
AikenRural
LHE -Aiken
Irick
Barwise
LHE -Harmony
Floyd Co. Interchange
LHE -Petersburg
AllmonSPEC -Becton
LHE -Wilson &Ellen
LHE -Lone Star
LockneyRural
ToLHE -South
Plains
ToLHE -
Cedar Hill
South Floydada
27
70
Y76
70
Y74 V -07
Y77
Y96
Z -38
T -68
J-01
62
T-65
Z-36
ToBriscoe &
LHE - SouthPlains
N
S
EW
Aiken
Barwise
Lockney Tap
TexasLubbock
LEGEND
SPS 230 kVSPS 345 kV
SPS 115 kVSPS 69 kVREC 69 kVCounty Line
City Limits
REC or Municipal STATIONSPS STATION
207 State Highways
' SPEC ' South Plains Electric Cooperative, Inc.' LHE ' Lighthouse Electric Cooperative, Inc.
SPS Transmission Line Designation
' SEC ' Swisher Electric Cooperative, Inc.
J- 01
New 115 kV line
US Highways70
27 Interstate Highways
Cox – Floyd115 kV line
Floyd County 115/69 kV Auto
Upgrade
24
Zone 4 ProjectsYear Project Descriptions Issues Cost $
2008 WTMPA Transmission Service Request
Upgrade Floyd Co 115/69 kV from 40 MVA to 84 MVA and install 2nd 230/115 kV auto at Tuco
Provide 325 MW firm network transmission service for WTMPA customers/network upgrades required under SPP tariff.
5.0M
2008 Terry Co. Auto Upgrades
Upgrade both 115/69 kV autos to 84 MVA units
Provide N-1 contingency relief for the loss of the other transformer.
2.0M
2008 Cochran Co. Auto Upgrades
Upgrade both 115/69 kV autos to 84 MVA units
Provide N-1 contingency relief for the loss of the other transformer.
2.3M
2009 Cox-Floyd 115 kV line
Last of Crosby-Floyd Co upgrades
Final phase of Plainview-Floyd-Crosby upgrade project started in 2001 to mitigate system system intact and contingency problems on the south eastern most edge of the SPS system in Texas.
8.9M
2009 Hale County Intg. Auto Upgrade
Upgrade both 115/69 kV autos to 84 MVA units
Provide N-1 contingency relief for the loss of the other transformer.
1.7M
2009 Lubbock East Auto Upgrade
Upgrade both 115/69 kV autos to 84 MVA units
Provide N-1 contingency relief for the loss of the other transformer.
2.1M
25
Mustang Station
Willard
98
V80
LTG McConal
Z21
T2
Z46
T57
Y95
LWe
Jaybee
Seagraves Int.
Denver City Int.
Wasson Sitching
Sta.
ODC
Wasson Pump
San Andress
East Denver
City
ShellC3
Denver City
Shell #7
C2
Allred
El Paso
Shell CO2
BennettPhillips Pump
#1
Russell Pool
AmfracMid
American
K55
V54
V80
K20
Y99
Y98
Y86
Y98
T16
T13 Tenneco
Boardman
Flannagan
West Hobbs
Sw. Sta.
East Sanger
S. HobbsS. Hobbs
Taylor Sw. Sta.
MillenNE.
Hobbs
N. Hobbs
West Bender
Sanger Sw. Sta.
T14
T15
V54
K20
Gaines Co. Int.
Doss Int.
AHCO2SUB
T40T39
Monument
Cooper Ranch
Drinkard
Eunice
Seminole
Hobbs
Eunice
Lovington
ngham ion Maddox
Lea Co. Int
Lea Road
Ward
Seagraves
Moss
LTG-Seagraves
180
385
62
83
214
385
62 180
188
176
176
234
483
18 132
83
83
K49
Lea Co.Waits Sub.
NE
W M
EX
ICO
TE
XA
S
GAINES CO.
TER
O.
N
S
EW
HiggSwitching
MAPCO
Riley
V94
V53
LEGEND
230 kV LINE115 kV LINE
69 kV LINE
18
180
K49
US HIGHWAYSTATE ROAD
CIRCUIT ID
WATER / DRAINAGE
SUBSTATION or INTERCHANGE
TexasSeminole
Legacy Interchange
Project
NewSeminole
Interchange
Hobbs Plant
Mustang – Hobbs - Seminole Project
Zone 5 Projects
26
Zone 5 Projects
Year Project Descriptions Issues Cost $
2009 Yoakum County Intg.
Add second 230/115 150 MVA transformer
Provides relief of existing transformer overload due to line contingency in area.
1.9M
2010 and 2011
Mustang -Hobbs -Seminole Project
Construct 230 kV line from GSEC Mustang Plant- Seminole Intg. to Hobbs Plant. Install 2 230/115 kV autos at Seminole Intg. Re-terminate several 115 kV lines in and out of the 115 kV bus at Seminole
Provides load service for major Hess Corp. expansion project and network transmission service for Hobbs Generator
32.8M
2011 Legacy Intg Project
115/69 kV auto, convert 9.5 miles of 69 kV to 115 kV , construct ~ 3 miles of new 115 kV to connect station in to existing transmission.
Provides system reliability and reinforcement during intact and contingency conditions to developing oilfield loads in the Gaines Co area. Mitigates overload of Gaines co. transformer and 69 kV lines in that area.
7.6M
27
L E A
Eddy Co
Chaves Co
Hopi
White City
Navajo #3
Wherry Housing
Cottonwood
Price
Fiesta
Navajo-Malaga
Loving South
Potash Junction
PCASeven Rivers
Del Hi
Sand Dunes
WIPP
Livingston Ridge
NM Potash #2
Duval #2
IMC #2
IMC #3
Ochoa
Dexter
Whitten
Ward
Hobbs
Teague
Jal
Millen
Pearl
Zia
AMFRA
Tenne
Bo
RusPo
Arco BP-Willard
Hagerman (CVEC)
Lake Arthur (CVEC)
Lakewood (CVEC)
Orchard Park (CVEC)
Pecos
Waterfield
Carlsbad
LovingtonDenver
City
Tatum
Roswell City
Carlsbad
Atoka
Artesia
Roswell
NewMexico
Tex
Eagle Creek Project
Seven Rivers – Pecos – Potash
Project
LEGEND
230 kV LINE115 kV LINE69 kV LINE
K49CIRCUIT ID
SUBSTATION or INTERCHANGE
Carlsbad
New Mexico
N
S
EW
HobbsStation
T41
T83
Z22T23
V61
V21
V84
K52
V83
Z05
Z57
T62
T61
K60
K23T43Z56
V26
J02
K38
Z08
Z09 T26
T39
T40
K20V54
T13
T16
V98
Z03
K49
Zone 6, and 7 Projects
28
Zone 6 and 7 Projects
Year Project Descriptions Issues Cost $
2009 Eagle Creek Project
Construct new 115/69 kV interchange in Artesia, NM and re-terminate nearby Eddy Co - Seven Rivers 115 kV line at Eagle Creek. Re-terminate sources to Navajo refinery into this new station.
Provides network support for Artesia Intg that provides service to town and more reliable service to a large industrial customer.
14.6M
2010 Seven Rivers -Pecos -Potash Project
Construct 230 kV transmission from Seven Rivers - Pecos - Potash and install 230/115 kV auto at Pecos Intg.
Provides network transmission service for Hobbs Generator.
20.1M
31
20-Year
Transmission Vision
Not a detailed plan, but a ‘vision’Three Scenarios• Scenario I - High Internal Renewables • Scenario II - High Resource Import• Scenario III - Minimum Load Growth
32
Base Scenario
Transmission Vision
+
Spearville - Commanche
Hitchland - Mooreland
Hitchland – East Amarillo
East Amarillo - Potter
Potter - Roosevelt
Roosevelt – Tolk - Tuco
Chaves - Crossroads
Crossroads - Hobbs
Hobbs – Midland – Borden
Legend345 kV to be constructed by 2018345 kV Base Scenario line additions345 kV 230 kV161 – 115 kV
Borden - Tuco
Crossroads - Tuco
East Amarillo - Tuco
Mooreland – NW Intg
Comanche - Mooreland
Comanche - Wichita
20 Year SPS Base Scenario
East Amarillo
Crossroads
Comanche
34
Scenario II
Transmission Vision
Legend345 kV to be constructed by 2018345 kV Scenario II line additions345 kV 230 kV161 – 115 kV
20 Year SPS Scenario II
Comanche
East Amarillo
Crossroads
Mooreland – NW Intg
Comanche - Mooreland
Comanche - Wichita
Spearville - Commanche
Hitchland - Mooreland
Hitchland – East Amarillo
East Amarillo - Potter
Potter - Roosevelt
Roosevelt – Tolk - Tuco
Chaves - Crossroads
Crossroads - Hobbs
Hobbs – Midland – Borden
Borden - Tuco
Crossroads - Tuco
East Amarillo - Tuco
East Amarillo – SW Station
35
Scenario III
Transmission VisionNo additional impacts beyond the Base Scenario expected• By 2028, only 100-150 MW would be
needed for a 0.25% growth rate• 345 KV Plan for Base Scenario likely
adequate