A practical guide for site personnel
Site sampling andtesting of concrete
Cubes have a vital role totest that the concretestrength meets thespecification requirement.
However, the cube resultswill be meaningless unlessthe sampling and testingprocedures given in thisbooklet are followedcarefully.
PART OF THE MINERAL PRODUCTS ASSOCIATION
Sampling amended booklet amended:Layout 1 4/8/09 14:14 Page 1
This practical guide for site personnel covers:
Sampling,
The slump test
The flow test
Making cubes
Storing cubes
it also gives guidance to Safety
This practical guide for site personnel isintended to be used in conjunction withthe poster ‘Site sampling and testingconcrete
Sampling amended booklet amended:Layout 1 4/8/09 14:14 Page 2
SamplingThe standard compositesample
BS EN12350-1
To ensure it is representative of thewhole load a standard sampleconsists of scoopfuls taken fromfour different parts of the load andcollected in buckets.
Scoopfuls must be taken throughthe moving stream, as the load isdischarged, sampling the wholewidth and depth – not just the toppart. The size of sample taken shouldbe 11/2 times the estimated volumerequired for testing.
Slump test - 6 litresFlow test - 41/2 litresCube test - 1 litre for each cube
Let very first concrete goTake a scoopful from part 1Take a scoopful from part 2Take a scoopful from part 3Take a scoopful from part 4Let the last concrete go
Complete a sampling certificate andrecord which sampling method wasused.
The alternative spotsample
BS EN206-1:2000,clause 5.4.1
Do not use this method to makecubes
For an early check on theconsistence of concrete delivered ina truck mixer, this alternative methodof spot sampling from the initialdischarge may be used. Additionaltolerances will be applicable forconcrete sampled by this method.
Scoopfuls must be taken through themoving stream sampling the wholewidth and depth.
Let very first concrete go
Take six scoopfuls from the next0.3m3
Take six scoopfuls after the first0.3m3 has been discharged.
1
Sampling amended booklet amended:Layout 1 4/8/09 14:14 Page 3
The slump test BS EN 12350-2
Step 1• Empty the sampling buckets ontothe mixing tray
• Scrape each bucket cleanStep 2• Thoroughly remix the sample,shovelling into a heap
• Turn the heap over to formanother
• Do this three timesStep 3• Flatten the finalheap by repeated-ly digging-in theshovel vertically
• Lift the shovelclear each time
Step 4• Ensure the slump cone and baseplate are clean and damp
• Place the metal plate on solidlevel base away from vibration orother disturbance
• Place the cone on the plate andstand on the foot-pieces
Step 5• Fill the cone in three equal depthlayers
• Use the standardslump rod
• Rod each layer25 times
• Spread the blowsevenly
• Heap theconcrete above thetop of the cone before rodding thethird layer over the area
• Make sure the rod just penetratesthe layer below
Step 6• Top up if necessary• Use the rodwith a sawingand rollingmotion to strikethe concretelevel with thetop of the cone
Step 7• Carefully clean off spillagefrom sides and base plate whilstmaintaining foot pressure
2
Sampling amended booklet amended:Layout 1 4/8/09 14:15 Page 4
Step 8• Carefully liftthe cone straightup and clear, to acount of between2 and 5 seconds
Step 9• Lay the rodacross theupturned slumpcone
• Measurethe distancebetween theunderside ofthe rod and the highest point of theconcrete – the true slump
• Record the distance to thenearest 10mm
• Check and record the kind ofslump
• If the slump isn’t true, take anew sample and repeat the test
• If the second slump isn’t true,get advice
• Complete the sampling andtesting certificates
There are three kinds of slump
TrueShear
Collapse
Youwill need this equipment(always clean and dry the equipment
after use)
� Small scoop
� Slump rod
� Square-mouthed shovel
�Mixing tray
� Buckets or wheelbarrow
� Sampling and testing certificates
� Steel rule
� Damp cloth
� Sampling scoop
� Slump cone and rigid metal plate
3
Sampling amended booklet amended:Layout 1 4/8/09 14:15 Page 5
The flow test BS EN 12350-5
First find a suitable location for aflow table. It must be placed on afirm, flat and level surface. It may benecessary to prepare an area for thetable.
Step 1• Empty the sampling buckets ontothe mixing tray
• Scrape each bucket cleanStep 2• Thoroughly remix the sample asdescribed for the slump test
Step 3• Ensure themould and tableare clean anddamp
• Place themould on thecentre of thetable and stand on the foot-pieces
• Fill the mould in two layers,tamping each layer ten times withthe tamping bar
• If necessary add more concrete tofill the top layer
• Use the tamping bar to strike thetop layer level with the top of themould
Step 4• Carefully clean off spillage fromaround the mould and table top
Step 5
• Wait 30 seconds from striking off
• Carefully lift themould straight upand clear to acount of between3 and 6 seconds
Step 6• Stabilise the flow table bystanding on the toe board at thefront of the table
Step 7• Slowly lift the table top by thehandle until it reaches the upperstop
• Allow the table to fall freely• Repeat this cycle to give a total of15 drops
• Each cycle should take about4 seconds
4
Sampling amended booklet amended:Layout 1 4/8/09 14:15 Page 6
Step 8• Measure the largest dimension ofconcrete spread in two directions,parallel to the table edges
• Record the flow value as d1 + d2divided by 2
• Report any segregation which mayhave occurred around the sampleedge
• Complete the sampling andtesting certificates
Youwill need this equipment(always clean and dry the equipment
after use)
� Sampling scoop
� Small scoop
� Damp cloth
� Buckets or wheelbarrow
� Hardwood tamping bar
� Square mouth shovel
�Mixing tray
� Flow table
� 700mm rule
� Sampling and testingcertificates
5
Sampling amended booklet amended:Layout 1 4/8/09 14:15 Page 7
Making cubes BS EN 12390-2
Collect a composite sample to thestandard method described above.Concrete sampled using thealternative spot method must not beused to make cubes.
Step 1• Check thatthe mouldsare clean andlightly oiledwith all boltstightened sothat therewill be no leakage
• Ensure that the correct halves ofthe moulds are used and that thecorner lifting pins are correctlylocated
• Thoroughly remix the sample asdescribed for theslump test
Step 2• Fill the mouldwith concretein 50mm layersusing the tampingbar, compact theconcrete with nofewer than 25 tamps for each of thetwo layers in a 100mm mould and
no fewer than 35 tamps for for eachof the three layers in a 150mmmould
• For very high workability concreteyou may not need the minimumnumber of tamps
Step 3• After tampingof each layer, tapthe sides of themould with thehide hammer untillarge bubbles ofair cease toappear on the surface and the holesleft by the tamping bar are closed
Step 4
• Remove surplus concrete andsmooth over with a float
• Wipe clean themould edges
• Number themoulds foridentification andrecord details andimmediately placewhere they are tobe storedovernight
6
Sampling amended booklet amended:Layout 1 4/8/09 14:15 Page 8
Step 5• Cover each mould with a dampcloth and plastic sheet
• Store inside at room temperature(15-250C) e.g. on top of the curingtank
• Protect the cube moulds at alltimes from high and lowtemperature (especially sub-zerotemperatures) and drying winds
• Complete the sampling and cubemaking certificates
Youwill need this equipment(always clean and dry the equipment
after use)
� Sampling scoop
� Small scoop
� Damp cloth and plastic sheeting
� Buckets or wheelbarrow
� Tamping bar
� Brush and mould oil
� Curing tank
�Hide hammer
�Maximum/minimum thermometer
� Square-mouthed shovel
� Felt tip pen or crayon
� Cube moulds
� Spanner
�Mixing tray
� Damp cloth
� Sampling. cube making and storagecertificates
7
Sampling amended booklet amended:Layout 1 4/8/09 14:15 Page 9
Storing cubes BS EN 12390-2
Having stored the moulds atbetween 15_250C the cubes shouldbe removed from the moulds noearlier than 16 hours and no laterthan 72 hours after casting.
Step 1• Record the maximum/minimumovernight storage temperatures onthe certificate
Step 2• Slacken all nuts• Part the sides of the mould,tapping gentlywith the hidehammer
• Lift offcarefully
• Remembernew cubes areeasily damagedunless handled carefully
Step 3• Mark each cube with itsidentification number on two of itscast sides
Step 4• Place thecubes in thecuring tankwith the watertemperaturecontrolled at200C ± 20C andthe cubes covered by water
Step 5• Clean and reassemble the moulds• Make sure the power supply is notswitched off day or night
• Check the temperature range dailyusing the maximum/minimumthermometer
• Keep a record of the readingsPlease note• If you have no curing tank,transport the cubes to the testinglaboratory within the 72 hour period
• For despatch to the testlaboratory, wrap the wet cubes indamp cloths, and then plastic bagsand pack in trays
• Attach the certificates forsampling, testing, cube making andstorage to the package – along withthe order for testing
8
Sampling amended booklet amended:Layout 1 4/8/09 14:15 Page 10
The first rule of working withconcrete is to be protected.
Ensure that the personnel arewearing adequate safetyequipment.
• If fresh, wet concrete touchesthe skin, it can cause cementburns - some of which don’tcause pain or dermatitis.
• The longer the skin is in contactwith the concrete, the worse theinjury will be. So it makes senseto protect yourself by wearingsafety goggles, waterproofgloves, a sturdy jacket,waterproof trousers and longboots.
• If wet concrete does contactyour skin, wash immediately andthoroughly with clean water.And if your eyes are affected, seekmedical help immediately.
• Remove and wash anyprotective clothes or boots thatbecome impregnated with freshconcrete, but making sure youwash yourself first.
• The water in the curing tank ishighly alkaline so ensure thatgloves are used when handlingcubes in the tank.
• Fresh concrete is heavy, with abarrow load weighing over 100kg.So carrying just a small volumemay cause physical injury.
Therefore organise enough help sothat you can place, compact andfinish the work before it setswithout straining yourself.
Safety
9
Safety spectaclesor goggles
Wellington boots
Always wearlong trousers
Protect your handsat all times withwaterproof gloves
If you canʼt avoid kneelingin concrete, mortar orscreed, wear knee pads oruse an impervious mat
Sampling amended booklet amended:Layout 1 4/8/09 14:15 Page 11
The other practical guide for site personnel inthis series is:‘Placing, compacting and curing concrete’.TCC/03/42
There are also A2 size posters of each of thesepublications.‘Placing, compacting and curing concrete’.TCC/03/41
‘Site sampling and testing of concrete’.TCC/03/39
All advice or information from Mineral Products Association is intended for use inthe UK only by those who will evaluate the significance and limitations of its con-tents and take responsibility for its use and application. No liability(including that for negligence) for any loss resulting from such advice orinformation is accepted by Mineral Products Association or its subcontractors,suppliers or advisors. Readers should note that the publications from MineralProducts Association are subject to revision from time to time and shouldtherefore ensure that they are in possession of the latest version.
Ref: TCC/03/40ISBN 978-1-904818-74-8Published May 2009
©Mineral Products Association
Produced and printed byThe Book on theWall Company.
Published byMineral Products AssociationGillingham House,38-44 Gillingham Street,London SW1V 1HUTel: +44 (0) 20 7963 8000
www.mineralproducts.org
Sampling amended booklet amended:Layout 1 4/8/09 14:15 Page 12