| NSW Department of Education
SINSW 2020 Delivery StrategyJune 2020
schoolinfrastructure.nsw.gov.au
| NSW Department of Education
2
SINSW 2020 Delivery Strategy
$300M in construction contracts awarded or currently being tendered, including:
■ Chatswood Public & High School Upgrade;
■ Bankstown North Public School Upgrade; and
■ Young High School Upgrade.
85 procurements awarded or currently being tendered across 40 projects.
Committed to providing the best learning environments at public schools across NSW to meet the needs of a growing student population
$20M in consultant fees awarded or currently being tendered.
Since 01 March 2020….
School Infrastructure NSW
Killara High School
SINSW 2020 Delivery StrategyOn the horizon….
SINSW 2020 Delivery Strategy | June 2020
SYD Metro NorthCentre of Excellence Hawkesbury $25m to $75mCranebrook High School < $25mNew Primary School in Epping South $25m to $75mEpping West Public School $25m to $75mGlenmore Park High School Performing Arts and Learning Centre < $25mJamison High School < $25mLindfield Learning Village> $75mMona Vale Public School $25m to $75mMosman High School $25m to $75m
Nepean Creative & Performing Arts High School < $25mPendle Hill High School $25m to $75mPenrith Lakes (new) Environmental Education Centre < $25mRichmond High School < $25mNew Primary School in Tallawong $25m to $75m
SYD Metro SouthDarlington Public School $25m to $75mEngadine High School Hall < $25mHurlstone Agricultural High School $25m to $75m
Jannali East Public School Hall < $25mNew School in Liverpool Electorate $25m to $75mLiverpool West Public School $25m to $75mMilperra Public School Hall < $25mMulgoa / Glenmore Park – New Primary School $25m to $75mPassfield Park School $25m to $75mStanwell Park Public School Hall < $25mSydney Olympic Park New High School> $75m
Western NSW
Northern Inland
North Coast
Hunter / Central Coast
Syd Metro
South East & Tablelands / Riverina
Illawarra / South Coast
SYD Metro North14 projects
SYD Metro South11 projects
LEGENDProject Size
< $25m
$25m to $75m
> $75mProject Name
DfMA Candidate
North CoastBangalow Public School < $25mBexhill Public School < $25mHastings Secondary College, Port Macquarie Campus $25m to $75mKingscliff Public School & Kingscliff High School> $75mMurwillumbah East Public School and Murwillumbah High School> $75mTeven-Tintenbar Public School Hall < $25mTweed Heads High School & Tweed Heads South Public School $25m to $75m
Hunter / Central CoastBrooke Avenue Public School < $25mMuswellbrook South Public School < $25m
Illawarra / South CoastBudawang School, SSP in Milton $25m to $75m
Western NSWBletchington Public School $25m to $75mMillthorpe Public School < $25m
South East & Tablelands / RiverinaBungendore High School – New $25m to $75mJerrabomberra – New High School $25m to $75mQueanbeyan West Public School Hall < $25mYass High School Hall < $25m
| NSW Department of Education
SINSW 2020 Delivery StrategyOn the horizon….
4
20+new business cases commencing with a further 100+ business case procurement opportunities
40+number of schools being constructed or upgraded
130+tendering opportunities across multiple disciplines
$1.2Binvestment to commence procurement
By the numbers….
$460minvestment in bushfire affected communities
14individual projects that are candidates for DfMA construction
31 Dectarget date to call identified tenders by
Parramatta Public School
SINSW 2020 Delivery Strategy | June 2020
5
SINSW 2020 Delivery Strategy
Estimated Value of Consultant Procurements vs Project Size ($M)
<$25M$25–$75M>$75M
$60
$50
$40
$30
$20
$10
$0
17 17
19 19 19
Project Manager
Cost Manager
Architect Services Engineer
Civil / Structural Engineer
Number of Procurements
$M
Estimated Value of Building Contractor Procurements vs Project Size ($M)
~ $156M 9 projects
~ $460M 19 projects
~ $450M 4 projects
<$25M$25–$75M>$75M
| NSW Department of Education
6
SINSW 2020 Delivery Strategy
Anticipated Number & Timing of Procurements by Discipline until Late 2020
Project ManagerCost ManagerArchitectServices EngineerCivil/Structural EngineerBuilding Contractor
40
35
30
25
20
15
10
5
0October
2020
4
December 2020
4
November 2020
10
September 2020
4
4
3
6
June 2020
7
5
5
4
4
3
July 2020
8
6
5
5
5
3
August 2020
4
8
7
8
8
2
1
NU
MB
ER
Bolwarra Public School
SINSW 2020 Delivery Strategy | June 2020
7
Engagement with the Market
Committed to developing and promoting a transparent pipeline of projects in line with the ‘NSW Government Action Plan: A Ten Point Commitment to the Construction Sector’.
$6.7 billion investment to deliver more than 190 new and upgraded schools.
Significant investment in planned maintenance on over 2,200 schools and programs such as $500m for Cooler Classrooms to provide sustainable air conditioning in more than 900 schools across NSW.
Following consultation with the market and advice from Subject Matter Experts, we have proposed:
■ Single team of consultants be appointed where the schools are geographically close and have similar programs.
■ Early Contractor Involvement contracts where considered appropriate for the project to be delivered using Design for Manufacture & Assembly or we wish to commence construction as soon as is appropriate.
■ A diverse and wider range of contract sizes and opportunities by a mixture of bundling and individual procurements.
■ To limit the number of tenders per discipline to no more than ten per month so as not to overwhelm the market and to enable feedback to be utilised in subsequent tenders.
SINSW will continue to:
■ Liaise with potential tenderers before finalising the tender list to ensure those invited have the appetite and capacity to be part of the team that will successfully deliver the project.
■ Monitor performance, using our performance management process, and based on this, reward high performance with the opportunity to tender for other opportunities.
■ Invite companies on our own and the whole of Government Panels to express their interest in a particular project(s); which will be taken into consideration as part of the process to develop an appropriate tender list for each opportunity.
■ Invite three tenderers so evaluations are quicker and there are only two unsuccessful tenderers.
■ Look for appropriate opportunities to appoint companies that are:
▶ Located in a bushfire affected areas; ▶ Aboriginal-owned businesses; and/or ▶ Able to provide a skills legacy.
June 2020… ■ The SINSW Delivery Strategy
is ‘launched’; ■ Market notified of our
Delivery Strategy via the SINSW website, email to companies on our and NSW Government Panels, our Communities of Practice and social media; and
■ Virtual Industry Briefing on our Delivery Strategy.
| NSW Department of Education
8
SINSW 2020 Delivery StrategyProject Manager & Cost Manager
Project Procurements commencing from Project size
North Coast Cluster: Bangalow PS, Bexhill PS, Teven-Tintenbar PS Hall
June 2020 $
Mosman HS June 2020 $$
South Cluster: Engadine HS Hall, Jannali East PS Hall, Milperra PS Hall, Stanwell Park PS Hall, Queanbeyan West PS Hall, Yass HS Hall
June 2020 $$
North-West Cluster: Glenmore Park HS Performing Arts & Learning Centre, Jamison HS, Nepean Creative & Performing Arts HS
June 2020 $$
Minor Upgrades: Brooke Ave PS & Cranebrook HS June 2020 $
Northern Suburbs Cluster: Epping West PS & Epping South (new) PS
June 2020 $$$
Penrith Lakes (new) Environmental Education Centre June 2020 $
Hastings Secondary College, Port Macquarie Campus July 2020 $$
Budawang School, SSP in Milton July 2020 $$
Murwillumbah East PS and Murwillumbah HS July 2020 $$$
Mona Vale PS July 2020 $$
Pendle Hill HS July 2020 $$
Greater Western Sydney Cluster: Tallawong (new) PS, Mulgoa & Glenmore Park (new) PS, (new) Centre of Excellence Hawkesbury, Richmond HS
July 2020 $$$
Hurlstone Agriculture HS July 2020 $$
Monaro Cluster: New HS in Bungendore, New HS in Jerrabomberra
July 2020 $$$
Muswellbrook South PS August 2020 $
Southern Suburbs Cluster: Liverpool West PS & Liverpool (new) PS
August 2020 $$$
Sydney Olympic Park (new) HS August 2020 $$$
Project Size $ < $25m $$ $25m to $75m $$$ > $75m
All projects are school upgrades unless noted otherwise
SINSW 2020 Delivery Strategy | June 2020
9
SINSW 2020 Delivery StrategyArchitects, Service Engineer & Civil/Structural Engineer
Project Procurements commencing from Project size
Far North Cluster: Kingscliff PS, Kingscliff HS, Tweed River HS & Tweed Heads South PS
June 2020 $$$
Mosman HS June 2020 $$
North Coast Cluster: Bangalow PS, Bexhill PS, Teven-Tintenbar PS Hall
June 2020 $
Penrith Lakes (new) Environmental Education Centre June 2020 $
North-West Cluster: Glenmore Park HS Performing Arts & Learning Centre, Jamison HS, Nepean Creative & Performing Arts HS
June 2020 $$
Hastings Secondary College, Port Macquarie Campus July 2020 $$
Minor Upgrades: Brooke Ave PS & Cranebrook HS July 2020 $
South Cluster: Engadine HS Hall, Jannali East PS Hall, Milperra PS Hall, Stanwell Park PS Hall, Queanbeyan West PS Hall, Yass HS Hall
July 2020 $$
Budawang School, SSP in Milton July 2020 $$
Murwillumbah East PS and Murwillumbah HS July 2020 $$$
Monaro Cluster: New HS in Bungendore, New HS in Jerrabomberra
July 2020 $$$
Northern Suburbs Cluster: Epping West PS & Epping South (new) PS
August 2020 $$$
Muswellbrook South PS August 2020 $
Mona Vale PS August 2020 $$
Central West Cluster: Bletchington PS, Millthorpe PS August 2020 $$
Sydney Olympic Park (new) HS August 2020 $$$
Greater Western Sydney Cluster: Tallawong (new) PS, Mulgoa & Glenmore Park (new) PS, (new) Centre of Excellence Hawkesbury, Richmond HS
September 2020 $$$
Pendle Hill HS September 2020 $$
Hurlstone Agriculture HS September 2020 $$
Southern Suburbs Cluster: Liverpool West PS & Liverpool (new) PS
September 2020 $$$
Project Size $ < $25m $$ $25m to $75m $$$ > $75m
All projects are school upgrades unless noted otherwise
| NSW Department of Education
10
SINSW 2020 Delivery StrategyBuilding Contractor
Project Procurements commencing from Project size
D&C Lindfield Learning Village June 2020 $$$
D&C Kingscliff PS & Kingscliff HS June 2020 $$
D&C Tweed River HS & Tweed Heads South PS June 2020 $$
D&C Passfield Park School July 2020 $
D&C Darlington PS July 2020 $$
ECI Mosman HS July 2020 $$
D&C Brooke Ave PS August 2020 $
D&C Cranebrook HS August 2020 $
ECI Budawang School, SSP in Milton September 2020 $$
ECI Monaro Cluster: New HS in Bungendore, New HS in Jerrabomberra
September 2020 $$$
ECI Murwillumbah East PS and Murwillumbah HS September 2020 $$$
D&C Bangalow PS & Bexhill PS September 2020 $
D&C Teven-Tintenbar PS Hall September 2020 $
D&C Muswellbrook South PS September 2020 $
ECI Central West Cluster: Bletchington PS, Millthorpe PS October 2020 $$
ECI Greater Western Sydney Cluster: Tallawong (new) PS, Mulgoa & Glenmore Park (new) PS, (new) Centre of Excellence Hawkesbury, Richmond HS
October 2020 $$$
D&C Hastings Secondary College, Port Macquarie Campus October 2020 $$
D&C Pendle Hill HS October 2020 $$
D&C Penrith Lakes (new) Environmental Education Centre November 2020 $
D&C Glenmore Park HS Performing Arts & Learning Centre November 2020 $$
D&C Nepean Creative & Performing Arts HS Hall November 2020 $$
D&C Jamison HS Hall November 2020 $$
Legend ECI: Early Contractor InvolvementD&C: Design & Construct
DfMA Project
All projects are school upgrades unless noted otherwise
Project Size $ < $25m $$ $25m to $75m $$$ > $75m
SINSW 2020 Delivery Strategy | June 2020
11
SINSW 2020 Delivery StrategyBuilding Contractor (continued)
Project Procurements commencing from Project size
D&C Queanbeyan West PS Hall November 2020 $$
D&C Yass HS Hall November 2020 $$
D&C Engadine HS Hall November 2020 $$
D&C Jannali East PS Hall November 2020 $$
D&C Stanwell Park PS Hall November 2020 $$
D&C Milperra PS Hall November 2020 $$
ECI Northern Suburbs Cluster: Epping West PS & Epping South (new) PS
December 2020 $$
ECI Southern Suburbs Cluster: Liverpool West PS & Liverpool (new) PS
December 2020 $$
D&C Mona Vale PS December 2020 $$
ECI Sydney Olympic Park (new) HS December 2020 $$
D&C Hurlstone Agriculture HS Post 2020 $$
Project Size $ < $25m $$ $25m to $75m $$$ > $75m
Legend ECI: Early Contractor InvolvementD&C: Design & Construct
DfMA Project
All projects are school upgrades unless noted otherwise
Ultimo Public School
| NSW Department of Education
12
What is Design for Manufacture & Assembly….?
Volumetric DfMA ‘Kit of Parts’ DfMA
Mostly finished modules including:
■ Structure; ■ External Finishes; ■ Services; and / or ■ Internal Finishes.
Manufactured building components such as:
■ Columns & Beams; ■ Wall & Floor Panels; and / or ■ Facade Panels & Trusses.
Hybrid DfMA
A combination of both such as:
■ Amenity/core modules; ■ Post and beam structure; ■ Floor & roof panels; and / or ■ Facade panels.
or
■ Bathroom pods; ■ Services riser pods; ■ Precast lift and stair cores; ■ Post and beam structure; ■ Floor & roof panels; and / or ■ Facade panels.
SINSW 2020 Delivery Strategy | June 2020
DfMA Benefits
DfMA has Benefits in Time, Sustainability & Minimising Disruption
Time savings
DfMA can reduce on-site construction time by up to 50%, reducing impacts to school operations
Improved health, safety & productivity
DfMA improves health & site safety, productivity & output in construction
Improved sustainability
DfMA reduces material & waste by ~70% & CO2 emissions by ~50%
Minimises impact on school operations
Reduced program & vehicle movements; peak construction activity during school holidays
Upskills the workforce
Upskilling opportunities for the supply & manufacturing workforce
Opportunity to reduce cost
Over time, design & standardisation reduces cost
13Manly Vale Public School
| NSW Department of Education
14
DfMA Procurement StrategyStrategic Objectives: Develop Industry DfMA Capability & Increase Manufacturing Capacity
14 projects selected with a specific DfMA procurement focus to foster investment and improve industry DfMA capability.
These projects are intended to be grouped into six geographical clusters to maximise bulk purchasing and achieve economies of scale.
Development of a panel of specialist DfMA Building Contractors & a separate panel of approved DfMA Manufacturers.
Following separate procurements, the successful Building Contractor and Manufacturer will be engaged through an ECI delivery method. Limits may be placed to the number of tender opportunities panelists are invited to in order to maximize industry capability.
Panels refreshed in 2021 based on performance and innovation.
Award ECI contract
Further market sounding to Building Contractors and Manufacturers
Call separate EOIs for Building Contractors and for Manufacturers
Contractor Panel and Manufacturer Panel list selected
Potential DfMA ECI contracts start being tendered
DfMA procurement steps
SINSW 2020 Delivery Strategy | June 2020
15
DfMA Procurement StrategyProposed Roadmap to Procurement of DfMA Partners
1. Next steps are to continue market sounding to ensure market readiness.
2. DfMA procurement & delivery will be managed as a single program by SINSW.
3. Partners will be tendered and evaluated against the below:
■ Cluster approach: Programme management principles apply in addition to core PM skills (depth of resource, range of personnel & roles)
■ DfMA focused: Tracked record with DfMA desirable given this is the first wave and success must be guaranteed
■ BIM: Proven track record with the use of BIM for 4D & 5D schedule management or similar
Q3 2020 Q4
Market sounding – Contractors & Manufacturers
EOI drafting
EOI to market (Contractors)
EOI to market (Manufacturers)
EOI Eval – (Contractors)
EOI Eval – (Manufacturers)
ECI tender
ECI tender
Cluster 1 commence
Cluster 2 commence
ECI tender
ECI tender
Cluster 3 commence
Cluster 4 commence
ECI tender
ECI tender
Cluster 5 commence
Cluster 6 commence
Ongoing
Manufacturers Panel Shortlisted
Contractors Panel Shortlisted
Manufacturers & Contractors selected
| NSW Department of Education
schoolinfrastructure.nsw.gov.au