Welcome toSeneca Lake Park & Marina
Master Plan Update
Please hold questions until after the presentation is complete. MWCD Staff will be
available at the stations set up around the room.
Deputy Chief of Parks‐Joe McGlothlin Deputy Chief of Projects‐Tony Luther Park Manager‐Matt Steffen Marina Manager‐Matt Miller Recreation & Park Planner‐
Eric Stechschulte
Introductions
Chief Engineer‐Boris Slogar Project Engineer‐Jeff Yohe Program Manager Consultant‐
Ken Ricker, MS Consultants
2013 2014 2015 2016
Master Plan Timeline
• Woolpert completes overall conceptual master plan
• MWCD Board of Directors approves master plan in October
• Recreation Department prioritized projects
• Completed branding and design guidelines
• Utilities survey & inventory completed at each park
• MS Consultants contracted as MWCD Project Management Consultant
• Aerial topography surveys completed
• 6 Individual Park Designers contracted and began refining preliminary designs on each park
• Individual Park Designers complete preliminary designs for each park
• Individual Park Designers begin detailed design on campground projects
• First campground park projects will be bid out and construction to begin in late 2016
Project Prioritization Transitional Seasonal Camping Areas Infrastructure Stand Alone Projects
Seneca Lake Park & MarinaProject Phasing Strategy
Seneca Lake Park & Marina Approved Projects
FUNDING‐ $20,750,000 Dollars Marina Point Gas Dock Replacement
and Fuel System Upgrade‐ Area M‐15‐Scheduled 2016 Completion
Cabin Renovations‐ Area P‐26B (Recreation Budget)‐Scheduled 2016 Completion
Beach Concession Building Replacement‐ Area P‐15‐Scheduled 2017 Completion
Parkside Sewer to Senecaville Waste Water Treatment Plant‐Scheduled 2017 Completion
New Transient RV Campground‐ Area P‐13 (79 Lots)‐ Scheduled 2018 Completion
New Boat Launch Ramp‐ Area P‐9‐Scheduled 2018 Completion
New Transient RV Campground‐ Area P‐21A (26 Lots)‐Scheduled 2018 Completion
Seasonal RV Campground Renovation‐ Area M‐10 (91 Lots)‐Scheduled 2019 Completion
Seasonal RV Campground Renovation‐ Areas M‐8 & M‐9 (107)‐Scheduled 2020 Completion
Seasonal Camper TemporaryMoving Transition Plan
MWCD is committed to providing assistance by moving your camper, deck and dock to your temporary site, and then moving them back to your newly renovated area.
Affected Seasonal Campers will be notified by letter one year in advance before you move.
Affected Seasonal Campers will receive a checklist that will address procedures for moving their camper, deck and dock.
Affected Seasonal Campers relocated in the Fall of the construction year will be moved back to their newlyrenovated area in Fall of the following year.
Proposed Shower/Restroom Building In Campground
Seneca Lake Park & MarinaCamping Lot LayoutProposed Seasonal Camping Lot Layout
Master Plan Budget
*Chart based on information from: http://www.macrotrends.net/1369/crude-oil-price-history-chart
Crude Oil Prices 2013-June 2016
The Master Plan is being funded through responsible stewardship of oil and gas resources.
In October of 2013 the MWCD Board of Directors approved the Master Plan.
$120 Million Dollars have been dedicated to Master Plan Projects over the next several years.
Seneca Lake Park Future Projects
FUTURE PROJECTS AS FUNDING BECOMES AVAILABLE 4 New Cabins‐ Area P‐26A RV Seasonal Campground Renovation Area
P‐3 (64 Lots) RV Seasonal Campground Renovation Area
P‐4, P‐5, P‐7 (52 Lots) Boat Trailer Storage‐Area M‐1 Campground Outdoor Space‐ Splash Pad,
Game Courts, Picnic Shelter, Playground‐Area M‐2
Public Boat Launch Improvements‐Area M‐3
Boat Storage‐Area M‐4 Marina Service Storage Area‐M‐5 Outdoor Space‐ Tot Lot, Seat Wall & Trellis‐
Area M‐6A Park Office & Laundry Building‐ Area M‐6B Marina Restaurant Improvements‐ Area M‐7 New Tent Campground‐ Area M‐11
Seneca Lake Park Future Projects
FUTURE PROJECTS AS FUNDING BECOMES AVAILABLE New RV Transient Campground‐ Area M‐12
(20 Lots) Gate House‐ Area M‐13 Marina Improvements‐ Area M‐15 Seasonal Camper Storage‐ Area M‐20 New RV Transient Campground‐ Area 574
(107 Lots) Primitive Camping & Trails‐ Area P‐1 Boat Trailer Parking‐ Area P‐2 RV Seasonal Campground Renovated Area
P‐6 (51 Lots) Landscape Entrance Improvements‐
Area P‐12 Beach Improvements‐ Picnic Shelter & Crib
Pier‐ Area P‐15 Parking Lot Improvements and Activity
Center‐ Area P‐16 Water Park‐ Area P‐17 Kayak/Canoe Rental Dock‐ Area P‐18 New RV Transient Campground‐ P19
(40 Lots) New RV Transient Campground ‐ Area P‐21B
(49 Lots) New Cabins‐ Areas P‐26B, P‐26C (16 Total)