[email protected] +91 9998025820
Indian Solar Rooftop Market
40% of Commercial & Industrial Roofs
100% of Commercial & Industrial Roofs
100% of Residential
Roofs
Toda
y
In 3
yea
rs
In 7
yea
rs
Timeline to Grid Parity
Indian Solar Rooftop Market
40% of Commercial & Industrial Roofs
100% of Commercial & Industrial Roofs
100% of Residential
Roofs
Toda
y
In 3
yea
rs
In 7
yea
rs
Timeline to Grid Parity
100 x Growth in the next 7 years
What do you consider while buying…
Price
Mileage
Waiting Period
Accessories
Warranties
Price
Efficiency
Delivery Time
Functions
Warranties
Price
Picture Quality
Delivery Time
Features
Warranties
Price
Cooling Efficiency
Delivery Time
Features
Warranties
Price - Money Matters
PRICE:
Anywhere between Rs. 60 / Wp or Rs. 60 Lacs for 100 kW system to Rs. 140 / Wp or Rs. 1.4 Lacs for a 1 kW system.
TERMS:
• All Inclusive - (Taxation / Statutory Clearances / documentation etc) • 10% Advance • 10% on Completion of Civil Work • 10% on Delivery of Structures • 30% on Dispatch of Modules • 20% on Dispatch of Inverters • 10% of Commissioning of System
Energy Generation
Guaranteed Generation:
No Guarantee = Low Generation
Types of Guarantee: • Absolute Generation Guarantee - same as asking a car
manufacturer to guarantee mileage irrespective of roads.
• Performance Ratio Guarantee - same as a car supplier confirming 15 km / liter mileage on City Roads.
Installation Time
Typical Time Period: 90 days for a 100 kW project
Typical Damages: 0.5% decrease in contract price per week of delay
But, why to enforce damages? • Loss of Tax Benefits for corporates (almost quarter of system cost) • Delay in savings • Increase in Interest Cost etc.
Scope
Define Contractor / Owner Scope exhaustively
Contractor: • Supplies: Specs / Makes / Quantity / Quality etc.
• Modules • Inverters • Cables • Structures • Earthing / Lightning / Protection • Junction Box
• Services: Installation / Civil / Quality / Statutory etc.
Owner: • Access / Space / Storage • Electricity & Water
Warranties
Overall Project Defect Liability Period - typically 12 months after commissioning
Individual Equipment • Modules - 25 years • Inverters - 5 years • Structures - 5 years (some suppliers) • Junction Boxes - 12 months