Name of the Faculty RAVI NANDAL
Discipline CIVIL ENGG.
Semester 6TH
Subject EARTHQUAKE RESISTANT BUILDING CONSTRUCTION
Lesson Plan Duration 15 weeks(from January, 2018 to April,2018)
Week Theory
Lecture
Day
Topic (inculding assignment/test)
1st Elements of Engineering Seismology:- General features of tectonic of seismic regions
2nd Causes of earthquakes, Seismic waves,
3rd Revision
4th Earthquake size (magnitude and intensity), Epicentre, Seismograph,
5th Classification of earthquakes,
6th Revision
7th Seismic zoning map of India,
8th Static and Dynamic Loading, Fundamental period.
9th Revision
10th Seismic Behaviour of Traditionally-Built Constructions of India:- Performance of
building during earthquakes
11th Mode of failure (Out-of-plane failure, in-plane failure, Diaphragm failure,
12th Revision/Assignment
13th Connection failure,
14th Non-structural components failure)
15th Revision
16th Special construction method,
17th Tips and precautions to be observed while planning,
18th Revision
19th Tesigning and construction of earthquake resistant building
20th Tesigning and construction of earthquake resistant building
21st Revision
22nd Introduction to IS: 4326, IS: 13828, IS: 1893(Part 1), 154326 and IS: 13920 (latest
edition)
23rd Introduction to IS: 4326, IS: 13828, IS: 1893(Part 1), 154326 and IS: 13920 (latest
edition)
24th Revision/Assignment
25th Seismic Provision of Strengthening
26th Retrofitting Measures for Traditionally- Built Constructions,
27th Revision
28th Brick and RCC Structures
29th , Brick and RCC Structures
30th Revision
31st Provision of reinforcement detailing in masonry and RC constructions
32nd Provision of reinforcement detailing in masonry and RC constructions
33rd Revision
3rd
2nd
4th
1st
9th
8th
7th
6th
5th
10th
11th
34th Disaster Management: Disaster rescue
35th Psychology of rescue,
36th Revision
37th Rescue workers,
38th Rescue plan, rescue by steps,
39th Revision
40th Rescue equipment,
41st Safety in rescue operations,
42nd Revision
43rd Debris clearance and casuality management.
44th Debris clearance and casuality management.
45th Revision/Assignment
12th
13th
15th
14th
Name of the Faculty S S NANDAL
Discipline CIVIL ENGG.
Semester 6TH
Subject RAILWAYS, BRIDGES AND TUNNELS
Lesson Plan Duration 15 weeks(from January, 2018 to April,2018)
Week Theory
Lecture
Day
Topic
(inculding assignment/test)
1st Introduction to Indian Railways
2nd Railway surveys: Factors influencing the railways route,
3rd Brief description of various types of railway survey
4th Classification of permanent way describing its component parts
5th Rail Gauge: Definition, types, practice in India
6th Rails – t pes of ails
7th Rail Fastenings:
8th Rail joints, types of rail joints,
9th Fastenings for rails,
10th Fish plates,
11th Fish plates,
12th Bearing plates
13th Sleepers: Functions of sleepers,
14th Types of sleepers,
15th Requirements of an ideal material for sleepers
16th Requirements of an ideal material for sleepers
17th Ballast: Function of ballast,
18th Ballast: Function of ballast,
19th Requirements of an ideal material for ballast
20th Requirements of an ideal material for ballast
21st Crossings and signallings:
22nd Brief description regarding different types of crossings/ signallings (Latest electronics
operated signal devices )23rd Brief description regarding different types of crossings/ signallings (Latest electronics
operated signal devices )
24th Brief description regarding different types of crossings/ signallings (Latest electronics
operated signal devices )25th Maintenance of track: Necessity,
26th Maintenance of track,
27th Inspection of soil, track and fixtures;
28th Maintenance and boxing of ballast maintenance gauges, tools
29th Earth work an drainage: Features of rail road,
30th Bed level, width of formation,
31st Side slopes, drains,
32nd Methods of construction,
33rd Requirement of drainage system/Assignment
34th BRIDGES:- Introduction
B idge – its fu tio a d o po e t pa ts,35th Difference between a bridge and a culvert
36th Classification of Bridges Their structural elements and suitability: 13.1 According to life-
permanent and temporary
1st
2nd
3rd
4th
5th
6th
7th
8th
37th A o di g to de k le el – De k, th ough a d se i-th ough38th A o di g to ate ial –ti e , aso , steel, RCC, p e-st essed39th According to structural form; - Grade Seperators-Railway Overbridges (ROB), Railway
underbridge (RUB)
40th Bea t pe –RCC, T-Bea , steel gi de idges, plate gi de a d o gi de , ala ed cantilever, Trussed bridges.
41st A h t pe – ope spa d el a d filled spa d el a el a d i t pe42nd Suspe sio t pe – u stiffe ed a d stiffe ed a d ta le its des iptio ith sket hes
43rd According to the position of highest flood level submersible and non submersible. IRC
classification
44th Bridge Foundations: Introduction to open foundation, pile foundation, well foundation
45th Bridge Foundations: Introduction to open foundation, pile foundation, well foundation
46th Pie s, A ut e ts a d Wi g alls:- Pie s-defi itio , pa ts; t pes –solid aso a d RCC , open
47th A ut e ts a d i g alls – defi itio , t pes of a ut e ts st aight a d tee , a ut e t ith wing walls (straight, splayed, return and curved)
48th A ut e ts a d i g alls – defi itio , t pes of a ut e ts st aight a d tee , a ut e t ith wing walls (straight, splayed, return and curved)
49th B idge ea i gs Pu pose of ea i gs; t pes of ea i gs – fi ed plate, o ke a d olle .
50th B idge ea i gs Pu pose of ea i gs; t pes of ea i gs – fi ed plate, o ke a d olle .
51st Maintenance of Bridges
52nd Inspection of Steel and Equipment bridges
53rd Routine maintenance
54th TUNNELS:- Definition and necessity of tunnels
55th Typical section of tunnels for a national highway
56th Typical section of tunnels for a national highway
57th Single and double broad gauge railway track
58th Ve tilatio – e essit59th Methods of ventilation
60th Blowing,
61st Exhaust and combination of blowing and exhaust
62nd Drainage method of draining water in tunnels
63rd Drainage method of draining water in tunnels
64th Lighting of tunnels
65th Lighting of tunnels
66th Revision of previous question paper
67th Revision of previous question paper
68th Revision of previous question paper
69th Revision of previous question paper
70th Revision of previous question paper
71st Revision of previous question paper
72nd Revision of previous question paper
73rd Revision of previous question paper
74th Revision of previous question paper
75th Revision of previous question paper
15th
9th
10th
11th
12th
13th
14th
Name of the Faculty SANJIV SANGWAN
Discipline CIVIL ENGG.
Semester 6TH
Subject QUANTITY SURVEYING AND VALUATION
Lesson Plan Duration 15 weeks(from January, 2018 to April,2018)
Week Theory
Lecture
Day
Topic
(inculding assignment/test)
1st Introduction to quantity surveying and its importance.
2nd Duties of quantity surveyor
3rd Types of estimates:- Preliminary estimates, Plinth area estimat, Cubic rate estimate
4th Detailed estimate, Definition, Stages of preparation
5th Revision
6th Details of measurement and calculation of quantities and abstract
7th Measurement:- Units of measurement for various items of work as per BIS:1200
8th Rules for measurements
9th Diffe e t ethods of taki g out ua tities – e t e li e ethod a d lo g all a d sho t all method
10th Revision
11th Preparation of Detailed and Abstract Estimates from Drawings for:A small residential
building with a flat roof and pitched roof building comprisin
12th Two rooms with W.C., bath, kitchen and veranda
13th Earthwork for unlined channel
14th WBM road and pre-mix carpetin
15th Revision
16th Single span RCC slab culvert
17th Earthwork for plain and hill roads
18th RCC work in beams, slab, column and lintel, foundation
19th users septic tank - 10 users, - 50 users
20th Revision/Assignment
21st Calculation of quantities of materials for:- Cement mortars of different proportion
22nd Cement concrete of different proportion
23rd Brick/stone masonry in cement morta
24th Brick/stone masonry in cement morta
25th Revision
26th Plastering and pointing
27th White washing, paintin
28th R.C.C. work in slab, beams
29th R.C.C. work in slab, beams
30th Revision
31st Analysis of Rates:- Steps involved in the analysis of rates. Requirement of material,
32nd labour, sundries,
33rd o t a to s p ofit a d o e heads34th o t a to s p ofit a d o e heads35th Revision
36th Analysis of rates for finished items when data regarding labour, rates of material and labour
is given:
37th Earthwork in excavation in hard/ordinary soil and filling with a concept of lead and lif
6th
1st
2nd
3rd
4th
5th
7th
8th
38th RCC in roof slab/beam/lintels/columns
39th RCC in roof slab/beam/lintels/columns
40th Revision
41st Brick masonry in cement mortar
42nd Cement Plaste
43rd White washing, painting
44th Stone masonry in cement mortar
45th Revision
46th Running and maintenance cost of construction equipment
47th Running and maintenance cost of construction equipment
48th Contractorship:- Meaning of contract
49th Qualities of a good contractor and their qualifications
50th Revision
51st Essentials of a contract
52nd Types of contracts, their advantages, dis-advantages
53rd Types of contracts, their advantages, dis-advantages
54th Suitability, system of payment
55th Revision
56th Single and two cover-bids; tender, tender forms and documents,
57th Tender notice, submission of tender and deposit of earnest money
58th security deposit, retention money, maintenance period
59th Classification and types of contracting firms/construction companies
60th Revision/Assignment
61st Preparation of Tender Document based on Common Schedule Rates (CSR):- Introduction to
CSR and calculation of cost based on premium on CSR
62nd Exercises on writing detailed specifications of different types of building works from
excavation to foundations, superstructure and finishing operation
63rd Exercises on preparing tender documents for the following:-Earth work
64th Construction of a small house as per given drawing
65th RCC works
66th Pointing, plastering and flooring, White-washing, distempering and painting
67th Wood work including polishing , Sanitary and water supply installations
68th False ceiling, aluminum (glazed) partitioning
69th Tile flooring including base course, Construction of W.B.M/Concrete road
70th Exercises on preparation of comparative statements for item rate contrac
71st Valuation:-Purpose of valuation, principles of valuation
72nd Definition of various terms related to valuation like depreciation, sinking fund, salvage and
s ap alue, a ket alue, fai e t, ea s pu hase et73rd Definition of various terms related to valuation like depreciation, sinking fund, salvage and
s ap alue, a ket alue, fai e t, ea s pu hase et74th Methods of valuation (i) replacement cost method (ii) rental return
75th Revision/Assignment
13th
14th
15th
9th
10th
11th
12th
Name of the Faculty RAVI NANDAL
Discipline CIVIL ENGG.
Semester 6TH
Subject CONSTRUCTION MANAGEMENT AND ACCOUNTS
Lesson Plan Duration 15 weeks(from January, 2018 to April,2018)
Week Theory
Lecture
Day
Topic
(inculding assignment/test)
1st CONSTRUCTION MANAGEMENT:Introduction:
2nd Significance of construction management
3rd Main objectives of construction management and overview of the subject
4th Functions of construction management, planning, organising,
5th Revision
6th Staffing, directing, controlling and coordinating, meaning of each of these with respect to
construction job.
7th staffing, directing, controlling and coordinating, meaning of each of these with respect to
construction job.
8th Classification of construction into light, heavy and industrial construction
9th Stages in construction from conception to completion
10th Revision
11th The construction team: owner, engineer,
12th Architect and contractors, their functions and inter-relationship
13th Construction Planning:- Importance of construction planning
14th Stages of construction planning:- Pre-tender stage, Contract stage
15th Revision
16th Scheduling construction works by bar charts:- Definition of activity, identification of activities
17th Preparation of bar charts for simple construction work
18th Preparation of schedules for labour, materials, machinery and finances for small works
19th Limitations of bar charts
20th Revision/Assignment
21st Scheduling by network techniques, Introduction to network techniques; PERT and CPM
22nd Differences between PERT and CPM terminology
23rd Organization-Types of organizations: Line,
24th line and staff, functional and their characteristics
25th Revision
26th Site Organization:-Principle of storing and stacking materials at site
27th Location of equipment
28th Preparation of actual job layout for a buildin
29th Organizing labour at site
30th Revision
31st Construction Labour:Conditions of construction workers in India
32nd wages paid to workers
33rd Important provisions of the following Acts:-Labour Welfare Fund Act 1936 (as amended)
34th Labour Welfare Fund Act 1936 (as amended)
35th Revision
6th
1st
2nd
3rd
4th
5th
7th
36th Payment of Wages Act 1936 (as amended)
37th Payment of Wages Act 1936 (as amended)
38th Minimum Wages Act 1948 (as amended)
39th Minimum Wages Act 1948 (as amended)
40th Revision/Assignment
41st Control of Progress:-Methods of recording progress
42nd Analysis of progress
43rd Taking corrective actions keeping head office informed
44th Cost time optimization for simple jobs -
45th Revision
46th Direct and indirect cost,
47th variation with time
48th cost optimization
49th Inspection and Quality Control:;-Need for inspection and quality control
50th Revision
51st Principles of inspection
52nd Stages of inspection and quality control for Earth work
53rd RCC
54th Sanitary and water supply service
55th Revision
56th A ide ts a d Safet i Co st u tio :A ide ts – auses a d e edies57th Safety measures for,:- Excavation work, Drilling and blasting -
58th Hot bituminous works - Scaffolding, ladders, form work - Demolitions
59th Safety campaign and safety devices
60th Revision
61st ACCOUNTS:-Public Work Accounts:Introduction, technical sanction, administrative approval
62nd Allotment of funds, reappropriation of funds bill
63rd Contractor ledger, measurement book running and final account bills complete, preparation
of bill of quantities (BOQ),
64th Completion certificate & report, hand receipt,
65th Aquittance roll. Muster Roll labour,
66th Casual labour roll-duties and responsibility of different cadres,
67th Budget-stores, returns, account of stock,
68th Mis . P.W. ad a es T & P – e ifi atio , su e epo t, oad etal ate ial ha ged di e t to works,
69th Account - expenditure & revenue head,
70th Revision
71st Remittance and deposit head, defination of cash,
72nd Precaution in custody of cash book, imprest account,
73rd Temporary advance, treasury challan, preparation of final bills.
74th Students must learn to prepare accounts register, stock register
75th Revision/Assignment
13th
14th
15th
8th
9th
10th
11th
12th
Faculty SUBHASH DAHIYA
Discipline CIVIL ENGG.
Semester 4TH
Subject RCC DESIGN
Lesson Plan Duration 15 weeks(from January, 2018 to April,2018)
Week Theory
Lecture
Day
Topic
(inculding assignment/test)
1st Teacher Tought Interaction
2nd Concept of Concrete RCC & Its application in field
3rd Reinforceing material & its suitability.
4th Steel as most suitable mat. And its types
5th Loading on structures as per IS: 875 & its assessment
6th concept. Of design
7th Different phylosphies of design with their merits & demerits
8th Detail of Working stress method
9th Detail of Limit state method
10th Abstract & 1st assignment to students
11th Concept of Shear stress, Nominal, average & maximum shear stress.
12th Shear strength of concrete &desgine of beam against shear stress on basis of Working stress
method as per IS: 456- 2000.
13th Max.permissible resistance of conc.&Types of shear reinforcement
14th Design Problem.
15th Design Problem.
16th Singly Reinforced Beam (Working stress method):- Basic assumption in design of RCC beam
17th stress& strain curve, safe permissible stresses in steel conc. As per IS :456
18th Neutral axis, balanced, underreinforcement and over reinforced beams,
19th Moment of resistance for singly reinforced beam.
20th Problem Practice
21st Design of singly reinforced beam including sketches showing reinforcement details.
22nd Contd.
23rd Concept of Limit State Method:- Definitions and assumptions made in limit state of collapse (flexure)
24th Study of limit states method
25th Characteristics& design values of load &strenght of materials
26th Contd.
27th Analysis of singly reinforced beam includes stress block parameters
28th Contd.
29th Contd.
30th Problem practice
31st Singly Reinforced beam
32nd Singly Reinforced beam
33rd Theory and design of singly reinforced beam by Limit State Method
34th Theory and design of singly reinforced beam by Limit State Method
35th Revision
6th
1st
2nd
3rd
4th
5th
7th
36th Doubly Reinforced Beams:- Theory and design of simply supported doubly reinforced rectangular
beam by
Limit State Method
37th Contd.
38th PROBLEM PRACTICE
39th PROBLEM PRACTICE
40th Tutorials
41st Behaviour of T beam,
42nd Inverted T beam,
43rd Isolated T beam
44th L ea s45th Revision
46th One Way Slab:-Theory and design of simply supported one way slab including sketches showing
reinforcement details (plan and section) by Limit State Method..
47th Contd.
48th Design problem.
49th Contd.
50th Tutorials
51st Two Way Slab:-Theory and design of two-way simply supported slab with corners free to lift, no
provisions for torsional reinforcement by Limit State Method including sketches
showing reinforcement details (plan and two sections)
52nd Contd.
53rd Design Problem.
54th Design Problem.
55th Third Assigment
56th Axially Loaded Column:- Definition and classification of columns
57th Effective length of column,
58th Specifications for longitudinal
59th lateral reinforcement
60th Revision
61st Design of axially loaded square,
62nd rectangular and circular short columns by Limit State Method including sketching of
reinforcement(sectional elevation and plan)
63rd Contd.
64th Design Problem.
65th Tutorials
66th Prestressed Concrete
67th Concept of pre-stressed concrete
68th Contd.
69th Methods of pre-stressing : pre-tensioning a
70th Abstract
71st Advantages and disadvantages of prestressing
72nd Contd.
73rd Losses in pre-stress
74th Contd.
75th ABSTRACT & 4th assignment
13th
14th
15th
8th
9th
10th
11th
12th
Faculty DALBIR SINGH
Discipline CIVIL ENGG.
Semester 4TH
Subject WATER SUPPLY AND WASTE WATER ENGINEERING
Lesson Plan Duration 15 weeks(from January, 2018 to April,2018)
Week Theory Practicals
Lecture
Day
Topic
(inculding assignment/test)
Practical
Day
Topic
1st WATER SUPPLY:- Introduction :-Necessity and brief description
of water supply system
2nd WATER SUPPLY:- Introduction :-Necessity and brief description
of water supply system
3rd Quantity of Water:- Water requirement,
4th Rate of demand and variation in rate of demand
5th Fire fighting uses as per BIS standards (no numerical problems)
6th Fire fighting uses as per BIS standards (no numerical problems)
7th Population Forecasting
8th Quality of Water:- Meaning of pure water and methods of
analysis of water
9th Physical, Chemical and bacteriological tests and their
significance
10th Standard of potable water as per Indian Standard
11th Maintenance of purity of water (small scale and large scale
quantity)12th Water Treatment (brief introduction):- Sedimentation -
purpose, types of sedimentation tanks
13th Coagulation floculation - usual coagulation and their feeding
14th Filtration - significance, types of filters, their suitability
15th Necessity of disinfection of water, forms of chlorination, break
point chlorine,16th residual chlorine, application of chlorine.
17th Flow diagram of different treatment units, functions of (i)
Areation fountain (ii) mixer 18th (iii) floculator, (iv) classifier,
19th (v) slow and rapid sand filters (vi) chlorination chamber.
20th Conveyance of Water:-Different types of pipes - cast iron, PVC,
steel, asbestos cement, concrete and lead pipes21st Their suitability and uses, types of joints in different types of
pipes.
22nd Appurtenances: Sluice, air, reflux valves, relief valves, scour
valves, bib cocks, stop cocks
23rd fire hydrants, water meters their working and uses
24th Distribution site: Requirement of distribution, minimum head
and rate, methods of layout of distribution pipes
25th Systems of water supply - Intermittent and continuous service
reservoirs - types, necessity and accessories.26th Wastage of water - preventive measures
viva-voice
To determine turbidity of water
sample
To determine dissolved oxygen of
given sample
To determine pH value of water
To determine residual chlorine in
water
To determine conductivity of water
and total dissolved solids
viva-voice
11th
10th
To perform jar test for coagulation
5th viva-voice
6th viva-voice
7th To determine BOD of given sample
1st
2nd
3rd
4th
1st
2nd
3rd
8th
9th
4th
5th
6th
27th Maintenance of distribution system, Leakage detection
28th Laying out Pipes:-Setting out alignment of pipes
29th Excavation for laying of pipes and precautions to be taken in
30th Handling, lowering beginning and jointing of pipes
31st Testing of pipe lines
32nd Back filling, Use of boring rods
33rd Building Water Supply:-Connections to water main (practical
34th Water supply fixtures and installations and terminology related
to plumbin
35th Water supply fixtures and installations and terminology related
to plumbin
36th WASTE WATER ENGINEERING:- Introduction, Purpose of
sanitation, Necessity of systematic collection and disposal of
waste37th Definition of terms in sanitary engineering, Collection and
conveyance of sewage
38th Conservancy and water carriage systems, their advantages and
Disadvantage
39th (a) Surface drains (only sketches) : various types, suitability
40th (b) Types of sewage: Domestic, industrial, storm water and its
seasonal variation
41st Sewerage System:- Types of sewerage systems, materials for
sewers
42nd their sizes and joints
43rd Appurtenance: Location, function and construction features
44th Manholes, drop manholes, tank hole, catch basin,
45th inverted siphon, flushing tanks grease and oil traps, storm
regulators, ventilating shafts
46th Laying and Construction of Sewers:Setting out/alignment of
sewers
47th Excavations, checking the gradient with boning rods
preparation of bedding,
48th handling and jointing testing and back filling of sewers/pipes.
49th Revision
50th Sewage characteristics:Properties of sewage and IS standards
for analysis of sewage
51st Physical, chemical and bacteriological parameters
52nd Natural Methods of Sewerage Disposal:-General composition
of sewage and disposal methods
53rd Disposal by dilution
54th Self purification of stream
55th Disposal by land treatment
56th Nuisance due to disposal
57th Sewage Treatment:-Meaning and principle of primary and
secondary treatment and activated sludge process their flow
diagram
viva-voice
Study of water purifying process by
visiting a field lab.
Study of water purifying process by
visiting a field lab.
viva-voice
To test house drainage
To demonstrate the laying of SW
pipes for sewers
viva-voice
viva-voice
To study the installation of following
a) Water meter b) Connection of
water supply of building with main c)
Pipe valves and bends d) Water
supply and sanitary fittings
To study and demonstrate the
joining/threading of GI Pipes, CI Pipes,
SW pipes, D.I. pipes and PVC pipes.
viva-voice
viva-voice
To demonstrate the laying of SW
pipes for sewers
23th
20th
21th
22th
17th
18th
19th
14th
15th
16th
11th
12th
13th
7th
8th
9th
10th
11th
12th
58th Introduction and uses of screens, grit chambers,
59th detritus tanks, skimming tanks, plainsedimentation tanks,
60th primary clarifers, secondary clarifers,
61st filters, control beds, intermittent sand filters, trickling filters,
62nd sludge treatment and disposal, oxidation ponds (Visit to a
sewage treatment plant)
63rd Building Drainage:-Aims of building drainage and its
64th Building Drainage:-Aims of building drainage and its
requirements
65th Different sanitary fittings and installations
66th Different sanitary fittings and installations
67th Traps, seals, causes of breaking seals
68th Traps, seals, causes of breaking seals
69th Revision of previous Question paper
70th Revision of previous Question paper
71st Revision of previous Question paper
72nd Revision of previous Question paper
73rd Revision of previous Question paper
74th Revision of previous Question paper
75th Revision of previous Question paper
To test house drainage
viva-voice
viva-voice
viva-voice
viva-voice
29th viva-voice
30th viva-voice
26th
27th
28th
24th
25th
15th
13th
14th
Name of the Faculty S S NANDAL
Discipline CIVIL ENGG.
Semester 4TH
Subject IRRIGATION ENGINEERING
Lesson Plan Duration 15 weeks(from January, 2018 to April,2018)
Week Theory
Lecture
Day
Topic
(inculding assignment/test)
1st Introduction:Definition of irrigation, Necessity of irrigation
2ndHistory of development of irrigation in India, Major, medium and
minor irrigation projects
3rd Discussion on various water resources
4thWater Requirement of Crops:-Principal crops in India and their water
requirements
5th C op seaso s – Kha if a d Ra i
6th Soil water, soil crop and water relationships,
7th duty, delta and base period, their relationship
8th Gross commanded area (GCA), culturable commanded area (CCA),
9th intensity of irrigation, irrigable area
10thHydrological Cycle Catchment Area and Run-off:-Rainfall , definition
ai -gauges – auto ati a d o -auto ati ,
11th methods of estimating average rainfall (Arithmatic system)
12th catchment area runoff, factors affecting runoff,
13th hydrograph, basic concept of unit hydrograph.
14th Important definations about hydrology
15th Methods of irrigation systems
16th Methods of Irrigation:-Flow irrigation - its advantages and limitation
17th Lift I igatio – Tu e ell a d ope ell i igatio
18th Their advantages and disadvantages
19th Sprinkler irrigation conditions favourable and essential requirements
for sprinkler irrigation,
20th sp i kle s ste – lassifi atio a d o po e t pa ts
21st Drip irrigation, suitability of drip irrigation,
22nd layout, component parts, advantages
23rd Advantages of various irrgation system
24th Canals:- Classification, apurtenancs of a canal and their functions,
5th
6th
3rd
4th
1st
2nd
25th Sketches of different canal cross-sections (unlined)
26thVarious types of canal lining - their related advantages and
disadvantages,
27thVarious types of canal lining - their related advantages and
disadvantages,
28th sketches of different lined canal x-sections
29th sketches of different lined canal x-sections
30th Breaches and their control
31st Maintenance of lined and unlined canals
32nd Practice on sketches of differents canal system
33rdTube Well Irrigation:-Introduction, occurrence of ground water,
location and command,
34th Advantages and disadvantages, comparison with canal irrigation
35thTube wells, explanation of terms: water table, radius of influence,
depression head, cone of depression
36thconfined and unconfined aquifers. Yield of a well and methods of
determining yield of well
37th Types of tube wells, cavity, strainer and slotted type;
38th Method of boring, installation of well assembly,
39th development of well, pump selection and installation and
maintenance
40thWater Harvesting Techniques: Need and requirement of various
methods, Run-off from roof top and ground surface
41st construction of recharge pits and recharge wells and their
maintenance.
42nd Dams:- Classification of dams; earthen dams - types, causes of failure;
43rd crosssection of zoned earthen dams, method of construction
44th g a it da s – t pes, oss-se tio s of a da , ethod of o st u tio
45th Concept of small and micro dams
46th Concept of spillways and energy dissipator
47th Canal Head Works and Regulatory Works:-Definition, object, general
48th Difference between weir and barrage
49th Cross Drainage Works:-Functions and necessity of the following
50th Sketches of the above cross drainage works
51st Types of head regulators
52ndDefinitions of following Hydraulic Structures with Sketches:-Falls,
Cross and head regulators
53rd Outlets, Canal Escapes
54thRiver Training Works:-Methods of river training, guide banks, retired
(levees) embankments, groynes
55th Spurs, pitched island, cut-off
56th
Water Logging and Drainage and Ground Water Re-charge:-Definition
of ate loggi g – its auses a d effe ts, dete tio , p e e tio a d remedies
57th Reclamation of soil,
58th Surface and sub-surface drains and their layout
15th
13th
14th
11th
12th
10th
7th
8th
9th
59th Concept and various techniques used for ground water re-charge
60th Revision of previous question papers
Faculty RAVI NANDAL
Discipline CIVIL ENGG.
Semester 4TH
Subject SURVEYING – IILesson Plan Duration 15 weeks(from January, 2018 to April,2018)
Week Theory Practicals
Lecture
Day
Topic
(inculding assignment/test)
Practical
Day
Topic
1st Contouring:-Concept of contours, purpose of contouring,
contour interval and horizontal equivalent,1st
Contouring:-Preparing a contour plan
by radial line method by the use of a
Tangent Clinometer/Tachometer
2nd factors effecting contour interval, characteristics of
contours, methods of contouring: 2nd Prepartion of master sheet
3rd Direct and indirect, use of stadia measurements in
contour survey, interpolation of contours; use of contour
map
3rdPreparing a contour plan by method of
squares
4th Drawing cross section from a contour map; marking
alignment of a road, railway and a canal on a contour map, 4th Prepartion of master sheet
5th computation of earth work and reservoir capacity from a
contour map 5th
Preparing a contour plan of a
Road/Railway track/Canal by taking
cross sections
6th Theodolite Surveying:Working of a transit vernier
theodolite, axes of a theodolite and their relation;
temporary adjustments of a transit theodolite6th Prepartion of master sheet
7th concept of transiting, swinging, face left, face right and
changing face7th
Theodolite:Taking out the Theodilite,
mounting on the tripod and placing it
back in the box
8th measurement of horizontal and vertical angles. Prolonging
a line (forward and backward) 8thStudy of a transit vernier theodolite;
temporary adjustments of theodolite
9th measurement of bearing of a line; traversing by included
angles and deflection angle method; 9th
Reading the vernier and working out
the least count, measurement of
horizontal angles by repetition and
10th traversing by stadia measurement, theodolite
triangulation,10th
Measurement of vertical angles and
use of tachometric tables
11th Plotting a traverse; concept of coordinate and solution of
omitted measurements (one side affected), 11th Exercise/viva-voice
12th errors in theodolite survey and precautions taken to
minimize them; limits of precision in theodolite traversing. 12thMeasurement of magnetic bearing of
a line
13th Height of o je ts – a essi le a d o -a essi le ases13th
Running a closed traverse with a
theodolite (at least five sides) and its
plotting14th Tacho-metric surveying:-Tachometry, Instruments to be
used in tachometry 14thHeight of objects with and without
accessible bases
15th methods of tachometry, stadia system of tachometry,15th
Height of objects with and without
accessible bases
16th general principles of stadia tachometry,
16th Exercise/viva-voice
7th
8th
6th
1st
2nd
3rd
4th
5th
17th examples of stadia tachometry and Numerical problems.
17th Exercise/viva-voice
18thCurves:Simple Circular Curve: Need and definition of a
simple circular curve; Elements of simple circular curve -
Degree of the curve, radius of the curve
18th
Curves:-Setting out of a simple circular
curve with given data by the following
methods a) Offsets from the chords
produced b) One theodolite method19th
(Apex point), tangent point, length of curve,
19th
Curves:-Setting out of a simple circular
curve with given data by the following
methods a) Offsets from the chords
produced b) One theodolite method
20th
long chord deflection angle,
20th
Minor instruments:-Demonstration
and use of minor instruments like
Ceylon Ghat Tracer, Tangent
Clinometer, Pantagraph, Abney level
etc
21st Apex distance and Mid-ordinate. Setting out of simple
circular curve: By linear measurements only: - Offsets from
the tangent
21st Use of planimeter for computing areas
22nd - Successive bisection of arcs - Offsets from the chord
produced b) By tangential angles using a theodolite 22nd Use of planimeter for computing areas
23rd b) By tangential angles using a theodolite 23rd Exercise/viva-voice
24th Revision/Assignment
24th
Demonstration of digital instruments
through field visits to Survey of India
and other government agencies.
25th Introduction to the use of Modern Surveying equipment
and techniques such as: a) EDM or Distomat b) Planimeter 25th Total Station (only demonstrations).
26th c) Total station d) Introduction to remote sensing, GIS and
GP26th Total Station (only demonstrations).
27th Minor Instruments:-Introduction and use of minor
instruments like Ceylon Ghat Tracer, Clinometer,
Pantagraph, Abney Level etc
27th Exercise/viva-voice
28th Use of planimeter for computing areas28th Exercise/viva-voice
29th Revision 29th Exercise/viva-voice
30th Assignment 30th Exercise/viva-voice
13th
14th
15th
9th
10th
11th
12th
Name of the Faculty BALRAJ SINGH
Discipline CIVIL ENGG.
Semester 4TH
Subject IRRIGATION ENGINEERING
Lesson Plan Duration 15 weeks(from January, 2018 to April,2018)
Week Drawings
Lecture
Day
Topic
(inculding assignment/test)
1st
2nd
3rd
4th
5th
6th
7th
8th
9th
10th
11th
12th
13th
14th
15th
16th
17th
18th
19th
20th
21st
22nd
IRRIGATION ENGINEERING DRAWING::-Typical cross-section of a
channel - L-section of a channel for given data
Typical cross section of an unlined and lined channel in cutting, partly
cutting and partly filling and fully in filling with given design data
Layout plan of a canal head works
WATER SUPPLY AND WASTE WATER ENGINEERING DRAWING:-Drains
and Sewers
Cross section of standard types of open drains (circular, v-shaped and
Traps, manholes and inspection chamber, Detailed section of floor
trap and gully trap
Detailed plan and section of a manhole:-Detailed plan and cross
sections of a domestic septic tank with soak pit for 10 and 50 users
Plan of a bathroom showing positions of lavatory, bath tub, wash-
basin, taps and showers
1st
2nd
3rd
4th
23rd
24th
25th
26th
27th
28th
29th
30th
31st
32nd
33rd
34th
35th
36th
37th
38th
39th
40th
41st
42nd
43rd
44th
45th
46th
47th
48th
49th
50th
51st
52nd
53rd
54th
55th
Layout plan of a canal head works
Draw the typical L-section of a weir
Practice of reading water supply and sanitary engineering working
drawings (PWD/urban Development agencies) including hot water
and cold water supply system of a two room set
Detailed Layout Plan of Sewage Treatment Plant for a residential
area and Effluent Treatment Plant for an industrial unit.
Sheet Checking and viva-voice
Sheet Checking and viva-voice
Bath room and W.C connections:-Cross-section through the external
wall of lavatories at ground and first floor showing the one and two
7th
8th
9th
10th
Zoned type
Diaphragm type
Cross section of earthen ware and RCC sewer pipes Cross sections of
masonry sewers (circular and egg shaped)
Detailed plan and section of an inspection chamber , Detailed plan
and section of a manhole
Draw the X-section of an Earthen Dam:-Homogeneous
6th
5th
56th
57th
58th
59th
60th
61st
62nd
63rd
64th
65th
66th
67th
68th
69th
70th
71st
72nd
73rd
74th
75th
76th
77th
78th
79th
80th
81st
82nd
83rd
84th
85th
86th
87th
88th
89th
90th
Cross section of a tube well
Layout and cross section of rain water harvesting system
Sheet Checking and viva-voice
Sheet Checking and viva-voice
Draw sectional elevation of a two storeyed building showing details
of one pipe and two pipes systems with sanitation system
Practice of reading water supply and sanitary engineering working
drawings (PWD/urban Development agencies) including hot water
and cold water supply system of a two room set
Detailed Layout Plan of Sewage Treatment Plant for a residential
area and Effluent Treatment Plant for an industrial unit.
Cross section of a tube well
Layout and cross section of rain water harvesting system
13th
14th
15th
wall of lavatories at ground and first floor showing the one and two
pipe system and the connections of the lavatory to inspection
11th
12th
Sheet Checking and viva-voice
Sheet Checking and viva-voice
Lesson Plan
Faculty VIKASH NARWAL
Discipline CIVIL ENGG.
Semester 4th
Subject CONCRETE TECHNOLOGY
Lesson Plan Duration 15 weeks(from January, 2018 to April,2018)
Week Theory Practicals
Lecture
Day
Topic (inculding assignment/test)Practical
Day Topic
1st Introduction: Definition of concrete, uses of concrete in comparison to other
building materials. 1stTo determine the physical properties
of cement as per IS Codes
2nd Introduction: Definition of concrete, uses of concrete in comparison to other
building materials.
3rd Ingredients of Concrete: Cement: physical properties of cement; different types of
cement as per IS Codes
4th Aggregates:-Classification of aggregates according to size and shape3rd viva-voice
5th Characteristics of aggregates: Particle size and shape, surface texture, specific
gravity of aggregate; bulk density,
6th water absorption, surface moisture, bulking of sand, deleterious materials,
soundness
7th Grading of aggregates: coarse aggregate, fine aggregate;
5thDetermination of specific gravity and
water absorption of aggregates
8th All-inaggregate; fineness modulus; interpretation of grading charts
9th Water: Quality requirements as per IS:456-2000
10th Water Cement Ratio:-Hydration of cement, principle of water-cement ratio, Duff
A a s Wate - e e t atio la : 7thTo determine surface moisture in fine
aggregate by displacement method
11th Limitations of water-cement ratio law and its effects on strength of concrete
12th Workability:-Workability factors affecting workability
13th Measurement of workability: slump test, compacting factor and Vee Bee
consistometer; 9th
Determination of particle size
distribution of fine, coarse and all in
aggregate by sieve analysis (grading of
aggregate) 14th Recommended slumps for placement in various conditions as per IS:456-2000/SP-
23
15th Revision/Assignment
16th Properties of Concrete:-Properties in plastic state: Workability, 11th viva-voice
17th Segregation, Bleeding and Harshness
18th Properties in hardened state: Strength, Durability,
19th Impermeability, Dimensional changes;13th
To determine workability by slump
test:
20th Proportioning for Normal Concrete:-Objectives of mix design, introduction to
various grades as per IS:4562000; proportioning for nominal mix design as
prescribed by IS 456-2000
21st Adjustment on site for: Bulking of fine aggregate, water absorption of aggregate,
workability
22nd Difference between nominal and controlled concrete
15th
To verify the effect of water, fine
aggregate/coarse aggregate ratio and
aggregate/Cement ratio on slump
23rd Introduction to IS-10262-2009-Code for controlled mix design
24th Revision
25th Introduction to Admixtures (chemicals and minerals) for improving performance of
concrete 17th viva-voice
26th Introduction to Admixtures (chemicals and minerals) for improving performance of
concrete
27th Revision
28th Special Concretes (only features) :- Concreting under special conditions, difficulties
and precautions before, during and after concreting19th Compaction factor test for workability
29th Cold weather concreting , Under water concreting
30th Hot weather concreting
31st Ready mix concrete, Fibre reinforced concrete,Polymer Concrete,
Fly ash concrete, Silica fume concrete 21th
Non destructive test on concrete by:
a) Rebound Hammer Test b)
Ultrasonic Pulse Velocity Test
32nd Concreting Operations: Storing of Cement:Storing of cement in a warehouse,
Storing of cement at site , Effect of storage on strength of cement, Determination
of warehouse capacity for storage of Cement
33rd Storing of Aggregate: Storing of aggregate at site
7th
8th
9th
10th
11th
To determine necessary adjustment
for bulking of fine aggregate
To determine workability by slump
test:
1st
2nd
3rd
5th
6th
To determine flakiness and elongation
index of coarse aggregate
4th
6th
8th
4th
To determine silt in fine aggregate
Determination of bulk density and
voids of aggregates
viva-voice
14th
16th
10th
12th
2nd
18th
20th
22th
To verify the effect of water, fine
aggregate/coarse aggregate ratio and
aggregate/Cement ratio on slump
viva-voice
Compaction factor test for workability
Non destructive test on concrete by:
a) Rebound Hammer Test b)
Ultrasonic Pulse Velocity Test
viva-voice
34th Batching (to be shown during site visit ):- Batching of Cement, Batching of
aggregate, Volume, using gauge box (farma) selection of proper gauge box, Weight
spring balances and batching machines, Measurement of water23th viva-voice
35th Mixing:-Hand mixing, Machine mixing - types of mixers, capacities of mixers,
choosing appropriate size of mixers, operation of mixers, Maintenance and care of
machines
36th Transportation of concrete: Transportation of concrete using: wheel barrows,
transit mixers, chutes, belt conveyors, pumps, tower crane and hoists etc.
37th Placement of concrete:- Checking of form work, shuttering and precautions to be
taken during placement 25th
Tests for compressive strength of
concrete cubes for different grades of
concrete38th Compaction:-Hand compaction, Machine compaction - types of vibrators, internal
screed vibrators and form vibrators, Selection of suitable vibrators for different
situations
39th Finishing concrete slabs - screeding, floating and trowelling
40th Revision 27th viva-voice
41st Curing:-Objectives of curing, methods of curing like ponding, membrane curing,
steam curing, chemical curing, Duration for curing and removal of form work
42nd Jointing: Location of construction joints, treatment of construction joints,
expansion joints in buildings - their importance and location
43rd Defects in concrete: Identification of and methods of repair 29th viva-voice
44th Importance and methods of non-destructive tests (introduction only)
45th Revision/Assignment
13th
14th
15th
12th
24h
26th
28th
30th
viva-voice
viva-voice
viva-voice
Tests for compressive strength of
concrete cubes for different grades of
concrete
C R POLYTECHNIC, Rohtak
Name of Faculty :- Dalbir Singh
Discipline :- CIVIL ENGG. Semester :-6th
Subject :- REPAIR AND MAINTENANCE OF BUILDINGS
lesson plan duration :-15 weeks
Work Load per week(in hours):- Lectures-3,Practicals-0
WEEK
1ST
DAY
2nd
day
3rd
day
1st
day
2nd
day
3rd
day
1st
day
2nd
day
3rd
day
4th
week
1st
day
2nd
day
3rd
day
1st
day
2nd
day
2nd
week
Factors influencing the repairs and maintenance
Definition of deterioration/decay
Factors causing deterioration and their classification
THEORY
1st
week
Importance and significance of repair and maintenance of
buildings
Meaning of maintenance
Objective of maintenance
3rd
week
Human factors causing deterioration, Chemical factors causing
deterioration,Enviromental condition causing deterioration,
Miscellaneous factors
Effects of various agencies of deterioration on various building
materials i.e bricks,stones,timber,concrete,paints,metals
Doubt will be taken and revision
Systematic approach/procedure of investigation
Sequence of detailed steps for diagnosis of building
defects/problems
5th
week
Revison of 3nd
unit
3rd
day
1st
day
2nd
day
3rd
day
1st
day
2nd
day
3rd
day
1st
day
2nd
day
3rdd
ay
1st
day
2nd
day
3rdd
ay
List non destructive and others tests on structural elements and
materials to evaluate the condition of the building
6th
week
Define defects in buildings and classification of defects
Building defects in various building elements Foundations
,basements and DPC,Walls,Column and beams, roof and
terrace, and defects caused by dampness
Compatibility aspects of repairs materials
Anti corrosion coatings, Adhesive bonding aids, repairs
mortars, curing compound, joints sealants, protective coating
7th
week
Revision of 4th
and 5th
unit and Doubt willl be taken
Preventive maintenance consideration and surface preparation
technique for repairs
Crack repairs method
Epoxy injection, Grooving and sealing,stitching,adding
reinforcement and grouting
8th
week
Repairs of surface defects of concrete
-Bug holes
Form tie holes, honey comb and larger voids
-Repairs of corrosion in RCC elements
-Steps in repairing
-prevention of corrosion in reinforcement
9th week
Materials placement technique with sketches
-Pneumatically applied, open top placement, bird mouth
,dry packing, form and pump, trowel applied method
Revision and Test will be given
1st
day
2nd
day
3rdd
ay
1st
day
2nd
day
3rdd
ay
1st
day
2nd
day
3rdd
ay
1st
day
2nd
day
3rdd
ay
1st
day
2nd
day
3rdd
ay
1st
day
2nd
day
3rdd
ay
10th
week
Repairs of DPC against rising dampness
-physical method, electrical method, chemical method
Doubt will be taken
11th
week
Repairs of walls
-repairs of mortars joints against leakage
-Efflorescence removal
Water proofing of wet areas ,water proofing of flat RCC roofs
Various water proofing system and their characterstitics
12th
week
Types of sealing joints with different types of sealants
Technique for repairs of joints and repair of overhead and
underground water tanks
Doubt will be taken
15th
week
Revision of 6th
unit
DOUBT WILL BE TAKEN
COMBINED TEST OF ALL UNIT
13th
week
Revision of 1st unit
Revision of 2nd
t unit
Revision of 3rd
unit
14th
wee
Unit test will be given
Revision of 4th
unit
Revision of 5th
unit
Top Related