Provincial Road Development Project (PRDP)
In Central & Sabaragamuwa Provinces. Loan No. SL-P96
Introduction of Project
JICA Funded Provincial Road Development Project Operating under the Ministry of Local
Government & Provincial Councils has launched a Project for the rehabilitation of Provincial
Road Network at Central & Sabaragamuwa Provinces.
The Project is implemented in 41 Road contract packages in 03 Phases through local
contractors. Ministry has established a Project Management Unit (PMU) headed by the
National Project Director in Colombo for the implementation of the Project. Respective
Provincial Councils has set up two Project Implementation Units (PIUs) headed by the
Provincial Project Director in Central and Sabaragamuwa Provinces.
Funding Agency
Japan International Cooperation Agency (JICA)
Justification and Objectives
To contribute to the development of local economy through the improvement of the service
level of Road Network by rehabilitating and upgrading of secondary roads (C and D class
road) and bridges in Central and Sabaragamuwa Provinces.
Capacity building of the Ministry, PMU, PIU and Roads Agencies in Provincial Councils and
Road Contractors, in order to maintain the road network efficiently.
Project Components and Activities
1. Rehabilitation & Upgrading of Secondary Roads and Bridges
2. Consulting services for selection of Roads, Design works and Construction
Supervision.
3. Capacity building of the Ministry, Roads Agencies in Provincial Councils and Road
Contractors, in order to maintain the road network efficiently.
Project Duration
05 years (2010 - 2015)
Project Financial Details :
• From JICA - 9,156 Yen Million
• From GOSL - 2,564 Rs. Million
• Total Allocation - 11,171 Yen Million
• Total Value - 14,212 Rs. Million
2
Details of Financial Allocation :
• Civil Works - 7,824 Rs. Million (Yen 6,150 Million)
• Equipment - 204 Rs. Million (Yen 160 Million)
• Price Escalation - 2,288 Rs. Million (Yen 1,798 Million)
• Physical Contingency - 516 Rs. Million (Yen 405 Million)
• Consultancy - 856 Rs. Million (Yen 673 Million)
• Administration - 584 Rs. Million (Yen 459 Million)
• Tax & Duties - 1,436 Rs. Million (Yen 1,129 Million)
• Interest during Construction - 447.8 Rs. Million (Yen 352 Million)
• Commitment Charges - 56 Rs. Million (Yen 44 Million)
TOTAL VALUE - 14,212 Rs. Million (Yen 11,171 Million)
Expected Output:
(a) Rehabilitation of 350 km of Secondary Roads (C & D Class Roads).
(b) Provision of road maintenance Machinery & Equipments.
(c) Institutional development of Provincial Road Agencies.
Expected Physical Output:
Rehabilitation and upgrading of 350 km of C & D class of Provincial roads at the end of year
2015.
Central Province 163.33 km
Kandy - 86.04 Km
Matale - 18.20 Km
Nuwaraeliya - 59.09 Km
Sabaragamuwa Province 159.44 km Kegalle - 85.80 Km
Rathnapura - 73.64 Km
TOTAL LENGTH 322.77 km
3
Overall Financial Progress US$ = Rs. 125.91
Expenditure up to 31st December 2013 (Foreign)
Expenditure up to 31st December 2013 (GOSL)
US $ Mn. Rs. Mn. Utilized US $ Mn. Rs. Mn. Utilized
41.2 5,187.30 44.53% 4.89 616.32 24.04%
Details of Project Core Staff :
SN Name of Officer Designation Work
Station T.P. Number E-mail Address
01. Eng. A.B. Ilangasinghe National Project
Director
PMU -
Colombo 011 - 2805386 [email protected]
02. Eng. A.M.M. Faleel Provincial Project
Director PIU - Central 081 - 2213600 [email protected]
03. Eng. W.K.A.S.
Chandraratne
Provincial Project
Director
PIU -
Sabaragamuwa 045 - 2226080 [email protected]
04. Eng A.A.D. Sarath Kumara Procurement
Specialist
PMU -
Colombo 011 - 2805412 [email protected]
05. Vacant Office Engineer PMU -
Colombo 011 - 2805412
06. Eng. R.A. Nawamal Office Engineer PIU -
Sabaragamuwa 045 - 2226081
uk
07. Eng. Mrs. E.M.S.D.
Ekanayake Office Engineer PIU - Central 081 - 2203884 [email protected]
08. Mr. S. Nandasiri Project
Accountant
PMU -
Colombo 011 - 2808947 [email protected]
09. Mr. P.G. Jayantha Accountant PIU -
Sabaragamuwa 045 – 2226081 [email protected]
10. Mr. H.M.S.
Darmawardhena Accountant PIU - Central 081 – 2203884
saliyadharmawardane@
yahoo.com
4
Present Status of the Project (End of December 2013) :
Civil Works :
11 Contract Packages (06 Packages in Central Province & 05 Packages in
Sabaragamuwa Province) under Phase I Contracts, are in progress but behind the
schedule. Some Contracts were in Final stage. However, original contract period is 18
months, at the moment 30 months lapsed by these contracts. The cumulative
Physical Progress of the Phase I contracts for end of December 2013 is around
73%.
16 Contract Packages under Phase II-1 & Phase II-2 contracts in Central Province
(Originally 07 Contracts, after slicing small packages) were awarded and works are in
progress. The cumulative Physical Progress of the Phase II-1 & Phase II-2
contracts of Central Province for end of December 2013 is 46%. However, 2/3 of
Schedule period were elapsed for these contracts.
11 Contract Packages under Phase II-1 & Phase II-2 contracts in Sabaragamuwa
Province were awarded and works are in progress. The cumulative Physical
Progress of the Phase II-1 & II-2 contracts of Sabaragamuwa Province for end
of December 2013 is also around 43%. However, 2/3 of Schedule period were
elapsed for these contracts too.
Procurement of Road Maintenance Machinery & Equipments :
Procured and provided Road Maintenance Machinery & Equipments to Road
Maintenance Divisions in Central & Sabragamuwa Provinces for capacity
development of respective provincial road organizations.
Procurement of Road Maintenance Machinery in Central Province was completed
and Handed over to Central Province. Procurement of Road Maintenance Machinery
in Sabaragamuwa Province is in progress.
5
Phase I Contract Details : (Central Province )
Dis
tric
t
Package
No.
Name & Address of
Selected contractor Name of the Road
Length
(km)
Accepted value
of the Contract
(without VAT)
Phy.
Progress
Up to
Dec.
2013
Fin.
Progress
Up to
Dec.
2013
Complet
ed
asphalt
length
(km)
Kan
dy
CP1KD1 V.V. Karunarathna &
Company
No. 579, Bulugaha
Jaunction, Kandy Road,
Kelaniya.
Theldeniya Cobersts
Gap 14.50 360,153,786.40 94.61% 86.04% 14.50
CP1KD2
Karalliyadda –
Putuhapuwa -
Werapitiya
10.40 369,172,204.90 75.52% 67.42%
6.17
Madawala - Lewella 4.80 4.12
CP1KD3
Sierra Construction
(Pvt.) Ltd.,
No. 112, Havelock
Road, Colombo 05.
Hurikaduwa -
Narampanawa 7.60
390,202,986.19 76.82% 61.85% 6.37
Sumanathissa Mawatha 5.34 4.13
Kandy District Total 42.64 1,119,528,977.49 35.29
Mat
ale CP1MT1
Star Construction &
Engineers (Pvt.) Ltd.,
No. 337/A, 01st Floor,
Nawala Road,
Rajagiriya.
Thenna – Ovilikanda -
Dodandeniya 9.60 241,890,373.91 67.97% 57.25% 6.58
CP1MT2 Kaduwela – Wehigala –
Leliambe 8.60 228,343,903.92 70.47% 71.54% 4.87
Matale District Total 18.20 470,234,277.83 11.45
N’
Eli
ya
CP1NE1
Sierra Construction
(Pvt.) Ltd.,
No. 112, Havelock
Road, Colombo 05.
Bogahawatta –
Maldeniya - Hedunawa 15.15 449,611,432.35 56.66% 52.80% 6.26
Phase I Contract Details : (Sabaragamuwa Province )
Dis
tric
t
Package
No.
Name & Address of
Selected contractor Name of the Road
Length
(km)
Accepted value
of the Contract
(without VAT)
Phy.
Progress
Up to
Dec.
2013
Fin.
Progress
Up to
Dec.
2013
Comple
ted
asphalt
length
(km)
Keg
alle
SG1KG1
Tissa Builders and
Contractors,
Kandalama,
Meerigama.
Panawala –
Maniyangama 10.40 312,425,644.55 84.60% 60.54% 6.30
SG1KG2
V.V. Karunarathna &
Company
No. 579, Bulugaha
Jaunction, Kandy Road,
Kelaniya.
Horagasmankada –
Algama 7.50
426,223,453.85 73.70% 62.56%
3.70
Thaliyadda –
Imbulowita 7.20 6.60
SG1KG3
Star Construction &
Engineers (Pvt.) Ltd.,
No. 337/A, 01st Floor,
Nawala Road,
Rajagiriya.
Uthuwankanda –
Ussapitiya 5.80
251,995,780.95 58.25% 54.09%
4.80
Manikkawa –
Alutnuwara –
Uyanwatta
(From 3.7 km to 5.4
km)
1.70 --
Kegalle District Total 32.60 990,644,879.35 21.40
6
Dis
tric
t
Package
No.
Name & Address of
Selected contractor Name of the Road
Length
(km)
Accepted value
of the Contract
(without VAT)
Phy.
Progress
Up to
Dec.
2013
Fin.
Progress
Up to
Dec.
2013
Comple
ted
asphalt
length
(km)
Rat
nap
ura
SGRP1-
A
V.V. Karunarathna &
Company, No. 579,
Bulugaha Jaunction,
Kandy Road, Kelaniya.
Pallebedda – Buluthota
(From 0.0 km to 11.2
km)
11.20 300,463,424.00 80.00% 66.60% 7.00
SG1RP1-
B
Nawaloka Construction
Company (Pvt.) Ltd.,
No. 115, Sir James
Peiris Mawatha,
Colombo 02.
Pallebedda – Buluthota
(From 11.2 km to 22.4
km)
11.20 333,346,131.89 82.00% 60.04% 10.20
Ratnapura District Total 87.60 2,615,099,314.59 17.20
Details of Awarded Packages under Phase II - 1 Contracts in Central
Province :
Dis
tric
t
Name of
Package Name of Road
Length
(km)
Name & Address of
Awarded Contractor
Contract
Amount
without VAT
(SL. Rs.)
Phy.
Progress
Up to
Dec.
2013
Fin.
Progres
s
Up to
Dec.
2013
Kan
dy
Hataraliyadda Palagala
Kebbekaduwa Road 16.05
CP2KD4 Hataraliyadda to Weliwita
Junction (From 0+000 to
6+050) km
6.05 M/s. Komuthi Engineering
Services (Pvt.) ltd.,
No. 595, Nawala Road,
Rajagiriya.
238,998,904.80 46.69% 25.85%
CP2KD5 Weliwita junction to
Walpalagolla (From
6+050 to 11+000) km
4.95 153,987,740.25 58.39% 43.50%
CP2KD6 Walpalagolla to
Kobbekaduwa (From
11+000 to 16+050) km
5.05
M/s. Hovel Construction
(Pvt.) Ltd.,
No. 245/47, Avissawella
Road, Orugodawatta.
205,281,521.25 48.88% 32.89%
Ampitiya Udawela Ankelipitiya
Road 15.90
CP2KD7 Ampitiya to Udawela
Junction (From 0+000 to
5+000) km
5.00 M/s. AMSK Construction
(Pvt.) Ltd.,
No. 1/29, New Town,
Madampe.
177,914,234.36 31.52% 32.26%
CP2KD8 Udawela Junction to
Puliyadda (From 5+000
to 10+500) km
5.50 200,080,738.69 34.28% 30.20%
CP2KD9 Puliyadda to Ankelipitiya
(From 10+500 to
15+900) km
5.40 193,778,431.96 35.12% 27.21%
Kandy District Total 31.95 1,170,041,571.31
7
Details of Awarded Packages under Phase II - 2 Contracts in Central
Province :
Dis
tric
t
Name of
Package Name of Road
Length
(km)
Name & Address of
Awarded Contractor
Contract
Amount
without VAT
(SL. Rs.)
Phy.
Progress
Up to
Dec.
2013
Fin.
Progress
Up to
Dec.
2013
Udapussellawa – Nildandahinna –
Wathumulla 24.64
Nu
wara
Eli
ya
CP2NE4
Udapussellawa
Nildandahinna Wathumulla
Section from
Udapussellawa to
Ilukpathana
(From 0+000 to 7+360) km
7.36 M/s. MAGA
Engineering (Pvt.) Ltd.
No. 200, Nawala Road,
Narahenpita,
Colombo 05.
343,701,080.47 56.89% 44.33%
CP2NE5
Udapussellawa
Nildandahinna Wathumulla
Section from Ilukpathana
to Dambagolla
(From 7+360 to 13+120)
km
5.76 272,147,388.42 48.98% 40.00%
CP2NE6
Udapussellawa
Nildandahinna Wathumulla
Section from Dambagolla
to Nildandahinna
(From 13+120 to 18+080)
km
4.96 M/s. Thudawe Brothers
(Pvt.) Ltd.,
No. 505/2, P.O. Box 26,
Elvitigala Mawatha,
Colombo 05.
220,389,917.42 54.12% 41.68%
CP2NE7
Udapussellawa
Nildandahinna Wathumulla
Section from
Nildandahinna to
Wathumulla
(From 18+080 to 24+640)
km
6.56 294,646,234.30 52.66% 25.54%
Hanguranketha - Adhikaragama 8.00
CP2NE8
Hanguranketha
Adikarigama
Section from
Hanguranketha to Malulla
(From 0+000 to 4+300) km
4.30 M/s. NEM Construction
(Pvt.) Ltd.
No. 629, Baseline
Road, Colombo 09.
147,998,600.87 64.69% 38.43%
CP2NE9
Hanguranketha
Adikarigama
Section from Malulla to
Adikarigama
(From 4+300 to 8+000) km
3.70 132,206,373.77 69.63% 26.27%
Brookside – Mahakudugala –High
Forest 11.30
N’ E
liya
CP2NE10
Brookside Mahakudugala
High Forest
Section from Brookside to
High Forest Tea Factory
Junction
(From 0+000 to 6+300) km
6.30
M/s. W.G.M.M.
Padmini Construction
(Pvt.) Ltd.
No. 37, Jayathilaka
Mawatha, Panadura.
287,496,136.55 40.78% 25.60%
8
Dis
tric
t
Name of
Package Name of Road
Length
(km)
Name & Address of
Awarded Contractor
Contract
Amount
without VAT
(SL. Rs.)
Phy.
Progress
Up to
Dec.
2013
Fin.
Progress
Up to
Dec.
2013
CP2NE11
Brookside Mahakudugala
High Forest
Section from High Forest
Tea Factory Junction to
End
(From 6+300 to 11+300) km
5.00
M/s. Anthony Builders,
Diyakalamulla,
Kuliyapitiya.
207,700,833.47 40.59% 24.14%
Nuwara Eliya District Total 55.24 1,906,286,565.27
Kan
dy
CP2KD10 Delthota Bopitiya
(From 0+000 to 6+720) km 6.72 M/s. M.R. Henry &
Company,
No. 72, Munathunga
Mawatha, Homagama.
212,953,776.60 28.40% 17.55%
CP2KD11
Thalathuoya
Kandakeputenna
(From 0+000 to 5+000) km
5.00 179,322,559.50 22.15% 17.54%
Kandy District Total 11.72 392,276,336.10
Details of Awarded Packages under Phase II - 1 Contracts in
Sabaragamuwa Province :
Dis
tric
t
Package
No. Name of the Road
Length
(km)
Name & Address of
Selected contractor
Accepted value
of the Contract
(without VAT)
Phy.
Progress
Up to
Dec.
2013
Fin.
Progress
Up to
Dec.
2013
Complet
ed
asphalt
length
(km)
Ratn
ap
ura
SG2RP1 Lellopitiya
Hettikanda 11.00
M/s. Thudawe Brothers
(Pvt.) Ltd.,
No. 505/2, P.O. Box 26,
Elvitigala Mawatha,
Colombo 05.
435,133,715.90 47.00% 44.32% 3.00
SG2RP2 –
A
Muwagama
Niralgama Alupotha
Yakdehiwatta
(From 6+500 to
14+000) km
7.50
M/s. R.N. Construction
(Pvt.) Ltd.,
No. 532/1, Kaduwela
Road, Thalahena,
Battaramulla.
368,227,696.52 24.50% 24.90% 1.00
SG2RP3 –
A
Kotamulla
Karangoda
Dimiyawa
(From 6+500 to
13+600) km
7.10
M/s. R.R. Construction
(Pvt.) Ltd.,
No. 865, Dr. Danister
De Silva Mawatha,
Wellampitiya,
Colombo 09.
316,570,533.91 81.77% 48.18% 5.66
Total for Ratnapura District 25.60 1,119,931,946.33 9.66
9
Dis
tric
t
Package
No. Name of the Road
Length
(km)
Name & Address of
Selected contractor
Accepted value
of the Contract
(without VAT)
Phy.
Progress
Up to
Dec.
2013
Fin.
Progress
Up to
Dec.
2013
Complet
ed
asphalt
length
(km)
Keg
all
e
SG2KG1 Annasigala
Bolagama
Paththampitiya
9.60 M/s. Star Construction
& Engineers (Pvt.) Ltd.,
No. 337/A, 01st Floor,
Nawala Road,
Rajagiriya.
293,902,198.45 58.00% 40.02% --
SG2KG2 Mabopitiay
Parambe Estate
(Via Dampelgoda)
8.20 286,800,480.60 47.00% 40.91% --
Total for Kegalle District 17.80 580,702,679.05
Details of Awarded Packages under Phase II - 2 Contracts in
Sabaragamuwa Province :
Dis
tric
t
Package
No. Name of the Road
Length
(km)
Name & Address of
Selected contractor
Accepted value
of the Contract
(without VAT)
Phy.
Progress
Up to
Dec.
2013
Fin.
Progress
Up to
Dec.
2013
Comple
ted
asphalt
length
(km)
Ratn
ap
ura
SG2RP3 -
B
Kotamulla
Karangoda
Dimiyawa
(From 0+000 to
6+500) km
6.50
M/s. Akila Engineering
(Pvt.) Ltd.
No. 180/60,
Jayawimana Watta,
Siyambalagoda,
Polgasowita.
255,807,105.92 19.72% 29.91% --
SG2RP4
Getaheththa
Karandana Madala
(From 7+200 to
15+340) km
8.14
M/s. Anthony Builders,
Diyakalamulla,
Kuliyapitiya.
284,730,303.30 31.09% 22.69% 1.00
SG2RP5
Mawela Welange
Rukkattana
(From 0+000 to
6+000) km
6.00
M/s. Ruhunu
Development
Contractors &
Engineers (Pvt.) Ltd.
No. 42/2, Main Street,
Battaramulla.
270,153,567.85 53.17% 50.31% 1.50
Total for Ratnapura District 20.64 810,690,977.07
2.50
Keg
all
e
SG2KG3
Aranayake
Ambalakanda Kellie
(From 0+000 to
10+700) km
10.70
M/s. V.V. Karunarathna
& Company
No. 579, Bulugaha
Junction, Kandy Road,
Kelaniya.
438,499,725.50 17.93% 21.49% --
10
Dis
tric
t
Package
No. Name of the Road
Length
(km)
Name & Address of
Selected contractor
Accepted value
of the Contract
(without VAT)
Phy.
Progress
Up to
Dec.
2013
Fin.
Progress
Up to
Dec.
2013
Comple
ted
asphalt
length
(km)
SG2KG4
Kotiyakumbura
Aruggammana
(From 0+000 to
4+200) km
4.20 M/s. Hovel
Construction (Pvt.) Ltd.
No. 245/47, Old
Avissawella Road,
Orugodawatta.
367,936,962.84 31.85% 18.22%
0.50
Yatapana Heenwella
(From 0+000 to
3+000) km
7.20km
3.00 --
SG2KG5
Kithulgala Malwatta
(From 0+000 to
5+000) km
5.00
M/s. Ruhunu
Development
Contractors &
Engineers (Pvt.) Ltd.
No. 42/2, Main Street,
Battaramulla.
207,175,782.75 59.00% 23.69%
Total for Kegalle District 22.90 1,013,612,471.09
0.50
Organization Chart for Project Implementation
(Overall)
Normal Communication Line Communication Line when requested
Ministry of Local Government and
Provincial Councils (MLGPC)
Project Management Unit (PMU)
Provincial Project Steering Committees, headed by Chief
Secretary of Respective Province (PPSC)
Project Steering Committee, headed by Secretary, M LG &
PC (PSC)
Project Implementation Units (PIUs)
Project Implementation Consultant (PIC)
(JICA)
Consultant’s Provincial Teams
11
Organization Chart - Project Management Unit (PMU)
Organization Chart - Project Implementation Units (PIUs)
Provincial Project Director
Office Engineer
Accountant
Accounts Clerks
(02)
Computer
Operators (02)
Office Aids
(01)
National Project Director
Project
Accountant
Office
Engineer
Office
Aids (02)
Computer
Operators (02)
Accounts
Clerks (03)
Procurement
Specialist
12
Major Issues/ Problems :
Major Problems Action Taken/to be Taken
01. Procurement of Phase II Contracts in
Central Province were delayed due to
exorbitantly high bid prices received
from bidders.
02. All Contractors failed to achieve
their own targeted progress, due to
inadequate resource mobilization
03. Contract payments in Last quarter of
2013 were delayed due to insufficient
financial allocation. This badly
affected to the progress of Project.
04. Allocation granted in year 2014
also not sufficient.
To overcome this problem, the TEC and CAPC has
recommended to re-bidding the contracts after slicing to
small contracts.
To reduce the delay PMU and PIU staff are also working
with the Engineer’s staff during preparation of Estimates
and Bidding documents.
In order to improve the Contractor’s cash flow, the
following steps were implemented.
01. The minimum Interim Payment Value mentioned in
the Conditions of The Contract (COC) has been
reduced from 4% to 2% to enable the contractors to
be entitled for Interim Payment Certificates (IPCs).
02. As per clause 14.7 in the COC, 56 days have been
allocated for the Engineer and the Employer’s staff to
release the payments for IPC but both parties expedite
their works and release the payments as early as
possible.
03. Most of the contractors were not performing to their
own targets. These contractors are given fortnightly
targets and monitored regularly for the compliance.
Regular meetings are conducted at PMU with higher
management of constructing companies and weekly
targets are set to expedite the progress. Contractors
who are continuously failing to show progress will be
summered again to explain there failures. It has been
decided to issue warnings followed up with “notices
for termination” if the slippage is more than 15%.
Contractors were encouraged to reschedule their
activities to minimize the effects of adverse weather
conditions.
01. Request letters sent to the Ministry of Finance, General
Treasury & Dept. of National Budget to obtain
additional allocation.
02. Balances of 2013 contract payments were paid using
year 2014 allocation.
Necessary actions already taken at increase the year 2014 allocation.