Promoters Tunnel
Presentation
Tim Smart
Head of Engineering & Operations
20th October 2014 1
P653 (1) HOC/10009/0002
Tunnel Briefing Agenda
1. Why tunnel? 2. Operational aspects of tunnels 2.1 Safety requirements 2.2 Noise and vibration 2.3 Aerodynamics and porous portals 2.4 Vent shafts and smoke control 2.5 Energy requirements
3. Construction 3.1 Tunnelling techniques 3.2 Shaft construction 3.3 Settlement 3.4 Rate of tunnelling 3.5 Construction aspects 4. Costs implications 4.1 Costs of tunnelling 4.2 Land costs 4.3 Impact on programme
2
P653 (2) HOC/10009/0003
Tunnels Location
3
P653 (3) HOC/10009/0004
1. Why Tunnel? Terrain
• Chiltern Tunnel
• Long Itchington
Surface Disruption
Cost effective
• Euston
• Northolt
• Bromford
Connectivity
• South Heath
• Wendover
• Burton Green
• Greatworth
4
P653 (4) HOC/10009/0005
Terrain Example: Chiltern Tunnel
Chalfont St Peter
Chalfont St Giles
Amersham
Little Missenden
5
P653 (5) HOC/10009/0006
Terrain Example: Chiltern Tunnel
6
P653 (6) HOC/10009/0007
Surface Disruption Example: Northolt Tunnel
OOC Station
Northolt
7
P653 (7) HOC/10009/0008
Surface Disruption Example: Northolt Tunnel
8
P653 (8) HOC/10009/0009
Connectivity Example: Burton Green Plan View
9
P653 (9) HOC/10009/0010
Connectivity Example: Burton Green Plan View
10
P653 (10) HOC/10009/0011
Tunnels Phase One
• 7.4km
• London Clay Euston
• 14km
• London Clay/Lambeth/Chalk Northolt
• 13.4km
• Chalk Chilterns
• 1.5km
• Penarth Group/Mercia Mudstone
Long Itchington Wood
• 2.8km
• Penarth Group/Mercia Mudstone
Bromford
• 1.1km
• Chalk South Heath
• 1.3km
• Chalk Wendover
• 2.1km
• Glacial Till/Oolite/Whitby Mudstone
Greatworth
• 2.5km
• Low Jurassic Marlstone/Mudstone
Chipping Warden
• 0.4km
• Penarth Group/Mercia Mudstone
Long Itchington Wood
• 0.5km
• Lower Carboniferous Mudstone
Burton Green
Twin Bored Tunnel Cut & Cover
11
P653 (11) HOC/10009/0012
2. Operational Aspects of Tunnelling
2.1 Safety Arrangements
2.2 Noise and Vibration
2.3 Aerodynamics and Porous Portals
2.4 Vent Shafts and Smoke Control
2.5 Energy Requirements
12
P653 (12) HOC/10009/0013
2.1 Minimum Safety Requirements (TSI)
Safe Area
• to the surface every 1 km or
• adjacent to independent tunnel tube every 500m
Fire Fighting Points - Applies to all tunnels over 1 km and rolling stock dependent
• Tunnel Length 1 to 5 km - portals with minimum standing area 550 sq m
• Tunnels Length over 5km - every 5km depending on rolling stock characteristics
Fire Fighting Point defined as
• Location inside or outside tunnel where fire fighting equipment can be used and passengers can evacuate
• Water supply capacity requires a minimum of 800 l/min for 2 hrs.
13
P653 (13) HOC/10009/0014
Tunnel Cross Passage
14
P653 (14) HOC/10009/0015
Emergency Train Evacuation
15
P653 (15) HOC/10009/0016
Evacuation Walkway
16
P653 (16) HOC/10009/0017
Tunnel Cross Passage Opening HS1
17
P653 (17) HOC/10009/0018
Typical Cross passage Door
18
P653 (18) HOC/10009/0019
2.2 Vibration
19
1. Noise/ vibration of rail caused by train 2. Attenuation through trackform 3. Attenuation through tunnel and ground 4. Attenuation through building foundations 5. Attenuation through structure building 6. Possible amplification from resonance of
building structure
INDICATIVE
P653 (19) HOC/10009/0020
Vibration mitigation via “booted sleeper” track
20
P653 (20) HOC/10009/0021
Tunnel Operational Noise
HS2 vent shafts are designed, constructed, operated and maintained along with associated stationary equipment so that noise in the worst affected residential receptors, conforms to British Standard Guidance and achieves the aims of the Noise Policy Statement for England.
Mechanical equipment within the vent shaft is only operated under the following circumstances:
• During an emergency;
• During maintenance when required to maintain an acceptable air quality environment; and
• During tunnel congestion when required to maintain an acceptable air quality environment.
21
P653 (21) HOC/10009/0022
2.3 Tunnel Aerodynamics
Tunnel aerodynamics are a function of the interaction of key infrastructure and rolling stock parameters such as:
• Diameter and roughness of tunnel • Length of tunnel • Provision of tunnel draught relief • Portal design • Train speed and length • Train aerodynamic profile
The primary controlling factors are the train speed and the “blockage ratio” (i.e. train area/tunnel area).
22
P653 (22) HOC/10009/0023
Tunnel Aerodynamics
23
Propagation of pressure wave
P653 (23) HOC/10009/0024
Porous Portal Slide
24
P653 (24) HOC/10009/0025
Porous Portal
25
P653 (25) HOC/10009/0026
Porous Portal
26
P653 (26) HOC/10009/0027
2.4 Vent Shafts
Primary Purpose • Smoke extract and control • Pressure relief • Access for emergency services • Passenger comfort to keep air quality and temperature
within acceptable limits
Secondary Uses • Tunnel boring machine maintenance intervention • Access for railway maintenance
27
P653 (27) HOC/10009/0028
Vent Shafts along Bored Tunnels
28
P653 (28) HOC/10009/0029
DOWN TUNNEL
UP TUNNEL
FANS
DAMPERS
DAMPERS
DAMPERS ARE NORMALLY CLOSED
FANS ARE FIXED PITCH, VARIABLE SPEED, REVERSIBLE
UP TUNNEL
Shaft Fans
29
P653 (29) HOC/10009/0030
DOWN TUNNEL
UP TUNNEL
FANS
DAMPERS
DAMPERS
Shaft Fans
30
P653 (30) HOC/10009/0031
DOWN TUNNEL
UP TUNNEL
FANS
DAMPERS
DAMPERS
Shaft Fans
31
P653 (31) HOC/10009/0032
In Line Tunnel Fan
32
P653 (32) HOC/10009/0033
Fans for portal arrangement via “Saccardo Nozzle”
33
P653 (33) HOC/10009/0034
“Saccardo Nozzle” viewed from the tunnel
34
P653 (34) HOC/10009/0035
2.5 Increased energy use in Tunnels
Traction power • Energy required for the traction power of the trains increases in tunnels. • In the open air 80% of the energy used by the train goes into overcoming air
resistance. This increases to 90% in a tunnel.
Increased power for Mechanical and Electrical plant and equipment • Increase in energy costs for the railway due to the plant necessary for safety
arrangements, for example: ― fans ― lifts ― fire mains ― emergency lighting plus tunnel integrity plant (e.g pumps, cooling
arrangements)
35
P653 (35) HOC/10009/0036
3. Construction
3.1 Types of Tunnelling Techniques Applicable to HS2
Bored Tunnels
• Shield type machines with precast segmental tunnel lining.
• Used when surface access is very limited at depths typically below one tunnel diameter.
• Longer tunnel lengths where economical to use machine.
Cut & Cover Tunnels (“Green Tunnels”)
• Typically concrete box structures constructed in excavated ground.
• Used at shallower depths where there is good surface access.
Mined/Sprayed Concrete Lining Tunnels
• Mechanically excavated with sprayed concrete lining.
• Used in shorter drives or more complicated shapes, also in soft rock ground conditions.
36
P653 (36) HOC/10009/0037
Bored Tunnels Earth Pressure Balance Tunnel Boring Machine (EPBM)
37
P653 (37) HOC/10009/0038
Bored Tunnels HS1 EPBM in factory showing back up arrangements
38
P653 (38) HOC/10009/0039
Bored Tunnels Cutter Head
39
P653 (39) HOC/10009/0040
Bored Tunnels Slurry or “Hydroshield” Tunnel Boring Machine
40
P653 (40) HOC/10009/0041
Precast Tunnel Lining Manufacture
41 INDICATIVE
50m
100m
Size Length - 300m Width - 100m Scale Length - 3 football pitches Width - 2 foot ball pitches
100m
280m
P653 (41) HOC/10009/0042
Bored Tunnels Tunnel Ring Segments
42
P653 (42) HOC/10009/0043
Segment Yard & Drive Site Locations
Old Oak Common
M25
Northolt tunnel Harvil Road
Washwood Heath
43
P653 (43) HOC/10009/0044
Mined tunnel
Excavator
44
P653 (44) HOC/10009/0045
Sprayed Concrete Lining
45
P653 (45) HOC/10009/0046
Cut & Cover “Green Tunnel”
46
P653 (46) HOC/10009/0047
Construction of tunnels where all the ground above is cleared
Cut and Cover Cross Section
47
P653 (47) HOC/10009/0048
Cut and Cover Construction Methodology 1
48
P653 (48) HOC/10009/0049
Cut and Cover Construction Methodology 2
49
P653 (49) HOC/10009/0050
HS1 Cut and Cover Under Construction
50
P653 (50) HOC/10009/0051
HS1 Cut and Cover Completed
51
P653 (51) HOC/10009/0052
Diaphragm Wall Construction
52
P653 (52) HOC/10009/0053
Diaphragm Wall Construction
53
P653 (53) HOC/10009/0054
Typical Plant for Cut & Cover Tunnel
54
P653 (54) HOC/10009/0055
3.2 Shaft Construction
55
P653 (55) HOC/10009/0056
Completed Shaft
56
P653 (56) HOC/10009/0057
Shaft Construction
57
P653 (57) HOC/10009/0058
Completed Shaft
58
P653 (58) HOC/10009/0059
Shaft Construction
59
P653 (59) HOC/10009/0060
Adit Construction
60
P653 (60) HOC/10009/0061
3.3 Settlement
INDICATIVE 61
P653 (61) HOC/10009/0062
Settlement Protective Measures • The primary form of settlement mitigation will be by good tunnelling
practice, including continuous working. Where required additional measures (e.g. grouting and structural solutions) will be carried out based on a three stage assessment as set out in Information Paper C3: Ground Settlement.
• Phase 1 Assessment: A preliminary assessment based on “green field” conditions will be undertaken. Where the predicted settlement is less than 10 mm or less than 1/500 slope, no further assessment is required.
• Phase 2 Assessment: In the case of predicted settlement of more than
10mm or 1/500 slope, an individual building assessment will be carried out. If the potential damage classification is Category 2 (slight) or below - no further assessment is required.
62
P653 (62) HOC/10009/0063
Settlement Protective Measures • Phase 3 Assessment: Where predicted settlement indicates potential
damage classification of 3 (moderate) or higher, a detailed evaluation will be carried out with the aim to reduce the effects to acceptable levels. Where this is not possible further protective measures will be implemented.
• Settlement Deed. Properties within 30 metres of tunnels may apply for a Deed (as set out in information paper C3) to ensure that protective measures are implemented in accordance with the assessment criteria.
63
P653 (63) HOC/10009/0064
3.4 Rate of Tunnelling
• The rate of tunnelling is important in minimising settlement. This is achieved by operating tunnel boring machines appropriately (such as using Earth Pressure Balance machines in “closed” mode).
• In order to keep settlement to acceptable limits, HS2 has specified a maximum of 1% volume loss for bored tunnels.
• Continuous 24 hour tunnelling also minimises settlement as it does not allow time for the ground to fully relax.
• Other methods of controlling settlement include grouting techniques, particularly compensation grouting.
64
P653 (64) HOC/10009/0065
3.5 Construction Aspects
(1) Construction Sites
(2) 24 hours/ 7 days working
(3) Supporting logistics – including excavated material
(4) Noise and Vibration
65
P653 (65) HOC/10009/0066
Construction Noise - Tunnel Drive Sites
• Tunnel drive sites generate similar noise levels to other large construction sites.
• Tunnelling activities and the associated local site material handling will be operated 24 hours a day.
• Noise mitigation is provided by the standard means such as hoarding, muffling, baffles and noise suppression on plant and equipment.
• Tunnel sites will be subject to the same HS2 procedures set out under the Code of Construction Practice and will be subject to Local Authority Approval under Section 61 of Code of Pollution Act 1974.
66
P653 (66) HOC/10009/0067
Construction Noise - Tunnel Boring
• Sound and vibration from the tunnel boring machine will be perceptible inside properties for a few days either side of the TBM as it passes beneath them.
• The effects of ground‐borne sound and vibration
from the TBM on building occupants will be short‐term and hence they are not considered to be significant.
67
P653 (67) HOC/10009/0068
4. Costs of Tunnelling Factors
• Tunnel Size • Ground Conditions (rate of progress) • Groundwater/aquifers • Material disposal methodology • Number of shafts • Cross Passages • Ground treatment • Settlement monitoring.
68
P653 (68) HOC/10009/0069
Costs of Tunnelling
Fixed Costs • TBM typically £15 to £20m • Back up material handling similar costs order.
Linear Costs • Labour • Lining materials • Excavated material disposal
Incremental Cost dependent on • Surface arrangements for drive sites, reception sites, portal arrangements. • Increase in shafts, cross passages, shaft M&E systems. • Number of logistics vehicles
69
P653 (69) HOC/10009/0070
Cost vs. Length
0 0 0
£
km
CO
ST
LENGTH
Shaft + M&E plant for vent & smoke control
INDICATIVE
Additional Shafts + M&E plant for vent & smoke control
Increase in cost per metre due to distance travelled by tunnel logistics requiring more spoil transport.
70
P653 (70) HOC/10009/0071
Tim Smart
71
P653 (71) HOC/10009/0072