PMG- Project Mgmt Group2

PMG Drafting Schedule

Date Milestone

5/16 Final agreement on CMAS Framework Deliverable and Drafting Schedule

5/30 Initial Drafts of CMAS Deliverable from WG Leaders to PMG Leader – This draft should be a template/outline of what is going to be recommended, a list of major issues to be resolved by the group with a schedule and any inter-WG issues that need resolution with a schedule. All inter-WG issues should have been coordinated between the groups prior to 5/30.

6/28 Second Round Drafts of CMAS Deliverable from WG Leaders to PMG Leader.

7/19 Identify final technical issues and lingering drafting needs; plot course corrections as needed.

8/9 Third Round Drafts of CMAS Deliverables from WG Leaders to PMG Leader – All technical issues resolved, only issues of style and formatting remain.

9/7 Final draft recommendations to PMG Chair.

Final draft recommendations to CMSAAC.

Early Oct CMSAAC Vote

Page 3: Project Management Group  (PMG)

PMG- Project Mgmt Group3

Next Steps

Polish final draft Distribute to Committee members for

review prior to October vote