PROJECT EXPERIENCE SUMMARY - INDONESIA
NoEJJV Project
NoClient Name Owner Project Name Specific Responsibilities/ Scope of Work Work Location Year Awarded Contract Duration
Year
CompletedContract Type
1 C0118 CS--17499876R Safety Equipment and Services Indonesia 201810January 2018 -
01 February 2021On Going Lumpsum
2 C0117 C1279730Retender Welding and Static Equipment Repair Services Indonesia 201822 January 2018 -
24 January 2023On Going Lumpsum
3 C0116 A2597459 Provision of Support Services for CPF and FSO Indonesia 201710January 2018 -
01 February 2021On Going Lumpsum
4 C0115 C1548979Operations Maintenance and Support Services for SLO
NorthIndonesia 2017
02 January 2018 -
01 February 2019On Going Lumpsum
5 C0114 CS-17270137Onshore Buidling Maintenance Facilities and Vegetation
Control ServicesIndonesia 2017
01 January 2018 -
31 December 2021On Going Lumpsum
6 C0113 4200002254 KG Repair Leakage Flowline Services Indonesia 201712 September 2017 -
11 December 20172017 Lumpsum
7 C0112 CS17416414RLifting Superintendent Services for Sumatera Onshore
Marine OperationsIndonesia 2017
09 february 2018 -
09 October 2020On Going Lumpsum
8 C0111 CS-17508844 Onshore Slope Repair Services Indonesia 201704 September 2017 -
03 September 2018On Going Lumpsum
9 C0110 A2588363R FSO Maintenance Services Indonesia 201719 June2017 -
16 June 2020On Going Lumpsum
10 C0109 A2603776 Provision of Tank Demucking Services for FSO Indonesia 201716 June2017 -
16 June 2020On Going Lumpsum
11 C0108 FAB-582/EJJV/VI/2017 Provision of KRN Pipeline Repair Survey Services Indonesia 201706 June 2017 -
05 July 20172017 Lumpsum
12 C0107 FAB-581/EJJV/III/2017 Provision of Pipe Fitter and Welder Services Indonesia 201724 March 2017 -
29 December 20172017 Lumpsum
PROJECT MANAGEMENT, ROV & DIVING, IT CONSULTANTS & CONSTRUCTION
PT EJJV Engineering Indonesia - Project Experience Summary Page 1 of 12
PROJECT EXPERIENCE SUMMARY - INDONESIA
NoEJJV Project
NoClient Name Owner Project Name Specific Responsibilities/ Scope of Work Work Location Year Awarded Contract Duration
Year
CompletedContract Type
13 C0106 4300006476 Production Facilities Maintenance Services Indonesia 201724 March 2017 -
29 December 20172017 Lumpsum
14 C0105 12000012379 Provision of KF WHRU Recondition Services Indonesia 201701 February 2017 -
01 Juni 20172017 Lumpsum
15 C0104 4420001734 - BP Berau Ltd Integrated C&CM-ER Services Indonesia 201605 September 2016 -
05 September 2021On Going Lumpsum
16 C0102 CS-17291944 R Aircraft Rescue and Firefighting (ARFF) Personnel Services Indonesia 201619 October 2016 -
19 Mei 2018On Going Lumpsum
17 C0101 FAB-042/EJJV/VIII/2016
Provision of Construction Drawing Service Including Field
Survey for KF Deluge Line Replacement and KRA
Instrumentation Air Line
Indonesia 201601 September 2016 -
01 Oktober 20162016 Lumpsum
18 C0100 C1405560 General Construction Services for Darajat Area Indonesia 201601 August 2016 -
01 August 2018On Going Lumpsum
19 C0103 SS1/PRJ-146/15/NOV Provision of Call Out Diving Supervision Services Indonesia 201601 July 2016 -
01 July 2018On Going Lumpsum
20 C0099 CS-16859277R Radiator and Heat Exchanger Repair & Services Indonesia 201601 February 2016 -
16 February 2019On Going Lumpsum
21 C0098 45033942 - BP Berau Ltd Supporting BP Voyager Deployment Phase 2 Indonesia 201512 September 2015 -
31 December 20152015 Lumpsum
22 C0097TNS-7000012202 - Eni Muara
Bakau B.VCommissioning Services for Project Indonesia 2015
1 June 2015 -
31 December 20172017 Lumpsum
23 C0096 4420001306A - BP Berau Ltd IT&S GOI Services Delivery and Technical Services Indonesia 201515 April 2015 -
15 April 2018On Going Lumpsum
24 C0094 4420001345A - BP Berau LtdTechnical Services for Safety & Emergency Response
Equipment Maintenance and Inspection ServiceIndonesia 2015
16 April 2015 -
15 Juni 20172017 Lumpsum
25 C0095 45033942 - BP Berau Ltd Supporting BP Voyager Deployment Indonesia 201520 January 2015 -
10 Maret 20152015 Lumpsum
PT EJJV Engineering Indonesia - Project Experience Summary Page 2 of 12
PROJECT EXPERIENCE SUMMARY - INDONESIA
NoEJJV Project
NoClient Name Owner Project Name Specific Responsibilities/ Scope of Work Work Location Year Awarded Contract Duration
Year
CompletedContract Type
26 C0093 4420001349 - BP Berau LtdTechnical Services Contract for Client Support Back Office
Operation and Project Management (Bridging)Indonesia 2015
02 March 2015 -
11 September 2015 2015 Lumpsum
27 C0092 EPPA-S14LL0096B-P23Jasa Pembuatan As Built 3D Model Fasilitas Produksi
Dengan Laser Scanning di Asset 5Indonesia 2014
13 Aug 2014 -
30 Aug 20172017 Lumpsum
28 C0090 4420000869 - BP Berau LtdProvision of Oversight Skill Competencies of Discipline
Capability ServicesIndonesia 2013
16 Dec 2013 -
15 Dec 20142014 Unit Rate
29 C0086 4420000784 - BP Berau Ltd Oversight Supervision of Boeing PK-TVZ C-Check Indonesia 20138 Oct 2013 -
20 Dec 20132013 Lumpsum
30 C0084M500-027-001 - BP UK / Rider Hunt
International UKThe Provision of Specilist Services Indonesia 2013
01 Oct 2013 -
30 Jan 20152015 Unit Rate
31 C0082212/DA/OPS/AUG-13 - West
Madura OffshoreProvision of Diving Supervisor for Under Water Services Indonesia 2013
26 Apr 2013 -
31 Jul 20152014 Unit Rate
32 C0081 4420000566 - BP Berau Ltd Upstream IT&S Project Services 2013-2016 Indonesia 201318 September 2013 -
17 September 2018On Going Unit Rate
33 C0079 4420000431 - BP Berau Ltd Supply Chain Business Support Service Indonesia 2013
8July 2013 -
7 June 2015
(2 Years)
2015 Unit Rate
34 C0076 4420000483 - BP Berau Ltd
Project Management Support Services for New
Condensate & Diesel Tanks, MATOA Mancamp & Aviation
Risk Study
Indonesia 2013
1 August 2013 -
1 January 2016
(2 Years)
2016 Unit Rate
35 C0075 4800022692 - BP Berau Ltd Fluid Database Project Consultation & Compliance Indonesia 20131 July 2013 -
1 March 20142014 Lumpsum
36 C0072 4420000550 - BP Berau LtdProject Management Support for Tangguh Expansion
Early WorksIndonesia 2013
15 March 2013 -
15 March 20142014 Lumpsum
PT EJJV Engineering Indonesia - Project Experience Summary Page 3 of 12
PROJECT EXPERIENCE SUMMARY - INDONESIA
NoEJJV Project
NoClient Name Owner Project Name Specific Responsibilities/ Scope of Work Work Location Year Awarded Contract Duration
Year
CompletedContract Type
37 C0071CS-16318106 ConocoPhillips
IndonesiaIT Support Services Indonesia 2013
01 February 2013 -
31 October 2016
(33 Months)
2016 Lumpsum
38 C0068 4420000256-BP Berau LtdTechnical Services for Client Support Back Office
Operation and Project ManagementIndonesia 2012
22 October 2012 -
11 March 20152015 Lumpsum
39 C0067STC-0768A Offshore North West
Java
Provision of Client Site Representative to Support Diving
and ROV CompaignIndonesia 2012
17 September 2012 -
16 Dec 20142014 Lumpsum
40 C0064 4420000112 - BP Berau LtdProject Management Support for Tangguh Expansion
Early WorksIndonesia 2012
10 July 2012 -
09 November 2014
(24 Months)
2014 Lumpsum
41 C0061STC-0765 Offshore North West
Java
Consulting Contract for Project Engineering &
Construction Management Services (Package 2)Indonesia 2012
07 May 2012 -
06 May 2014
(24 Months)
2014 Unit Rate
42 C0060CS-15924767 ConocoPhillips
IndonesiaApplication Development and Maintenance Services Indonesia 2012
20 July 2012 -
19 July 2015
(36 Months)
2015 Lumpsum
43 C0058 4420000201 BP Tangguh Oversight Supervision of Boeing PK-TVZ C-Check Indonesia 20125 Apr 2012 -
15 Jul 20122012 Lumpsum
44 C0063SO 9420003527 - West Madura
OffshoreProvision of ROV and Diving Specialist Indonesia 2012
1 Mar 2012 -
31 Mar 20122012 Unit Rate
45 C0057 4420000206 BP TangguhProject management Support and Sevices for Onshore
ProjectIndonesia 2012
14 March 2012 -
3 Sept 2013
(12 Months)
2013 Unit Rate
46 C0056STC-0720 Offshore North West
Java
Consulting Contract for Project Engineering &
Construction Management Services (Package 1)Indonesia 2012
22 February 2012 -
21 February 2014
(24 Months)
2014 Unit Rate
47 C0042STC-0609 Offshore North West
Java
Provision of Project Management & Construction
Engineering
- Project Management Team
- Project Delivery Procedure
Indonesia 2010
30 November 2010 -
29 November 2012
(24 Months)
2012 Lumpsum
PT EJJV Engineering Indonesia - Project Experience Summary Page 4 of 12
PROJECT EXPERIENCE SUMMARY - INDONESIA
NoEJJV Project
NoClient Name Owner Project Name Specific Responsibilities/ Scope of Work Work Location Year Awarded Contract Duration
Year
CompletedContract Type
48 C0039STC-0768 Offshore North West
Java
Technical Services for Provision of Client Site
Representative to Support Diving and ROV CampaignsIndonesia 2010
17 September 2010 -
16 September 2012
(24 Months)
2012 Lumpsum
49 C00384400000157 - BP Tangguh Gas
Processing Facilities
Provision of Technical Support Services for Tangguh Gas
Processing Facilities. General Scope of work are:
- Quality Management Services
- HSE Management Services
- Logistic Requirement Services
- Constructability Study
- Contracting & Project Control Services
- Specialized Study
Indonesia 2010
26 March 2010 -
25 Dec 2012 2012 Lumpsum
50 P0030STC-0429 - Offshore West Java
Rehabilitation Project
Project Management Services
The services are:
- Project Management Services
- Provide personnel for Construction
- Review Piping Validation
- Engineering Works for TAR 2009
- Project HSE Reviews
- Engineering Quality Plan
- Capital Value Process (CVP) Review
- Construction Engineering
Indonesia 20095 Jan 2009 -
30 Jul 20102011 Lumpsum
51 P0013 West Java Rehabilitation ProjectProvision of Piping Design Engineer / Construction
EngineerJakarta 2007
16 Apr 2007 -
15 Oct 20072007 Lumpsum
52 P0011 West Java Rehabilitation Project Provision of Workpack Development Specialist Services Onshore Jakarta 20076 Dec 2007 -
14 Jan 20092008 Lumpsum
53 P0003 West Java Rehabilitation Project Provision of As-Built Specialist Consultancy Onshore Jakarta 200720 Nov 2007 -
31 Jan 20082008 Lumpsum
54 P0003 West Java Rehabilitation ProjectProvision of Workpack Development Specialist
ConsultancyOnshore Jakarta 2007
15 Oct 2007 -
30 Nov 20072007 Lumpsum
55 P0003 West Java Rehabilitation ProjectProvision of Workpack Development Specialist
ConsultancyOnshore Jakarta 2007
11 Jul 2007 -
28 Sep 20072007 Lumpsum
56 P0023Shell Sarawak Berhad (B11LQ)
ProjectProvision of Manpower Services - Indirect Personnel
Miri, Sarak,
Malaysia2008 25-Jan-08 2008 Unit Rate
PT EJJV Engineering Indonesia - Project Experience Summary Page 5 of 12
PROJECT EXPERIENCE SUMMARY - INDONESIA
NoEJJV Project
NoClient Name Owner Project Name Specific Responsibilities/ Scope of Work Work Location Year Awarded Contract Duration
Year
CompletedContract Type
57 P0031Mafumeira KWIP Offshore
Development ProjectProvision of Manpower Services - Direct Personnel US - Offshore 2008 05-Feb-09 2009 Unit Rate
58 P0028Takula Gas Processing Platform
ProjectProvision of Manpower Services - Direct Personnel Angola - Offshore 2008 2009 Unit Rate
59 P0016Takula Gas Processing Platform
ProjectProvision of Manpower Services - Direct Personnel Angola - Offshore 2008 2009 Unit Rate
60 P0016Takula Gas Processing Platform
ProjectProvision of Manpower Services - Direct Personnel Angola - Offshore 2008 2009 Unit Rate
61 TOTAL TUNU 11 Direct Hire of Lead Electrical Engineer PMT Jakarta 2006 2007 Lump Sum
62 P0001 TOTAL TUNU 11 Seconded Lead Piping Engineer PMT Jakarta 20061 Jun 2006 -
30 Nov 20062007 Lump Sum
63 C0077
3900214656
Cleaning Tanki and Processing
SOR
Cleaning Tanki T-2 / T-9 & Processing Sludge Oil Recovery
(SOR) - Pertamina EP Jatibarang FieldIndonesia 2013
15 June 2013 -
14 Oct 2013 2013 Lumpsum
64 C0066 SO2435 - EPC-1 Banyu Urip Project Completion System for Banyu Urip EPC-1 Indonesia 2012
13 July 2012 -
12 January 2014
(18 Month)
2014 Lumpsum
65 C0091 P14-049Provision to Supply for Tehcnical Safety Engineer for CP2
ProjectIndonesia 2014
12 Sept 2014 -
12 Oct 20142014 Lumpsum
66 C0089 MSOCL/CON-HSE/DEC/13/218 Provision of HAZID Workshop & Report Service Indonesia 201310 Dec 2013 -
30 Jun 20142014 Lumpsum
ENGINEERING & PROCESS SAFETY STUDIES
MAINTENANCE
PROJECT COMPLETION SYSTEM & COMMISSIONING
PT EJJV Engineering Indonesia - Project Experience Summary Page 6 of 12
PROJECT EXPERIENCE SUMMARY - INDONESIA
NoEJJV Project
NoClient Name Owner Project Name Specific Responsibilities/ Scope of Work Work Location Year Awarded Contract Duration
Year
CompletedContract Type
67 C0088 SCA No : 2778-EN-SC-014 HAZOP & QRA Studies of Chevron AIP Project Indonesia 201317 Nov 2013 -
30 March 20142014 Lumpsum
68 C0087Safetec Malaysia Provision of Process Safety Engineer in Foorozan FZ-A
project at NGL Tech office in Kuala LumpurMalaysia 2013
17 May 2013 -
30 Oct 20132013 Unit Rate
69 C0085P00036 - Safetec Malaysia
Murphy Permas Topsides EPCC - RAM & AIV Studies Jakarta 201301 Oct 2013 -
30 Dec 20132013 Unit Rate
70 C0083380/CA/2013 Pertamina (persero)
RU III Plaju
Update P&ID Menggunakan 3D Scanning Kilang Utilities
PlajuIndonesia 2013
23 Sept 2013 -
15 Dec 20132013 Lumpsum
71 C0080
PS-102/EJJV/VI/2013
GSWP Project of Petronas Carigali
SDN Bhd
Hazid & Hazop Studies for Development of Generic
Satelite Wellhead Platform (GSWP) Project Jakarta 2013
4July 2013 -
4 August 20132013 Lumpsum
72 C0078SO No. PA03780613
PT Atamora Tehnik MakmurUmbilical Project for Hazid Study Indonesia 2013
17 June 2013 -
5-July-2013 2013 Lumpsum
73 C0074 PS-095A/EJJV/II/2013 Pertamina RFCC Cilacap QRA & BRA Studies Indonesia 2013
1 March 2013 -
1 June 2013
(3 month)
2013 Lumpsum
74 C0073 PS-095/EJJV/II/2013 Pertamina RFCC Cilacap QRA & BRA Studies Indonesia 2013
25 March 2013 -
25 June 2013
(3 month)
2013 Lumpsum
75 C0070RFCC-A-PR-AG-008A Cilacap Resid
Fluid Catalityc Cracking (RFCC)Provision Hazop and SIL Study Indonesia 2013
26 October 2012 -
26 January 2013
(3 month)
2013 Lumpsum
76 C0069 PPGJ-PS-TSA-079 Gundih Project Dispersion Study for Thermal Oxidaton Package (PE-0401) Indonesia 2012
23 October 2012 -
23 November 2012
(1 month)
2012 Lumpsum
PT EJJV Engineering Indonesia - Project Experience Summary Page 7 of 12
PROJECT EXPERIENCE SUMMARY - INDONESIA
NoEJJV Project
NoClient Name Owner Project Name Specific Responsibilities/ Scope of Work Work Location Year Awarded Contract Duration
Year
CompletedContract Type
77 C0065 Naga Pelikan ProjectProvision of Hazid, Hazop & SIL Chairman & Scriber
ServicesIndonesia 2012
10 July 2012 -
9 July 2013
(1 years)
2013 Lumpsum
78 C0062 KF Booster Gas Compressor Project Hazid and Hazop Engineering Study Indonesia 20122 May 2012 -
29 June 20122012 Lumpsum
79 C0059 FEED GG Field Development ProjectPerform Safety Case Study i.e Fire and Explosion Analysis,
Pipeline Risk Assessment, QRA Study and FERA Study.Indonesia 2012
4 Apr 2012 -
31 May 20122012 Lumpsum
80 C0055Proyek Pengembangan Gas Jawa
Area GundihPerform QRA Study Indonesia 2012 05-Jan-12 2012 Lumpsum
81C0053 &
C0054EPC for LTRO Project Perform HAZOP and HAZID Study for LTRO Project Indonesia 2012 05-Jan-12 2012 Lumpsum
82 C0051EPCI OF AGX COMPRESSOR
RECONFIGURATION
Provision of Safety Studies i.e HAZID, HAZOP, QRA,
NHHA, ESSA, EERA, SIL, ALARP, Safety Case, What if
analysis, Safety critical elements and performance
standard, Noise Study, Chemical handling and Hazard
Register.
Indonesia 2011
10 October 2011 -
10 July 2012
(9 Months)
2012 Lumpsum
83 C0052 Subsea Project SSIV QRA Study Indonesia 2011 02-Nov-11 2012 Lumpsum
84 C0050Ujung pangkah Development WHP
B
Perform HAZID for Ujung pangkah Development WHP B
Upgrade and InspectionIndonesia 2011 12-Oct-11 2011 Lumpsum
85 C0049 CO-11-138 PremierOil Natuna Written Scheme of Examination Development & Safety
Safety Critical Element VerificationIndonesia 2011
12 Sep 2011 -
11 Sep 20122012 Lumpsum
86 C0048Bakrie Sumatera Plantations (BSP)
ProjectATEX 137 Hazardous Area Classification (HAC) Study Sumatera 2011
10 May 2011 -
24 Jun 20112011 Lumpsum
PT EJJV Engineering Indonesia - Project Experience Summary Page 8 of 12
PROJECT EXPERIENCE SUMMARY - INDONESIA
NoEJJV Project
NoClient Name Owner Project Name Specific Responsibilities/ Scope of Work Work Location Year Awarded Contract Duration
Year
CompletedContract Type
87 C0046Salamander Existing Gas Plant
Pangkalan Brandan North Sumatra
Performed Hazard Identification (HAZID) study for
Installation VRU Compressor Package Jakarta 20114 Jun 2011 -
18 Jun 20112011 Lumpsum
88 C0047 Block A Gas Development ProjectPerformed Quantitative Risk Assessment (QRA) study for
Medco Block A Gas Development ProjectJakarta 2011
13 Apr 2011 -
22 Jun 20112011 Lumpsum
89 C0045LIMA Subsidence Remediation
Project
Performed Hazard Identification (HAZID) study for PHE
LIMA Subsidence Remediation ProjectJakarta 2011
11 Mar 2011 -
1 Apr 20112011 Lumpsum
90 C0044EHMR Water (reinjection) FEL-3
Project
Facilitating HAZID, SIL and HAZID/ENVID Session of CESC
Eastern Hub Mercury Removal - Water (Reinjection) FEL-3
project
Indonesia 201111 Feb 2011 -
23 Feb 20112011 Lumpsum
91 C0043 Ammonia Plant Project Performed QRA Study for Ammonia Gas Plant project Indonesia 201114 Dec 2010 -
25 Mar 20112011 Lumpsum
92 C0041CESC Bungin Develeopment FEL-2
Project
Facilitating HAZID, HAZOP and SIL of CESC Bungin
Development FEL-2 ProjectIndonesia 2010
15 Nov 2010 -
31 Dec 20102011 Lumpsum
93 C0040 CESC LTRO FEL3 projectFacilitating HAZID, HAZOP and SIL of CESC LTRO FEL3
ProjectIndonesia 2010
22 Oct 2010 -
31 Dec 20102010 Lumpsum
94 P0034 CO-09-098 PremierOil Natuna
Independent Verification Services In Accordance With the
Offshore Safety case Requirements
- Development of Written Scheme Examination (WSE)
Indonesia 20096 Jul 2009 -
5 Jul 20102010 Lumpsum
95 P0032 CO-09-101 PremierOil Natuna
Provision of Enhancement of Scheme of Verification for
Static Equipment Elements.
- Identification of Static SCEs
- SCE/MAE Matrix
- Development Operational Performance Standards for
approved Static SCEs
- Electrical Ex-Register Review
- Inputs for Update of Scheme of Verification Document
- SCE ID and First Pass Performance Standards
- Provide advice on in corporatation of Static SCE's in TSS
matrix
Indonesia 20096 Jul 2009 -
9 Oct 20102010 Lumpsum
PT EJJV Engineering Indonesia - Project Experience Summary Page 9 of 12
PROJECT EXPERIENCE SUMMARY - INDONESIA
NoEJJV Project
NoClient Name Owner Project Name Specific Responsibilities/ Scope of Work Work Location Year Awarded Contract Duration
Year
CompletedContract Type
96 P0017SC-0063 - HSE Management
System Services
HSE Audit Support, Contractor Safety, Health and
Environt management System Implementation Support
Services, SIMOP Procedure, HSE Acceptance List, HSE
Online
Jakarta, West
Java & WJ
Marunda
200821 Apr 2008 -
13 Apr 20112012 Lumpsum
97 P0012 Anoa Safety Case
Performed Offshore Quantitative Risk Assessment (QRA),
Base Case Definition, Supporting Studies, Safety Case,
Offshore Handbook and Rollout, Training, Management
Updates, Safety Critical Element (SCE) studies for Anoa
Safety Case
Indonesia 200817 Dec 2007 -
18 Sep 20082009 Lumpsum
98 P0018 Update QRA & HAZOP Study Update QRA & HAZOP Study Onshore Jakarta 200822 Apr 2008 -
29 Apr 20082009 Lumpsum
99 P0025 Specialist Safety Study ProjectSpecialist Study for Quantitive Risk Assessment (QRA) and
Safety Integrity Level (SIL) AssessmentJakarta 2008 17-Jul-08 2009 Lumpsum
100 P0035Pangkah Liquid Development Oil
Treating & LPG Facilities ProjectPerform Detailed Surge Analysis Study Indonesia 2009 2009 Lumpsum
101 P0026Singa Gas Development Project
Lematang - South SumatraQuantitative Risk Assessment Study Indonesia 2009
23 Jan 2009 -
20 Mar 20092010 Lumpsum
102 P0027Ujung Pangkah Liquid Development
ProjectFireproofing Requirement Review Indonesia 2009
7 Aug 2009 -
21 Aug 20092009 Lumpsum
103 P0037Cnooc Mila A Wellhead Platform
and Pipeline ProjectPerformed HAZOP, HAZID and ALARP Studies Indonesia 2009 21-Aug-09 2010 Lumpsum
104 P0036Ujung Pangkah CPP & AUP EPCC
ProjectLQ Sprinkler System Requirement Review Indonesia 2009
23 Aug 2009 -
22 Sept 20092009 Lumpsum
105Ujung Pangkah Liquid Development
ProjectOTF & LPG Detailed Surge Analysis Indonesia 2009 2009 Lumpsum
PT EJJV Engineering Indonesia - Project Experience Summary Page 10 of 12
PROJECT EXPERIENCE SUMMARY - INDONESIA
NoEJJV Project
NoClient Name Owner Project Name Specific Responsibilities/ Scope of Work Work Location Year Awarded Contract Duration
Year
CompletedContract Type
106 P0033 OTF & LPG recovey Plant Additional HAZOP study for LPG product Segregation &
produced water system packageIndonesia 2009 2009 Lumpsum
107 P0029Ujung Pangkah Development
ProjectPipeline Transient Analysis Revisit Indonesia 2009 2009 Lumpsum
108EPC Gas Production Facilities Jambi
Merang Development ProjectSafety Engineering - Review of Critical Indonesia 2008 2009 Lumpsum
109 P0024 LPG-FSO Petrostar Failure Analysis Matering of LPG-FSO PetrostarOffshore Jabung,
Jambi2008 07-Jul-08 2008 Lumpsum
110 P0022Oyong Phase 2 Onshore Processing
Plant (OPF) Project
Performed Hazard Identification (HAZID) study for Santos
Oyong Phase 2 OPF ProjectJakarta 2008 26-Jun-08 2009 Lumpsum
111 P0021Ujung Pangkah Liquid Development
ProjectWater Hammer Analysis & Surge Analaysis Indonesia 2008 01-Jul-08 2009 Lumpsum
112 P0020Gelagah Kambuna Development
ProjectSPECIALIST HAZOP, HAZID & SIL STUDY Indonesia 2008 04-Jun-08 2009 Lumpsum
113 P0019Singa Gas Development Project
Lematang - South Sumatra
Performed HAZOP and HAZID studies for Singa Gas Plant
Development Project
Lematang, South
Sumatra2008
4 Jun 2008 -
18 Jun 20082009 Lumpsum
114 P0015Gas Production Facility Jambi
Merang Project
Performed HAZOP and HAZID Studies for Jambi Merang
ProjectJAMBI MERANG 2008 06-Mar-08 2008 Lumpsum
115 P0014 West Java Rehabilitation Project Preparation of Material Take Off Onshore Jakarta 2008 23-Jan-08 2008 Lump Sum
PT EJJV Engineering Indonesia - Project Experience Summary Page 11 of 12
PROJECT EXPERIENCE SUMMARY - INDONESIA
NoEJJV Project
NoClient Name Owner Project Name Specific Responsibilities/ Scope of Work Work Location Year Awarded Contract Duration
Year
CompletedContract Type
116 P0010North Duri Development Project -
Area 13
Performed HAZOP study for North Duri Development
Project - Area 13
North Duri -
Indonesia2007
17 Sept 2007 -
12 Nov 20072008 Lumpsum
117 P0008LPG FSO (Petrostar), FPU and Oil
FSO (Federal-I) Jabung Offshore
Undertake Safety Review to identify all the potential
hazards associated with the LPG FSO (Petrostar), FPU and
Oil FSO (Federal-I).
Offshore Jabung,
Jambi2007
31 Aug 2007 -
4 Oct 20072008 Lumpsum
118 P0009 `Export hose rupture case, Effect of pump seal failure at
MD3
Offshore Jabung,
Jambi2007
31 Aug 2007 -
9 Oct 20072008 Lumpsum
119 P0007
Ujung Pangkah Liquids
Development Projects –Oil Treating
Facility and LPG Recovery Plant
Project
Performed SIL, HAZOP, HAZID and QRA Studies for Ujung
Pangkah Liquids Development Projects –Oil Treating
Facility and LPG Recovery Plant Project
HESS
(INDONESIA
PANGKAH)
LIMITED
2007 27-Jul-07 2007 Lumpsum
120 P0006 Wellhead PlatformPerformed SIL and Noise studies for ENI Blacktip Gas
ProjectAUSTRALIA 2007
10 May 2007 -
17 Jul 20072007 Lumpsum
121 P0005Cilamaya Onshore Receiving Facility
and Offshore Platform
Performed SIL Verification for Cilamaya ORF and NGLB
Dehydration as part of the project
ONSHORE
CILAMAYA2007
24 Apr 2007 -
23 May 20072007 Lumpsum
122 P0004 KG Platform Modification ProjectPerformed FERA and EERA Studies for the KG Platform
Modification Project
KG PLATFORM,
OFFSHORE
NATUNA
200716 Mar 2007 -
16 Jun 20072007 Lumpsum
123 P0002Offshore LPG/Oil Terminal, Offshore
JabungHAZOPS, HAZID, and Safety Review
Offshore Jabung,
Jambi2007 4 Weeks 2007 Lumpsum
PT EJJV Engineering Indonesia - Project Experience Summary Page 12 of 12