Presentation Title One Programme Two Clients 19 June 2012 Jenni
MacGregor BSc(Hons) CEng MICE
Slide 2
Introduction The First Client - External The Second Client -
Internal Approach to servicing both Practical Programme
Challenges
Slide 3
Jenni MacGregor Chartered Civil Engineer I have 36 years of
diverse civil engineering experience, principally within Major
Projects and Asset Management I have worked for two major UK civil
engineering contractors, Costain and BAM Nuttall I moved into full
time planning over 25 years ago I am currently Head of Planning for
BAM Nuttall, a 800+m turnover company within the Royal Bam Group. I
have a company wide functional responsibility for providing support
and guidance in relation to planning matters to all operational
staff including some 70 planning engineers. I also enjoy the
strategic vision and goal setting facets of the role I contribute
to several industry wide forums Introduction
Slide 4
Royal BAM One of Europes leading construction companies BAM
Nuttall A leading UK civil engineering company Introduction
Slide 5
History
Slide 6
Liver Buildings Liverpool. Built in 1910 One of the earliest
reinforced concrete buildings First Mersey Tunnel Built in 1926
Mulberry Harbour World War 2 History
Slide 7
Netherlands, Belgium, Germany, UK, Ireland, International Royal
BAM Markets Construction, Property, Civil Engineering, PPP BAM
Group
Slide 8
UK Companies
Slide 9
Slide 10
Slide 11
Slide 12
The First Client External
Slide 13
Transport for London Blackwall Tunnel Northbound Tottenham
Court Road and Victoria Station redevelopments Olympic Delivery
Authority and Legacy Company Argent at Kings Cross Local
Authorities Network Rail GSMR National Telecoms Programme Rail
South Framework Airdrie to Bathgate Regeneration Reading Station
Upgrade Other Railways Chiltern Railways Evergreen Phase 3 Borders
Railway ECI and Design External Clients
Slide 14
Cont..Crossrail C200 Pudding Mill Lane Site
Facilities20/07/09