2018 Transportation Planning Conference 6/7/2018
PLANNING FOR ACCELERATED CONSTRUCTION IN THE BRYAN DISTRICT Allison Kurwitz, P.E. District Advance Planning Engineer
6/7/2018
2018 Transportation Planning Conference 6/7/2018
BRYAN DISTRICT
2
Bryan District Letting
FY18 – 85 million FY19 – 104 million FY20 – 132 million FY21 – 276 million
2018 Transportation Planning Conference 6/7/2018
Project Development and Delivery
Planning and Programming
Preliminary Design
Environmental
Public Involvement
Right-of-Way
Utilities
Plans, Specifications and Estimates
Letting
Construction
3
2018 Transportation Planning Conference 6/7/2018
Planning and Programming
Develop schedules with all of your key subject matter experts-Review the schedules often with everyone to minimize risk.
Approach every project with a Value Engineering mentality, starting with scoping and continue discussion throughout to the end.
Grouped Procurement
Start Advance Funding Agreement discussions early
Consider which projects are good candidates for accelerated construction.
Alternative Contracting Methods
Resources
MPO – Prioritize, Funding, Partnering,…
Best time of year to let
Get projects Ready to Let in anticipation of funding
4
2018 Transportation Planning Conference 6/7/2018
Project Development Schedule
5
2018 Transportation Planning Conference 6/7/2018
Preliminary Design
Involve internal stakeholders & subject matter experts from multiple disciplines in scoping, preliminary design, review,…
Include Hydrology and Hydraulics Study to determine culverts and bridges.
Develop conceptual traffic control plan and sequence of work.
Involve right of way staff early. Discuss impacts & access.
Include preliminary bridge design. Utilize Bridge Division for review.
Look for work to be considered in milestone calculations.
Include SUE & Geotech (pavement & bridge).
Look for ways to minimize risk and opportunities for innovation and accelerated construction.
Start bicycle, pedestrian, ADA and aesthetics conversations early.
Use appropriate surveying for phase of project development.
6
2018 Transportation Planning Conference 6/7/2018
Environmental
Begin environmental Right of Entry early along with survey ROE. On projects where right of way is to be acquired and right of entry has been denied, work closely with right of way to gain access during or after acquisition.
Begin early environmental constraints within the study area- Desktop surveys.
If you identify that your project would require a USACE Permit with mitigation, especially if you anticipate an Individual Permit-Hold a pre-application meeting, face to face, with the USACE to discuss the project and anticipated impacts. Consider them a stakeholder until the permit risk is resolved.
7
2018 Transportation Planning Conference 6/7/2018
Public Involvement
Develop a public involvement plan for projects- No matter what size of project you have. Use the Office of Public Involvement and their various resources
Hold early Stakeholder meetings- Public Officials, ISD, Emergency Response and identified landowners or citizen groups
Hold Public Involvement early in the project just after all the identified Stakeholders have been informed
Hold internal bi-weekly meetings with all internal stakeholders to discuss public involvement efforts for the next three months
Develop Project Web Pages for project that will have Hearings or Meetings
Develop business cards with our district contact information and the web address of our District Projects and Studies Page on txdot.gov
Metroquest
Have Public Involvement Early and throughout, including keeping public informed in construction
8
2018 Transportation Planning Conference 6/7/2018
Right of Way
Include Right of Way mapping in Schematic phase
Involve Right of Way section early.
Start Right of Way process early (Deed Research, Locate Monuments, Property Descriptions,…)
Let Prep Right of Way contracts (Allows Utilities to relocate sooner, schedule around nesting season, aid in fence relocation, gets ahead of construction)
Acquire enough right of way.
9
2018 Transportation Planning Conference 6/7/2018
Utilities
Look for utility issues during feasibility phase.
Include SUE work during schematic phase.
Prep ROW for ease of utility relocations.
Identify potential conflicts at the schematic phase. Look for space to relocate or make design adjustments to work around.
Early planning when laying out alignments to miss big ticket items: cell towers, control offices, transmission structures, sub stations, lift stations,…
Prep ROW for ease of utility relocations.
Start Utility Coordination efforts at 60% schematic.
Use UACV contracts to assist with increased workload.
Accelerate drainage design to identify conflicts early.
Don’t allow abandonment in place, eliminates future issues.
10
2018 Transportation Planning Conference 6/7/2018
Project: FM 60: Snook to Lyons
11
Phasing Coordinate ROE with ROW Acquisition Prep ROW Project – help with
utilities, nesting birds and accelerate construction Included Design PM in Planning Mtgs Coordinate with County for old
sections of roadway
2018 Transportation Planning Conference 6/7/2018
Project: IH 45 Corridor
12
Phasing Consult with Contractors Use of CE&I Discuss any TCP changes
throughout – open discussions Big PI effort - working towards
project page that carries through construction Innovated design considerations
through VE studies, early coordination with FHWA and Design Division peer review
https://www.txdot.gov/inside-txdot/projects/studies/bryan.html
2018 Transportation Planning Conference 6/7/2018
Projects: FM 2818 from FM 60 to FM 2154
13
New design for area (alternatives) Can use existing pavement for traffic
control Sets up for future phase conversion to
freeway (multilane with frontage roads)
Metroquest – get public involvement and buy-in
Focus on bicycle/pedestrian concerns and opportunities
https://www.txdot.gov/inside-txdot/projects/studies/bryan/fm2818.html
2018 Transportation Planning Conference 6/7/2018
Projects: FM 60 @ FM 2818
14
Convert existing unsignalized at-grade
intersections with the FM 2818 ramps into a diverging diamond interchange (DDI). Widen existing bridge over FM 2818.
Separate Feasibility and Traffic Engineering Studies.
Outside the box thinking. Unique design for this area.
Public Involvement included simulation. Involved Active Transportation users in
design. Use media and project pages to
communicate lane closures. https://www.txdot.gov/inside-txdot/projects/studies/bryan/fm60.html
2018 Transportation Planning Conference 6/7/2018
Project: George Bush Drive @ Wellborn Road
15
At 99% plans but not funded, revisit design
Renewed Public Involvement Partnering with Texas
Transportation Institute Look at construction sequencing
and traffic control. Include contactors in discussion.
Compare construction duration vs closures during construction.
Multi-level with separated bike and pedestrian facility
https://www.txdot.gov/inside-txdot/projects/studies/bryan/fm2347.html
2018 Transportation Planning Conference 6/7/2018
Project: US 190 / SH 21 Navasota River to Madisonville
16
Re-evaluating alternatives with
renewed public involvement. Shifted alignment to re-use
existing pavement. Using Consultant Management
for 3 ROW Mapping Consultants. Broke into sections for time savings.
Early right of way activities Purchase ROW for drainage
instead of easement. Determine crossovers with
schematic.
https://www.txdot.gov/inside-txdot/projects/studies/bryan/sh21-madison.html
2018 Transportation Planning Conference 6/7/2018
Project: SH 249 Todd Mission to Navasota
17
Design-Build Extensive Public Involvement
(Contentious Project) Several iterations of alternative
alignments Phased Construction – Acquire right
of way for ultimate Coordination with Houston District Toll vs Non-Toll (Decision impacts
design) Lack of Right of Entry and changes
delayed Environmental Clearance
https://www.txdot.gov/inside-txdot/projects/studies/bryan/sh249.html
2018 Transportation Planning Conference 6/7/2018
Thank you!
18