Development Plan for Wynyard Quarter
HISTORY OF WYNYARD QUARTER
1930 – The Western Reclamation, now known as Wynyard Quarter was progressively constructed by Ports of Auckland’s predecessor,
the Auckland Harbour Board with the last component of the reclamation being completed in 1930.
2004 - Early plans intended to name the new area 'Kahurangi', Māori for 'blue/precious jewel'. This has now been replaced with
'Wynyard Quarter', though it is still generally referred to as Tank Farm, including when talking about the whole Western Reclamation. Others have suggested the label 'Tech-Farm', referencing a 2004 call to showcase on the waterfront New Zealand's best sustainable design and technology, as well as anticipating the government's and council's 2012 initiative to establish an 'innovation precinct' within the Wynyard Quarter.
Political and design processes were underway in the mid and late 2000s to define the future shape of the area, a change process that will take up to 20 years. One of the main public inputs at that time was a wish for increased waterfront access, as well as the desire for more parkland on the point. However, some of these wishes were muted from political sources, as the redevelopment of the area is to be paid by the development of residential areas, with the available land for this use shrinking with an increase of the proposed park space. Already mostly agreed on was a bridge connecting the new quarter to the Viaduct Basin.
2006 - Ports of Auckland still owned 18ha of the 35ha site in 2006 when it was decided that the land would be transferred to its
parent company, Auckland Regional Holdings, owned by the Auckland Regional Council. Also in 2006 after 10-16 storey buildings proposed met strong opposition, the revised July 2007 design contained only a small number of 14-storey towers, with the main apartment strips along the eastern side of Wynyard Wharf being no higher than seven storeys at the road, stepping down to three storeys at the water’s edge. In addition, the plan stated the new Western Reclamation zone was to be dominated by public transport, with the targeted transport mix being 70% public transport / walking / cycling and 30% motor vehicle, a reversal of the rest of Auckland City. Ferries are also mooted as possible connections.
HISTORY OF WYNYARD QUARTER CONTINUED
2007 – In June 2007, more detailed concept plans were published after a year of negotiation between stakeholders. In the first stage of
the redevelopment, the eastern section of the Western Reclamation, along Jellicoe Street, was to be turned into an entertainment strip, to complement similar areas on the eastern side of the Viaduct Basin, and to be completed in time for the 2011 Rugby World Cup. This area was to be linked to the Auckland CBD via a new 'Te Wero' bridge, to be constructed as a lift- or swing bridge after an international design competition, and expected to cost around NZ$35 million.
SeaLink runs a car and passenger ferry service to Great Barrier Island from a terminal at the base of Wynyard Wharf. The company was seeking clarification of its future facilities in the area in 2007, as their lease was running out in 2010, and it was unlikely to invest a planned NZ$19 million in a new terminal or start using a new, faster ferry vessel before legal concerns were sorted out. An ARC planning committee noted that it supported the further provision of the ferry service in the area, though there had previously been concerns about the island freight shipping not fitting into the redevelopment vision of the area. The Waterfront Plan completed 2012 does include the island ferry terminal, to be in the same general area as before.
Late 2000’s - As of the late 2000s, the area was still used by the bulk liquid industry which provides NZ$1.2 billion of yearly
turnover, and 4000 jobs in the Auckland economy. There are also more than 100 marine companies around the area, with a NZ$400 million yearly turnover, exporting items worth NZ$120 million per year.
2011 - The August 2011 opening of the Wynyard Quarter to the general public, with the main features being the new Jellicoe Street and
North Wharf areas, as well as the open spaces around 'Silo Park' (designed by Taylor Cullity Lethlean and Wraight and Associates) and the Viaduct Events Centre, were met with great public interest, and critical acclaim for the synthesis between open space and formerly industrial use.
1. Wynyard Crossing (TeWero Bridge) –pedestrian/cycle bridge
2. Viaduct Events Centre (2011) - exhibition, meeting and hospitality space
3. Karanga Plaza – Public Open Space: Features art, steps down to the water’s edge and is the perfect spot to relax and watch the world go by on the large wooden recliners. Also features KarangaKiosk – hub for info on Wynyard Quarter
4. North Wharf (1910-15) -redeveloped to strengthen pedestrian and cycle connectivity along the waterfront axis. The waterfront edge featuresretail & hospitality businesses and remains a working wharf, accessible to ferries and fishing industries and the public
5. Jellicoe Street – runs parallel to North Wharf and connects KarangaPlaza to marine related activity in the West including Silo Marina. Primary destination for entertainment, retail commercial activity. Includes up-market shopping, dining, bars/clubs and fishing activity such as the fish market.
6. Silo Park – The park comprises of a combination of grass areas, concrete areas, low impact swales (to manage water runoff and filter pollutants) and walkways. The combination of these elements within the park provides a setting to host outdoor events including Silo markets, an open-air movie theatre, exhibitions and other events.
7. North Wharf Extension -an extension to North Wharf will facilitate its use for recreational activities as well as the potential for ferry and water taxi services that will compliment and support the adjacent land based activities.
1.Wynyard Wharf2.Point Park3.Beaumont Plaza4.Public Open Space/Water Feature5.Jellicoe Plaza6.North Wharf7.Wynyard Plaza8.Madden Plaza/Viaduct Harbour Edge9.Daldy Street Linear Park10.Central Park11.Gateway Plaza
A.Te Wero BridgeB.North Wharf extensionC.Fanshawe Street intersectionsD.Pedestrian Bridge
Purpose of
Development
Mission: As most exciting and diverse places in
Auckland, the creation of marine park joining the
neighbourhood and new marine parks will open for
visitors and local’s to enjoy, offer a more exciting
and new Wynyard Quarter.
Vision: Offer combination of residential, retail and
commercial development to support development of
stable, diverse, lively residential and business
community while keeping the existing industries.
Potential Market
Segments
• Families
• Schools/Educational Institutions
• Property Investors
• Upscale shoppers
AUCKQUATIC Marine Park
Dolphin Pool
Dolphin and Seal Shows
Stingray Pool
Penguin Pool
Aquarium
Souvenir Shop
Indoor Garden
Coffee Shop
Car Park
Full Facilities For Those With Disabilities
OTHER AuckQUATIC MARINE PARK DETAILS
Opening Times
5th April – 26th September (2020)Monday – Thursday: 9:00am – 6:00pmSaturday – Sunday: 10:00am – 5:00pm
27th September – 4th April (2020-21)Monday – Thursday: 9:00am – 8:00pmSaturday – Sunday: 9:00am – 7:00pm
Admission Costs
Adults - $40.00Children (2-15 yrs) - $20.00Under 2 Years – FREE!Family Pass A (2 Adults, 1 Child) - $75.00Family Pass B (2 Adults, 2 Children) - $100.00Family Pass Additional Child - $15.00
• Added bonus – pre purchase your ticketsonline and show your ticket to public transportin order to receive free return travel on tram,red link bus, or 010 bus.
Location
Located between ANZ Events Centre and Wynyard Wharf
ESTIMATED INITIAL INVESTMENT COST TO BUILD MARINE PARK : $200 Million = 4 Years for return of initial investment costs based on an average of 500,000 visitors a year at an average spending rate of $100.00 per guest.
Residential AccommodationThree different styles of residences:
Pavilions - The pavilions are distinct, free-standing buildings which overlook Daldy Street Park. The individual pavilions are on a modest scale and provide for only one, two or three apartments on each level. On the ground floor of Daldy Street you will find boutique retailers and cafés, while the pavilion apartments are accessed from a lane off Pakenham Street.
Townhouses – A row of eight townhouses is accessed via private patios and individual garages that open to the lane. They are developed over three levels.
Apartments - The larger apartment building is situated behind the row of townhouses and is accessed from a Pakenham Street laneway. The apartments come with one, two or three bedrooms. The intimacy of the lane makes the ground floor of the apartments a perfect location for cafés and boutique retail.
The residences are priced from $1,095,000 for a two bedroom apartment with car park, and $1,460,000 for a three bedroom apartment with car park.
Penthouses built on 132 Hasley are expected to go for in excess of $5 million!
Commercial Accommodation
Park Hyatt Hotel
Hawkins Group Ltd & China Construction NZ Ltd signed the contract with Fu Wah International Group to deliver the Park Hyatt Auckland hotel in the Wynyard Quarter through a joint venture.
Hawkins built the ANZ Viaduct Events Centre and is building the ASB Theatre, working on streetscapingthroughout the Wynyard Quarter and on the Precinct Properties NZ Ltd Innovation Precinct project in Madden St.
The 7-storey hotel on the former Team NZ site fronting the Viaduct Basin will have a total floor area of 29,000m², 195 rooms, food & beverage outlets, event spaces, a spa and a fitness centre that includes a 25m pool.
Work is due to start this month for completion in late 2018.
Accessibility
WALKING/CYCLINGFrom Britomart Transport Centre, Wynyard Quarter is a short five-minute walk down Quay Street, on to Te Wero Island and across the new Wynyard Crossing bridge.
Also plans to build a new pedestrian bridge to establish a link to Victoria Park and adjacent areas.
DRIVINGFrom Fanshawe Street take either Halsey or Beaumont Street onto Jellicoe Street.
RED INNER CITY LINK BUSWynyard Quarter – Britomart-Queen Street – K-Road (return)
Monday to Saturday every 7 to 8 minutes from 6:25am to 11:25pm
Sundays and Public Holidays every 10 minutes for 7am to 11.20pm
010 BUSOnehunga to Wynyard Quarter via Ponsonby, Williamson Ave, Great North Road, Carrington Road and Mt Albert Road.
Monday to Friday every 30 minutes from 6:30am to 9am then every hour until 3pm. Then every half hour until 6pm
PUBLIC TRANSPORT
PUBLIC TRANSPORT CONTINUED
TRAMThe 15 minute tramway circuit loops around Halsey, Gaunt, Daldy and Jellicoe Streets between the Auckland Viaduct Basin and Westhaven Marina.
The tram however is currently closedwhile the final stages of the road developments in Wynyard Quarter takes placeand is expected to reopen in late 2016 and will have a new 1.8km extension added which connects the Wynyard Quarter loop toBritomart (shown in green in photo).
Initially admission prices were $2.00 foradults, $1.00 for children and $5.00 for a family pass, however this was some time ago and public transport prices have continuedto gradually rise so admission prices willbe revised prior to reopening of the tramservice.
Public Parking
CAR PARKSIf you're coming from Downtown Auckland, Viaduct Harbour or Te Wero Island, the Downtown car park is the most convenient located at31 Customs Street West.
Disability car parking is available in the Jellicoe Street Car Park at the end closest to the Playspace. There is also disability car parking available behind the Viaduct Events Centre.
There is a Wynyard Quarter carpark with the entranceoff Beaumont Street and Madden Street. First hour free—$2 hour following that.
Other street side parking availability is indicated on map.
LEGISLATION
RESOURCE MANAGEMENT ACT 1991 - The RMA promotes the sustainable management of natural and physical resources such as land, air and water.
(1) The purpose of this Act is to promote the sustainable management of natural and physical resources.
(2) In this Act, sustainable management means managing the use, development, and protection of natural and physical resources in a way, or at a rate, which enables people and communities to provide for their social, economic, and cultural wellbeing and for their health and safety while—
(a) Sustaining the potential of natural and physical resources (excluding minerals) to meet the reasonably foreseeable needs of future generations; and(b) Safeguarding the life-supporting capacity of air, water, soil, and ecosystems; and(c) Avoiding, remedying, or mitigating any adverse effects of activities on the environment.
BUILDING ACT 2004 –Building work in New Zealand is controlled by the Building Act 2004 and the various Building Regulations which includes the building code.
The purpose of the Act is to ensure that buildings:• Are safe, sanitary and have suitable means of escape from fire; and• Contribute to the physical independence and well being of people who use them• Are designed, constructed and able to be used in ways that promote sustainable development.The regulations prescribe the Building Code with which all building work must comply. Performance standards that must be met include building:• Durability• Fire safety• Sanitation (services and facilities)• Moisture control• Energy efficiency• Access
POTENTIAL ENVIRONMENTAL IMPACTs
POSITIVE NEGATIVE
• Increased conservation of local area including land, sea and air.
• Improvement of natural environment, especially soil and water.
• Improvement of infrastructure • Increased environmental awareness• Conservation programmes of marine
life (education through Marine Park).
• Water, air, soil, noise pollution.• Visual Pollution?• Water and waste disposal problems• Ecological disruption• Environmental hazards• Land use problems?
ENVIRONMENTAL IMPACT RISK ASSESSMENT
AIR QUALITY
VIADUCT WATER QUALITY
SURFACE WATER QUALITY
GROUND WATER QUALITY
SOIL QUALITY
NOISE LEVELS
TYPE OF IMPACT
EVALUATION OF IMPACT
NO IMPACT MINOR IMPACT MODERATE IMPACT SERIOUS IMPACT COMMENTS
WASTE DISPOSAL
VISUAL AMENITY
MANAGING ENVIRONMENTAL IMPACTs
NEGATIVE IMPACT EXAMPLES OF CONTROL MEASURES
Water pollution • Sewage treatment• Industrial waste water treatment• Erosion and sediment control for
construction sites• Control of urban run off
Visual pollution; Land use problems • Application of land zoning regulations• Architectural design standards• Strategic/appropriate location placement
of visual construct
Water and waste disposal problems • Installation of water supply and sewage disposal systems
• Use of proper solid waste disposal techniques
• Recycling of water where applicable
Environmental hazards • Construction of adequate drainage to prevent flooding
• Adequate setback of buildings from shoreline
Ecological disruption • Management of visitor flow/use control• Control on collection of plants, species
POTENTIAL SOCIO-ECONOMIC IMPACTs
POSITIVE NEGATIVE
• Economic benefits i.e. increased revenue generation and contribution to local economy
• Creates opportunities for employment• Infrastructure/development
investment• Increased carrying capacity• Increase in local tourism numbers
• Loss of economic benefit throughleakages and uneven distribution of benefits
• Infrastructure costs• Overcrowding and loss of amenities
for residents• Increase in prices e.g. local
commodities, land and real estate
SOCIO-ECONOMIc IMPACT RISK ASSESSMENT
LEAKAGES
INFRASTUCTURECOSTS
OVERCROWDING
INCREASE IN PRICES
TYPE OF IMPACT
EVALUATION OF IMPACT
NO IMPACT MINOR IMPACT MODERATE IMPACT SERIOUS IMPACT COMMENTS
MANAGING SOCIO-ECONOMIC IMPACTs
NEGATIVE IMPACT EXAMPLES OF CONTROL MEASURES
Loss of economic benefit through leakages • Provide financial incentives and trainings for local ownership
• Use local products and services• Use domestic investors with development where
possible
Increase in prices • Create collective agreements/consortiums between similar neighbouring regions/businesses
• Adopt local strategies to combat inflation• Offer cheaper alternatives to public sector
Infrastructure costs • Use more than one investor• Take into consideration both private AND public
stakeholders in development• Keep infrastructure construction/development
relevant• Use a mix of both private and public investment
Overcrowding • Establish control measures to preventovercrowding
• Promote/encourage and provide use of public transport to prevent traffic congestion
• Further develop area to increase carrying capacity
QUALMARK
Those businesses wanting to be specifically recognised for their sustainable tourism practices may be further evaluated through the Qualmark Enviro Award.Businesses are awarded for meeting strict environmental and social standards, with achievement levels of Gold, Silver and Bronze.
All businesses that display a Qualmark star grading or endorsed logo are evaluated on their environmental performance and have met minimum requirements including:
• Having facilities in place for recycling and initiatives to reduce waste, energy or water consumption
• Completing and using an environmental checklist to review the environmental impacts of the business
• The ability to verify all environmental claims
INVESTMENT AND KEY STAKEHOLDERS
• Private investment of $2 billion is needed towards development of Wynyard Quarter.
• The Auckland City Council has contributed $285 million towards development of the area.
• $750 million will be invested towards a block of 120 apartments which will be on the corner of Daldy and Madden Street. Willis Bond Capital Partners have invested $228 million towards this project.
• Expected cost of $504 million to develop area of which 5-10% are expected to be spent on clean up of soil contamination.
• $349 million going towards public infrastructure with $112 million from Auckland Regional Holdings (Auckland Regional Council) and $43 million from Auckland City Council.
• $2.5 million was spent on constructing the ‘Te Wero’ Bridge.• $200 million invested by Fu Wah International Group
towards the Park Hyatt Hotel with $2.5 million committed to the development of a new public space and art display in the area around the hotel in Wynyard Quarter.
KEY STAKEHOLDERS• Auckland City Council• Auckland Regional Holdings• Willis Bond Capital Partners• Athfield Architects• Fu Wah International Group• Architectus• LT McGuinness• Auckland Transport• Merlin Entertainments??
KEY OWNERS• Waterfront Auckland• Viaduct Harbour Holdings Ltd• ASB, Auckland Theatre Company Fonterra,
Marine Industries, Sanford’s, Viaduct Event’s Centre, Percy Vos Charitable Trust, Hyatt Corporation.
POTENTIAL RETURN AND COMPLETION
The redevelopment is projected to
extend over
30 years, directly supporting 20,000
new full-
time jobs in Auckland and contributing
towards
an additional 20,000 jobs across the
region.
By 2040 the
waterfront redevelopment is forecast
to
contribute $4.29 billion to Auckland’s
economy.
INNOVATION PRECINCTPopulation: 3,000 workersSite area: 14,000m² - 16,000²Proposed GFA: up to 48,000²Project timing: 2013 - 2018End value: $190m - $230m
RESIDENTIAL DEVELOPMENTPopulation: 1,100 - 1500 (600-1000 dwellings)Site area: 20,000² - 22,000²Proposed GFA: 65,000² - 100,000 ²Project timing: 2014 - 2030End value: $470m - $700m
HYATT HOTELNumber of rooms: 200 - 240Site area: 5,500²Proposed GFA: 17,000²Project timing: 2014 – 2018End value: $70m - $90m
2015
2020Proposed Development Sites after 2020
Thank you for watchingour presentation!
REFERENCES
http://www.wynyard-quarter.co.nz/history (Slides 2-3)https://en.wikipedia.org/wiki/Wynyard_Quarter (Slides 2-3)http://www.aucklandcity.govt.nz/council/documents/central/pdfs/annexure14c.pdf (Slide 4)http://www.aucklandcity.govt.nz/council/documents/central/pdfs/annexure14c.pdf (Slide 5)http://www.wynyard-quarter.co.nz/living-in-wynyard (Slide 20)https://www.panuku.co.nz/wynyard-quarter (Slide 20)http://www.wynyard-quarter.co.nz/news/park-hyatt-consent-approved (Slide 21)http://www.wynyard-quarter.co.nz/getting-here (Slide 23)https://at.govt.nz/projects-roadworks/wynyard-quarter/ (Slide 22&25)http://www.mfe.govt.nz/rma (Slide 26)https://www.consumer.org.nz/articles/the-building-act (Slide 26)http://www.tourismnewzealand.com/tools-for-your-business/qualmark/getting-your-qualmark/ (Slide 33)https://www.panuku.co.nz/www/uploads/moduleresourceitems/the-waterfront-plan-2012-9e08935901.pdf (Slide 34)https://www.panuku.co.nz/www/uploads/moduleresourceitems/sustainable-development-framework-2013- 198fab5712.pdf (Slide 35)https://www.youtube.com/watch?v=fAQoz_n3FYo (Slides 36 & 37)