Download - Notification of Connection Disconnection of Electricity · Notification of Connection Disconnection of Electricity Author: Department of Natural Resources, Mines and Energy Subject:

Transcript
Page 1: Notification of Connection Disconnection of Electricity · Notification of Connection Disconnection of Electricity Author: Department of Natural Resources, Mines and Energy Subject:

Department of Natural Resources, Mines and Energy

COAL MINING SAFETY & HEALTH REGULATION 2017 (CMSHR)

NOTIFICATION OF CONNECTION / DISCONNECTION OF ELECTRICALSUPPLY AT A COAL MINE

I,……………….………………………………………………………...………….……………………………, the SSE for the mine known as: (Print Name)

………………………………………………………..…….……………….………………………………………………………………………………. (Mine or Quarry Name)

with Mine Identification Number: MI…………………………….

Connection Date:

Details of Installed Load:

Disconnection Date:

Details of how the electrical installation/s have been made safe:

*Engineering assessment should be given to the change on the system maximum demand, load flow, protection systems, coordination systems and arc flash to understand the nature of the change

Signed: …………………..……………………………………………… Date: …….…….…. (Site Senior Executive) dd / mm / yy

Note: Retain original in Mine Record. Forward a copy to the Regional Inspector of Mines at the address closest to the location of the mine.

South Region PO Box 3679

Red Hill Q 4701 P (07) 4936 0184

[email protected]

North Region PO Box 1801

Mackay Q 4740 P (07) 4999 8512

[email protected]

Board of Examiners PO Box 15216

City East Q 4003 P (07) 3199 8037

[email protected]

V190108 Page 1 of 1