Topics
• SC06 Results• Infrastructure Update• New Services• Research
nlr.net© 2004 National LambdaRail, Inc
4
Overview
• Plan was to focus on FrameNet and PacketNet Service• Did do a few WaveNet circuits
• Atlantic Wave, 2 FrameNet, 2 PacketNet, misc others. • All FrameNet and PacketNet bandwidth was allocated
• 40 Gb total - primary and backup links• Hand scheduled, relied on users to honor the specific day
and time assignments. • Monitoring - NLRview
• Phase 1 measurement infrastructure installed• Measured FrameNet and PacketNet bandwidth in and out of
Tampa.
nlr.net© 2004 National LambdaRail, Inc
5
SC06 Users - PacketNet and FrameNet
• CalTech (CACR)• CANARIE• Center for Computation and
Technology at LSU• EVL (Calit2/CEOA)• Indiana University• KREONet, KISTI• NASA
• National Center for Data Mining
• Pittsburgh Supercomputing Center
• Purdue University• RENCI• Research Channel• University of Tokyo• Virginia Institute of
Technology
nlr.net© 2004 National LambdaRail, Inc
6
NLR PacketNet HOUS to ATLA
QuickTime™ and aTIFF (Uncompressed) decompressor
are needed to see this picture.
QuickTime™ and aTIFF (Uncompressed) decompressor
are needed to see this picture.
• Wednesday 11/15/06• Max 7.34 Gbps
• Week 11/10/15 - 11/16/06
nlr.net© 2004 National LambdaRail, Inc
7
QuickTime™ and aTIFF (Uncompressed) decompressor
are needed to see this picture.
QuickTime™ and aTIFF (Uncompressed) decompressor
are needed to see this picture.
FrameNet - Houston to Baton Rouge
• Wednesday - 11/15/06• Max of 9.931 Gbps
• Week 11/10/06 - 11/15/06
nlr.net© 2004 National LambdaRail, Inc
8
FrameNet Traffic Map
QuickTime™ and aTIFF (Uncompressed) decompressor
are needed to see this picture.
nlr.net© 2004 National LambdaRail, Inc
11
WaveNet Allocation
• 98 WaveNet Circuits (was 94 in 12/06)• ~312 out of 1029 segments allocated
• 30% of the backbone• Avg number of segments per circuit ~ 3
• Busiest Segments - Northern Route• CHIC to STAR - 24 waves or 75%• CHIC to CLEV - 19 waves or 48%• CHIC to DENV - 18 waves or 45%
• Expansion• Adding 15454 chassis on Northern route to accommodate
additional waves• Add capacity between CHIC and STAR
• 24 out of 32 Waves allocated• Investigating additional fiber and equipment
nlr.net© 2004 National LambdaRail, Inc
13
PacketNet
• Designed to be extremely reliable• Diverse backbone• Redundant route processors, power supplies• Redundant member connections
• 10 GE primary connection• 1 GE backup connection • Backup connection opposite direction and connects to different
router• PacketNet routes
• 7212 distinct routes• Announced (not all distinct)
• Members: 1263• FedNets: 1119• International: 8575
nlr.net© 2004 National LambdaRail, Inc
14
International Peers
Peer Starlight PacWave MANLAN v4 mcv6 uni v6 mcSURFnet 127 39 1 1CA*Net4 712 82 1 1TWAREN 218 137 10 Starlight router 2723 544 Kreonet 584 CUDI GLORIAD 1119 GEANT 2154 TransPac 441 117 CLARA 493 Ultralight/LHCnet 4 1 Singaren 28 Total 4776 1518 2281 919 13 2
nlr.net© 2004 National LambdaRail, Inc
16
FrameNet Services
• VLANs• Dedicated and non-dedicated bandwidth• Point-to-point or multi-point• Bandwidth increments of 100 Mbps
• Up to full link bandwidth• Additional backbone links are added if dedicated
bandwith exceeds 6 Gbps.
• Redundant non-dedicated VLAN available upon request for dedicated VLANS
nlr.net© 2004 National LambdaRail, Inc
17
FrameNet
• Non-dedicated bandwidth • No cost for bandwidth through 2007• Cost for additional port (if you want them)
• 1 GE or 10 GE available
• Service implementation• Close to on demand when port exists
• Annual contracts• Shorter durations are available upon request.
nlr.net© 2004 National LambdaRail, Inc
19
NLRview - NLR Measurement Infrastructure
• Phase 1 - Installation completed by January 2007• Phase 1: Atlanta, Baton Rouge, Houston• Phase 2 - Installation February/March 2007
• Seattle, Sunnyvale or Jacksonville• Chicago - last node to be installed - pending co-location
space and power.
• Uses so far:• Provided statistics for SC06• 10 GE performance tuning at SC06• Multicast testing and debugging
nlr.net© 2004 National LambdaRail, Inc
20
NLR Optical Switch
• Locate NLR Switch in Kansas City• Node which connects to 3 segments
• CHIC - KANS
• DENV - KANS
• TULS - KANS
• Scheduled to be installed end of February• Pending co-location space and power in KANS Node.
• Initial Projects• Collaboration with Enlightened project• Service restoration
nlr.net© 2004 National LambdaRail, Inc
23
Research
• Ongoing interest in using NLR infrastructure to support research projects.
• Proposal support• Quotes for services and infrastructure• Letters of Support
• New Projects• Requests for BGP debug information• Distance Learning Class
• Taught by Thomas Sterling at LSU– Participants - Louisiana Tech University, University
of Arkansas, MCND, and Masaryk University in the Czech Republic
nlr.net© 2004 National LambdaRail, Inc
24
ESS
• ESS Engineer to be assigned to • Every project• Every major user
– To track and anticipate additional needs• Inquiry to Installation
• ESS will track and support the entire process• Improved customer service
• Single point of contact until service placed into production• Support for NNRC and NSRC
• Review of network and science research abstract• Documentation
• Revise Research support documents• Release NLR Research Program