INSPECTION PROCEDURE IN THE DEPARTMENT OF TOWN AND COUNTRY PLANNING, PUNJAB
Service Name- Change of Land Use/N.O.C. in case of petrol pump, rice sheller, brick kiln.
Time Limit to provide Service under RTS - 15 Working Days after the submission of complete documents.
Level- District Town Planner
Name of office
Name of Officer Nature of Work No. of Days
District Town Planner
1. o/o District Town Planner
Receipt and marking of the case to concerned Planning Officer for site report. 1
2. Planning Officer Site Inspection and submission of report to A.T.P.
3
3. Patwari Scrutiny of revenue documents 3
4. Assistant Town Planner
Scrutiny of field report submitted by Planning Officer and submission of office report to D.T.P.
5
5. District Town Planner
Forwarding the report/comments to the nodal department.
3
Total No. of Days 15 working days
(A) CHECKLIST OF DOCUMENTS TO BE SUBMITTED BY APPLICANT FOR OBTAINING
CHANGE OF LAND USE/ N.O.C. IN CASE OF PETROL PUMP, RICE SHELLER, BRICK KILN.
1. Location map of site showing nearby features and roads to enable official staff to locate the proposed site of the colony.
2. Copy of Shajra Plan showing the site duly signed by Patwari. 3. Proof of ownership: Fard Jamabandi (Not older than two months). 4. Copies of sale deeds · 5. Copy of irrevocable consent at (Annexure-III) if the land belongs to another owner, authorizing the promoter to
obtain CLU and license for the development of colony on a non judicial stamp paper. 6. Non encumbrance certificate issued by concerned Tehsildar (Sub Registrar). 7. Draft of processing fee @Rs.5000/for first acre and Rs.1000 for every subsequent acre as per instructions issued
by state govt. vide memo no.18/65/2005-6hg-2/7102 dated14.7.2005.
(B) OFFICE REPORTS REQUIRED FOR ISSUANCE OF CLU
1. District Town Planner’s field report 2. Verification report by concerned Tehsildar
Service Name- Change of Land Use (For Residential, Industrial, Institutional upto 25 acres and Commercial upto 2 acres) Time Limit to provide Service under RTS- 23 Working Days after the submission of complete documents.
Level- Senior Town Planner
Name of office
Name of Officer Nature of Work No. of Days
Total No. of Days in
Concerned Office
Senior Town Planner
1. o/o Senior Town Planner
Receipt and diary of the case.
Forwarding the case to the concerned D.T.P. office for field report and C.R.O. office for revenue report.
1 1
2
District Town Planner
2. District Town Planner
Receipt and marking of the case to concerned Planning Officer for site report.
1
13
3. Planning Officer Site Inspection, preparation and submission of report to A.T.P.
3
4. Patwari Scrutiny of CRO report and revenue documents
2
5. Assistant Town Planner
Scrutiny of field report submitted by Planning Officer and submission of office report by A.T.P. to D.T.P.
5
6. District Town Planner
Scrutiny of report submitted by A.T.P. and forwarding the report to S.T.P. office.
2
Senior Town Planner
7. o/o Senior Town Planner
Receipt and diary of the case 1
8
8. Planning Officer Scrutiny of report received from D.T.P. and C.R.O. office and submitting the report/comments to A.T.P.
2
9. Assistant Town Planner
Scrutiny of report received from D.T.P. and C.R.O. office and submitting the report/comments to S.T.P.
3
10. Senior Town Planner
Issuance of Approval/Refusal. 2
Total No. of Days 23 working days
(A) CHECKLIST OF DOCUMENTS TO BE SUBMITTED BY APPLICANT FOR OBTAINING CHANGE OF
LAND USE/ N.O.C. IN CASE OF PETROL PUMP, RICE SHELLER, BRICK KILN.
1. Location map of site showing nearby features and roads to enable official staff to locate the proposed site of the colony. 2. Copy of Shajra Plan showing the site duly signed by Patwari. 3. Proof of ownership: Fard Jamabandi (Not older than two months). 4. Copies of sale deeds · 5. Copy of irrevocable consent at (Annexure-III) if the land belongs to another owner, authorizing the promoter to obtain CLU
and license for the development of colony on a non judicial stamp paper. 6. Non encumbrance certificate issued by concerned Tehsildar (Sub Registrar). 7. Draft of processing fee @Rs.5000/for first acre and Rs.1000 for every subsequent acre as per instructions issued by state
govt. vide memo no.18/65/2005-6hg-2/7102 dated14.7.2005.
(B) OFFICE REPORTS REQUIRED FOR ISSUANCE OF CLU
1. District Town Planner’s field report 2. Verification report by concerned Tehsildar
Service Name- Change of Land Use (For Residential, Industrial, Institutional area more than 25 acres and
Commercial more than 2 acres)
Time Limit to provide Service under RTS- No time Limit as the Competent Authority is Government.
Level- Government
Name of office Name of Officer Nature of Work No. of Days
Total No. of Days in Concerned
Office
Chief Town Planner
1. Assistant Town Planner
Receipt and diary of the case.
Forwarding the case to the concerned D.T.P. office for field report and C.R.O. office for revenue report.
1 1
2
District Town Planner
2. District Town Planner
Receipt and marking of case received from C.T.P. office.
1
11
3. Planning Officer Site Inspection and submission of report to A.T.P.
3
4. Patwari Scrutiny of CRO report and revenue documents
2
5. Assistant Town Planner
Scrutiny of report submitted by Planning Officer and submission of office report by A.T.P. to D.T.P.
3
6. District Town Planner
Scrutiny of office report submitted by A.T.P. and forwarding the report to S.T.P. office.
2
Senior Town Planner
7. o/o Senior Town Planner
Receipt and diary of the case 1
8
8. Planning Officer Scrutiny of field report received from D.T.P. office and submitting the report/comments to A.T.P.
2
9. Assistant Town Planner
Scrutiny of report submitted by Planning Officer and submission of office report by A.T.P. to S.T.P.
3
10. Senior Town Planner
Scrutiny of report submitted by A.T.P. and forwarding the report to C.T.P. office.
2
Chief Town Planner
11. o/o Chief Town Planner
Receipt and diary of the case 1
14
12. Assistant Town Planner (H.Q.)
Scrutiny of report received from S.T.P. and C.R.O. office and submitting the report/ comments to D.T.P (HQ).
7
13. District Town Planner (H.Q.)
Scrutiny of report/comments submitted by A.T.P. and submission of report to S.T.P(HQ).
2
14. Senior Town Planner (H.Q.)
Scrutiny of report/comments submitted by D.T.P. and submission of report to C.T.P.
2
15. Chief Town Planner
Forwarding the report to Government
2
Total No. of Days 35 working days
(A) CHECKLIST OF DOCUMENTS TO BE SUBMITTED BY APPLICANT FOR OBTAINING CHANGE OF
LAND USE/ N.O.C. IN CASE OF PETROL PUMP, RICE SHELLER, BRICK KILN.
1. Location map of site showing nearby features and roads to enable official staff to locate the proposed site of the colony. 2. Copy of Shajra Plan showing the site duly signed by Patwari. 3. Proof of ownership: Fard Jamabandi (Not older than two months). 4. Copies of sale deeds · 5. Copy of irrevocable consent at (Annexure-III) if the land belongs to another owner, authorizing the promoter to obtain CLU
and license for the development of colony on a non judicial stamp paper. 6. Non encumbrance certificate issued by concerned Tehsildar (Sub Registrar). 7. Draft of processing fee @Rs.5000/for first acre and Rs.1000 for every subsequent acre as per instructions issued by state
govt. vide memo no.18/65/2005-6hg-2/7102 dated14.7.2005.
(B) OFFICE REPORTS REQUIRED FOR ISSUANCE OF CLU
1. District Town Planner’s field report 2. Verification report by concerned Tehsildar
Service Name- Sanction of Building Plans for size upto 500 sq. mtrs. (Fresh and Revised)
Time Limit to provide Service under RTS- 15 Working Days after the submission of complete documents.
Level- District Town Planner
Name of office Name of Officer Nature of Work No. of Days
District Town
Planner
1. o/o District Town Planner
Receipt and diary of the case. 1
2. Planning Officer Submission of field inspection by Planning Officer
Scrutiny of Building Plans submitted by the applicant with respect to PUDA Building Rules, C.L.U. approval and permissions granted by other departments and preparation of report.
3
3
3. Patwari Scrutiny of CRO report and revenue documents
2
4. Assistant Town Planner
Scrutiny of report/comments submitted by Planning Officer and submission of report to D.T.P.
4
5. District Town Planner
Issuance of approval/Refusal to the applicant.
2
Total No. of Days 15 working days
CHECKLIST OF DOCUMENTS REQUIRED TO BE SUBMITTED FOR APPROVAL OF BUILDING PLANS
1. Building plan drawings (Site Plan, Building Floor Plans ,Elevation & Sections drawn to a readable and manageable scale)
2. Approved Layout plan copy of the project Drawing no. _____________ . 3. Zoning plan of project with khasra nos. Drawing no. _____________. 4. Copy of approval of CLU granted by competent authority showing khasra wise area detail. 5. Any other document if required.
Service Name- Sanction of Building Plans upto 5000 sq. mtrs. (Fresh and Revised)
Time Limit to provide Service- 15 Working Days after the submission of complete documents.
Level- Senior Town Planner
Name of office
Name of Officer Nature of Work No. of Days
Total No. of Days in
Concerned Office
Senior Town Planner
1. o/o Senior Town Planner
Sending the documents to concerned D.T.P. office for field report and receipt of documents by D.T.P. office.
1 1
District Town Planner
2. o/o District Town Planner
Receipt and diary of the case 1
7
3. Planning Officer Site Inspection and submission of report to A.T.P.
3
4. Patwari Scrutiny of revenue documents and ownership as per approved CLU
1
5. Assistant Town Planner
Scrutiny of field report submitted by Planning Officer and submission of office report to D.T.P.
1
6. District Town Planner
Scrutiny of office report submitted by A.T.P. and forwarding the report to S.T.P. office.
1
Senior Town Planner
7. o/o Senior Town Planner
Receipt and diary of the case 1
7
8. Planning Officer Scrutiny of Building Plans with respect to the report received from D.T.P. office, PUDA Building Rules, CLU approval and permissions granted by other departments and submission of the report to A.T.P.
3
9. Assistant Town Planner
Scrutiny of report/comments submitted by Planning Officer and submission of report to S.T.P..
2
10. Senior Town Planner
Issuance of approval/Refusal to the applicant.
1
Total No. of Days 15 working days
CHECKLIST OF DOCUMENTS REQUIRED TO BE SUBMITTED FOR APPROVAL OF BUILDING PLANS
1. Building plan drawings (Site Plan, Building Floor Plans ,Elevation & Sections drawn to a readable and manageable scale)
2. Approved Layout plan copy of the project Drawing no. _____________ . 3. Zoning plan of project with khasra nos. Drawing no. _____________. 4. Copy of approval of CLU granted by competent authority showing khasra wise area detail. 5. Any other document if required.
Service Name- Sanction of Building Plans for 5000-10,000 sq. mtrs. (Fresh and Revised)
Time Limit to provide Service- 45 Working Days after the submission of complete documents.
Level- Chief Town Planner
Name of office
Name of Officer Nature of Work No. of Days
Total No. of Days in
Concerned Office
Chief Town Planner
1. o/o Chief Town Planner
Sending the documents to concerned D.T.P. office for field report and receipt of documents by D.T.P. office.
1 1
District Town Planner
2. o/o District Town Planner
Receipt and diary of the case 1
9
3. Planning Officer Site Inspection and submission of report to A.T.P.
3
4. Assistant Town Planner
Scrutiny of field report submitted by Planning Officer and submission of office report to D.T.P.
3
5. District Town Planner Scrutiny of office report submitted by A.T.P. and forwarding the report to S.T.P. office.
2
Senior Town Planner
6. o/o Senior Town Planner
Receipt and diary of the case 1
7
7. Planning Officer Scrutiny of report received from D.T.P. office and submission to A.T.P.
2
8. Assistant Town Planner
Scrutiny of report/comments submitted by Planning Officer and submission of report to S.T.P..
3
9. Senior Town Planner Scrutiny of office report submitted by A.T.P. and forwarding the report to C.T.P. office.
1
Chief Town Planner
10. o/o Chief Town Planner
Receipt and diary of the case 1
28
11. Planning Officer Scrutiny of Building Plans with respect to the report received from S.T.P. office, PUDA Building Rules, CLU approval and permissions granted by other departments and submission of the report to A.T.P.
9
12. Patwari Scrutiny of revenue documents and ownership as per approved CLU
3
13. Assistant Town Planner
Scrutiny of report/comments submitted by Planning Officer and submission of report to D.T.P..
7
14. District Town Planner Scrutiny of report/comments submitted by A.T.P. and submission of report to S.T.P..
3
15. Senior Town Planner Scrutiny of report/comments submitted by D.T.P. and submission of report to C.T.P..
3
16. Chief Town Planner Issuance of approval/Refusal to the applicant
2
Total No. of Days 45 working days
CHECKLIST OF DOCUMENTS REQUIRED TO BE SUBMITTED FOR APPROVAL OF BUILDING PLANS
1. Building plan drawings (Site Plan, Building Floor Plans ,Elevation & Sections drawn to a readable and manageable scale)
2. Approved Layout plan copy of the project Drawing no. _____________ . 3. Zoning plan of project with khasra nos. Drawing no. _____________. 4. Copy of approval of CLU granted by competent authority showing khasra wise area detail. 5. Any other document if required.
Service Name- Sanction of Building Plans for size of more than 10,000 sq. mtrs. (Fresh and Revised)
Time Limit to provide Service- 60 Working Days after the submission of complete documents.
Level- Chief Town Planner
Name of office
Name of Officer Nature of Work No. of Days
Total No. of Days in
Concerned Office
Chief Town Planner
1. o/o Chief Town Planner
Sending the documents to concerned D.T.P. office for field report and receipt of documents by D.T.P. office.
1 1
District Town Planner
2. o/o District Town Planner
Receipt and diary of the case 1
18
3. Planning Officer Site Inspection with respect to approved Building Plans.
Preparation and submission of technical report to A.T.P.
3
7
4. Assistant Town Planner
Scrutiny of field report submitted by Planning Officer and submission of office report to D.T.P.
5
5. District Town Planner Scrutiny of office report submitted by A.T.P. and forwarding the report to S.T.P. office.
2
Senior Town Planner
6. o/o Senior Town Planner
Receipt and diary of the case 1
7
7. Planning Officer Scrutiny of report received from D.T.P. office and submission to A.T.P.
2
8. Assistant Town Planner
Scrutiny of report/comments submitted by Planning Officer and submission of report to S.T.P..
3
9. Senior Town Planner Scrutiny of office report submitted by A.T.P. and forwarding the report to C.T.P. office.
1
Chief Town Planner
10. o/o Chief Town Planner
Receipt and diary of the case 1
34
11. Patwari Scrutiny of revenue documents and ownership as per approved CLU
3
12. Planning Officer Scrutiny of Building Plans with respect to the report received from S.T.P. office, PUDA Building Rules, CLU approval and permissions issued by other departments and submission of the report to A.T.P.
15
13. Assistant Town Planner
Scrutiny of report/comments submitted by Planning Officer and submission of report to D.T.P.
6
14. District Town Planner Scrutiny of report/comments submitted by A.T.P. and submission of report to S.T.P.
5
15. Senior Town Planner Scrutiny of report/comments submitted by D.T.P. and submission of report to C.T.P.
2
16. Chief Town Planner Issuance of approval/Refusal to the applicant
2
Total No. of Days 60 working days
CHECKLIST OF DOCUMENTS REQUIRED TO BE SUBMITTED FOR APPROVAL OF BUILDING PLANS
1. Building plan drawings (Site Plan, Building Floor Plans ,Elevation & Sections drawn to a readable and manageable scale)
2. Approved Layout plan copy of the project Drawing no. _____________ . 3. Zoning plan of project with khasra nos. Drawing no. _____________. 4. Copy of approval of CLU granted by competent authority showing khasra wise area detail.
5. Any other document if required.
Service Name- Issuance of Completion/Partial Completion Certificate (upto 500 sq. mtrs.)
Time Limit to provide Service under RTS- 15 Working Days after the submission of complete documents.
Level- District Town Planner
Name of office Name of Officer Nature of Work No. of Days
District Town Planner
1. Planning Officer Site visit to verify construction on site with respect to approved building plans.
Preparation and submission of technical and field report to A.T.P..
3
7
2. Assistant Town Planner
Scrutiny of report submitted by Planning Officer and submission of report to D.T.P..
3
3. District Town Planner
Issuance of Completion/ Partial Completion Certificate
2
Total No. of Days 15 working days
CHECKLIST OF DOCUMENTS REQUIRED TO BE SUBMITTED FOR ISSUANCE OF COMPLETION/PARTIAL
CERTIFICATE
1. Request for issuance of Completion certificate in Form ‘C’ of PUDA Building Rules 2013. 2. Completion certificate by Architect. 3. Completion certificate by Plumber. 4. Final structure safety certificate issued by a structural engineer. 5. Final Fire N.O.C. issued by Competent Authority. 6. Any other document if required.
Service Name- Issuance of Completion/Partial Completion Certificate (500 to 5000 sq. mtrs)
Time Limit to provide Service under RTS- 15 Working Days after the submission of complete documents.
Level- Senior Town Planner
Name of office
Name of Officer Nature of Work No. of Days
Total No. of Days
Senior Town Planner
1. o/o Senior Town Planner
Forwarding the case to concerned D.T.P. for verification of constructed building on site with respect to approved building plans.
1 1
District Town Planner
2. Planning Officer Site visit to verify construction on site with respect to approved building plans.
Preparation and submission of office report to A.T.P..
3
3
9 3. Assistant Town Planner
Scrutiny of report submitted by Planning Officer and submission of report to D.T.P.
2
4. District Town Planner
Scrutiny of report submitted by A.T.P. and forwarding the report to S.T.P. office.
1
Senior Town Planner
5. Planning Officer Scrutiny of report received from D.T.P. office and submission of report to A.T.P.
3
5 6. Assistant Town
Planner Scrutiny of report received from
Planning Officer and submission of report to S.T.P..
1
7. Senior Town Planner
Issuance of Completion/ Partial Completion Certificate
1
Total No. of Days 15 working days
CHECKLIST OF DOCUMENTS REQUIRED TO BE SUBMITTED FOR ISSUANCE OF COMPLETION/PARTIAL
CERTIFICATE
1. Request for issuance of Completion certificate in Form ‘C’ of PUDA Building Rules 2013. 2. Completion certificate by Architect. 3. Completion certificate by Plumber. 4. Final structure safety certificate issued by a structural engineer. 5. Final Fire N.O.C. issued by Competent Authority. 6. Any other document if required.
Service Name- Issuance of Completion/Partial Completion Certificate (above 5000-10,000 sq. mtrs.)
Time Limit to provide Service under RTS- 23 Working Days after the submission of complete documents.
Level- Chief Town Planner
Name of office
Name of Officer Nature of Work No. of Days
Total no. of Days
Chief Town Planner
1. Chief Town Planner
Forwarding the case to concerned D.T.P. for verification of constructed building on site with respect to approved building plans.
1 1
District Town Planner
2. Planning Officer Site visit to verify construction on site with respect to approved building plans.
Preparation and submission of office report to A.T.P.
3
1
6 3. Assistant Town Planner
Scrutiny of report submitted by Planning Officer and submission of report to D.T.P..
1
4. District Town Planner
Scrutiny of report submitted by A.T.P. and forwarding the report to S.T.P. office.
1
Senior Town Planner
5. Planning Officer Scrutiny of report received from D.T.P. office and forwarding the comments/report to A.T.P.
2
4
6. Assistant Town Planner
Scrutiny of report submitted by Planning Officer and submission of report to S.T.P..
1
7. Senior Town Planner
Scrutiny of report submitted by A.T.P. and forwarding the report to C.T.P. office.
1
Chief Town Planner
8. Planning Officer Analysis of report received from D.T.P. and forwarding the comments to A.T.P.
5
12
9. Assistant Town Planner
Scrutiny of report submitted by Planning Officer and submission of report to D.T.P..
3
10. District Town Planner
Scrutiny of report submitted by A.T.P. and submission of report to S.T.P.
2
11. Senior Town Planner
Scrutiny of report submitted by D.T.P. and submission of report to C.T.P.
1
12. Chief Town Planner
Issuance of Completion/ Partial Completion Certificate
1
Total No. of Days 23 working days
CHECKLIST OF DOCUMENTS REQUIRED TO BE SUBMITTED FOR ISSUANCE OF COMPLETION/PARTIAL
CERTIFICATE
1. Request for issuance of Completion certificate in Form ‘C’ of PUDA Building Rules 2013. 2. Completion certificate by Architect. 3. Completion certificate by Plumber. 4. Final structure safety certificate issued by a structural engineer. 5. Final Fire N.O.C. issued by Competent Authority. 6. Any other document if required.
Service Name- Issuance of Completion/Partial Completion Certificate (more than 10,000 sq. mtrs.)
Time Limit to provide Service under RTS- 30 Working Days after the submission of complete documents.
Level- Chief Town Planner
Name of office
Name of Officer Nature of Work No. of Days
Total No. of Days
Chief Town Planner
1. o/oChief Town Planner
Forwarding the case to concerned D.T.P. for verification of constructed building on site with respect to approved building plans.
1 1
District Town Planner
2. Planning Officer Site visit to verify construction on site with respect to approved building plans.
Preparation and submission of report to A.T.P..
3
5
11 3. Assistant Town Planner
Scrutiny of report submitted by Planning Officer and submission of report to D.T.P..
2
4. District Town Planner
Scrutiny of report submitted by A.T.P. and forwarding the report to S.T.P. office.
1
Senior Town Planner
5. Planning Officer Scrutiny of report received from D.T.P. office and forwarding the comments/report to A.T.P.
2
4
6. Assistant Town Planner
Scrutiny of report submitted by Planning Officer and submission of report to S.T.P..
1
7. Senior Town Planner
Scrutiny of report submitted by A.T.P. and forwarding the report to C.T.P. office.
1
Chief Town Planner
8. Planning Officer o/o Chief Town Planner
Analysis of report received from D.T.P. and submission of report to A.T.P.
8
14
9. Assistant Town Planner
Scrutiny of report submitted by Planning Officer and submission of report to D.T.P..
2
10. District Town Planner
Scrutiny of report submitted by A.T.P. and submission of report to S.T.P.
2
11. Senior Town Planner
Scrutiny of report submitted by D.T.P. and submission of report to C.T.P.
1
12. Chief Town Planner
Issuance of Completion/ Partial Completion Certificate
1
Total No. of Days 30 working days
CHECKLIST OF DOCUMENTS REQUIRED TO BE SUBMITTED FOR ISSUANCE OF COMPLETION/PARTIAL
CERTIFICATE
1. Request for issuance of Completion certificate in Form ‘C’ of PUDA Building Rules 2013. 2. Completion certificate by Architect. 3. Completion certificate by Plumber. 4. Final structure safety certificate issued by a structural engineer. 5. Final Fire N.O.C. issued by Competent Authority. 6. Any other document if required.
Service Name- Land Use Classification.
Time Limit to provide Service under RTS- 5 Working Days after the submission of complete documents.
Level- District Town Planner
Name of office
Name of Officer Nature of Work No. of Days
District Town Planner
1. Planning Officer Site Inspection and submission of report to A.T.P..
3
2. Assistant Town Planner
Scrutiny of field report submitted by Planning Officer and submission of report to D.T.P.
1
3. District Town Planner
Issuance of Land Use Classification Certificate.
1
Total No. of Days 5 working days
(A) CHECKLIST OF DOCUMENTS TO BE SUBMITTED BY APPLICANT FOR OBTAINING LAND
USE CLASSIFICATION
1. Location map of site showing nearby features and roads to enable official staff to locate the proposed site of the colony.
2. Copy of Shajra Plan showing the site duly signed by Patwari. 3. Proof of ownership: Fard Jamabandi (Not older than two months). 4. Copies of sale deeds · 5. Copy of irrevocable consent at (Annexure-III) if the land belongs to another owner, authorizing the promoter to
obtain CLU and license for the development of colony on a non judicial stamp paper. 6. Non encumbrance certificate issued by concerned Tehsildar (Sub Registrar). 7. Draft of processing fee @Rs.5000/for first acre and Rs.1000 for every subsequent acre as per instructions issued
by state govt. vide memo no.18/65/2005-6hg-2/7102 dated14.7.2005.
PART-A
Check list for Scrutiny of Building Plan (office use)
Name of the project
Type of Project
Area of project
C.L.U permitted/Purpose
Sr. No. ITEM REMARKS
1 Site Area as per approved CLU
2 Whether site according to CLU/Zoning Plan/Layout Plan?
3 Whether layout approved by competent authority or not?
4 Zoning Plan approved or not?
5 Existing approach road i.e. NH/SH and widening and no construction zone (if required)
6 Status of Building plan as per PUDA Building Rules
Ground Coverage
F.A.R
Height
Set backs
Distance between building blocks
Parking
Play Ground / Green / Parks
Basement
Travelling distance
Stair/ramps/lift
Public utilities i.e. Toilet for Male/Female /Handicapped
Provision of facilities for handicapped
7 Whether location of gates & No. as per zoning or not?
8 Whether Rain Water Harvesting provided or not?
9 Whether disposal of sewage and solid waste provided or not?
10 Source of Water Supply?
11 NOCs/ Clearances/ Charges required
ITEM REQUIRED (YES/NO) PROVIDED
(YES/NO)
REMARKS
Structural Safety Certificate
Fire safety provision/noc from Fire
department
Sr. No. ITEM REMARKS
NOC from A.A.I for height
Permission for access from
Schedule road/State Highway
Permission for access from
National Highway
E.D.C
SIF
License fee
Scrutiny Fee
Labour Cess
Any other Requirement from Case
To case
PART-B
Check list for Scrutiny of Building Plan (for field visit)
Name of the project
Type of Project
Area of project
C.L.U permitted/Purpose
Sr. No. ITEM REMARKS
1 Site Area with dimensions
2 Width of approach road
3 Whether the site is located on scheduled road/ National
Highway or not?
4 Whether approach is drawn through forest area and any
forest area is located within the site.
5 Status of Site (Vacant/Constructed/Partially
Constructed)
6 Existing Facilities(Provision of Water Supply/Sewerage
system/electricity/street light/storm water)
7 Report regarding revenue rastas whether terminating
within the site or connects the area/building outside the
site boundary.
8 Location of red category industry within 500mts. Radius
of site.
9 Location & alignment of HT line if passing through the
site etc
10 Location of Heritage Building or Protected monument
within 100 meter radius of site.