November 29, 2018
CBTC Case Study –MTA Maryland’s Experience with a Brown Field Installation
1
AGENDA
♦ Overview of MTA Metro♦ Project Background♦ Project Overview♦ HAB Solution♦ Challenges and Solutions♦ Questions
2
MTA METRO AT A GLANCE
♦ Grade separated♦ 11th Largest in the US – Nearly 15 Million Passenger
Trips Annually♦ 15.5 miles long
• Owings Mills to Johns Hopkins Hospital♦ Dedicated inbound and outbound track♦ Single Maintenance and Storage Yard♦ 14 mainline stations (6 above ground/ 8 underground)♦ Powered by 750 VDC Third Rail♦ Current Fleet of 100 Vehicles and Train Control
System are 35 years old• Original Railcars – Budd Company• Original Train Control – Ansaldo Breda
♦ Headway• 8 Minutes Peak• 10 to 15 Minutes Off-peak
METRO HISTORY
4
• Phase 1 Section A (Northwest Line): was completed in November 1983 and it extends northwest from downtown Baltimore. It consists of a 5.55-mile underground section and a 2-mile aerial section.
• Phase 2 Section B (Northwest Line extension): was completed in July of 1987 and operates at grade level. It extends for 6 miles.
• Phase 3 Section C (Northeast Line): was completed in 1996. It is 1.5 miles long and it operates Northeast underground from the city center.
Train Control Project Overview♦ Data Communications System (DCS):
• Fiber Optic Cable System (FOCS)• Ground Based Network (GBN)• Wireless Communication System (WCS)
♦ Solid State Interlockings with existing signals, switches, and snow melters
♦ CBTC – Zone Controllers and Carborne Controllers
♦ ATS: Hardware/software and interfaces to SCADA, “Next Train Arrival” messaging, and Google Transit
♦ Axle counters♦ Yard Test Track♦ Removal of existing track circuits
Phased Installation for Brownfield Success
P2SSI Installation – Continue
revenue operation with existing fleet
P3 Install and commission backup/primary ATS
P1 Install and Commission new DCS P4
Install and commission CBTC wayside and room equipment in
segments
P5Delivery and dynamic testing of
new railcars. New cars increase, old cars decrease
P6Install new wayside cables and
remove AF track circuits in sections
All work will begin at OM and move towards JH
Migration/Cutover Planning
♦ Phase 1 – DCS (Fiber, GBN, WCS)• All fiber and network hardware installed. • Wireless access points installed• No cutovers during Phase 1• Utilize existing conduit as much as possible
o Remove unused cables – highway encroachment, sound phoneo Move wayside cable replacement from Phase 2 to Phase 6 – allowing conduits
to be freed later in the project.
Migration/Cutover Planning – Phase 1 DCS
Migration/Cutover Planning – Phase 1 DCS
♦ In order to progress work to Phase 2 before Phase 1 is complete, a portion of the North Ring will be closed as the first SSI locations go into service.
Migration/Cutover Planning
♦ Phase 2 – SSI Installation OM to JH• Microlok installation begins at OM working towards JH. • Testing will be conducted during non-revenue service from Midnight to
4AM. • Over and Back (Existing to New) is accomplished by removing and
replacing plug couplers into defined mating connections• Existing fleet is in operation with Microlok control of all existing track circuit
equipment. • Requires interface to existing train management system and existing track
circuits. Existing ATS provides control and monitoring during Phase 2.• Locations will be released for revenue service once installed, tested, and
safety certified.
Existing Equipment
11
Phase 1 - DCS
12
Installation and Testing
13
Non-Revenue Operation
14
Safety Certified Revenue Service
15
Migration/Cutover Planning
♦ Phase 3 – Primary/Backup ATS• MTA has a Primary OCC and a Backup OCC, which also serves as a training
location. • Migration to the new ATS will take advantage of the existence of a BOCC by
installing, testing, and commissioning in that location first. Allowing system to be fully implemented and tested.
• BOCC will control and monitor the line while the new ATS equipment is installed and commissioned in the MOCC.
• Once the MOCC is tested and commissioned, the system will be entirely controlled and monitored by the new ATS.
• Requires interface to existing SCADA System. o Existing ATS will continue to serve to gather field I/O for MTA’s SCADA system. An
intermediate server with serve as data pass-through to the new ATS. This provides a clear demarcation of responsibility for the two system. SCADA will remain in service after the project is complete.
Migration/Cutover Planning
DCS Backbone B
DCS Backbone A
Main OCC LAN α & β to OCC Server Room
Color Laser Printer Pool
(x4)
MOCC (Metro Operation Control Centre) MOCC Server Room
Cabling to Backbone(existing Fiber Optic)
Cabling to MOCC(CAT6 & Fiber Optic)
ATS Server MTASYS001
SAN
Patch Panel
PWR & GND
ATS System
KVM & Console Switch
PWR & GND
ATS Rack 001
DB ServerMTAHST001
Interfaces
SCADA
CIS
Google Transit
CBTC System
Frontam
Zone Controller
Twenty Remote Workstation Locations(exact locations, and QTY. TBD via RFI)
24" 24" 24"
ATS WorkstationMTACWS001
24" 24" 24"
24" 24" 24"
ATS WorkstationMTACWS002
24" 24" 24"
24" 24" 24"
ATS WorkstationMTACWS003
24" 24" 24"
ATS WorkstationMTACWS###
(x20)
24" 24" 24"
Typical Field + Depot + Test Track (x11)
Interfaces
MLK
WirelessATS LATS wrkstATS LATS α
L3 Switch αPatch Panel
PWR & GND
ATS System
L3 Switch β
PWR & GND
ATS LATS β
KVM Switch
DCS SW ADCS SW B
DCSsystem
Main BOCC LAN α & β to BOCC Server Room
Color Laser Printer Pool
(x4)
BOCC (Backup Operation Control Centre) Main Shop TC&C
ATS Server MTASYS101
SAN
Patch Panel
PWR & GND
ATS System
KVM & Console Switch
PWR & GND
ATS Rack 101
OVW ServerMTAOVW101
Interfaces
SCADA
CIS
Google Transit
CBTC System
Frontam
Zone Controller
24" 24" 24"
ATS WorkstationMTACWS101
24" 24" 24"
24" 24" 24"
ATS WorkstationMTACWS102
24" 24" 24"
24" 24" 24"
ATS WorkstationMTACWS103
24" 24" 24"
DCSsystem
MIMIC Panel(1x1 matrix of 55” Panels)
Matrox Extio Receiver (1)
Cabling to BOCC(CAT6 & Fiber Optic)
SCADA
DCS system
Cabling to Backbone(New Fiber Optic)
Provided by Installer
Cabling to Backbone(existing Fiber Optic)
Cabling to Backbone(New Fiber Optic)
Provided by Installer
12
Migration/Cutover Planning
♦ Phase 4 – CBTC Goes Into Service• Install and commission wayside and on-board CBTC for the Pilot Train (3
Married Pair Train)• Low speed testing can occur on the test track at Wabash Yard. Full-speed
testing will occur on the main-line• Mixed mode operation begins. Non-CBTC Trains will operate with fixed
block. CBTC Trains will utilize MAL• Phase 4 culminates in revenue service of the
o SSIo ZCo Existing cab codeso New ATS
Migration/Cutover Planning
Migration/Cutover Planning♦ Phase 5 – Installation and dynamic testing of all new car
equipment. New cars increase, old cars decrease• Mixed mode operation continues.
Migration/Cutover Planning
♦ Phase 6 – Install new wayside cables and Remove AF track circuits in sections.
• All new vehicles will be in service under CBTC Control. • Axle counters will be installed.• Wayside cables will be installed as track circuit cables are
removed and conduits are made available.
Hitachi Ansaldo Baltimore Offering
Challenges and Solutions
♦ Space Limitations♦ Infrastructure Limitations♦ On-going Maintenance and Repairs♦ Other Projects♦ Mixed Fleet Operation♦ Training and Existing Skillsets
Space Limitations
24
Space Limitations
25
Space Limitations
26
Infrastructure Limitations
27
On-going Maintenance/Repairs and Other Projects
Maintenance/Repairs Project WorkQ3/4 2018 – 3rd Rail Heater Controls Conduit Identification/Space LiberationQ4 2018 – Tie and Rail Repairs Inner Duct InstallationQ1 2019 – JH Interlocking Replacement DCS Fiber InstallationQ2 2019 – Asbestos Removal SSI InstallationsQ1 2020 – State Center/Charles Center Interlocking Replacement – Permanent Magnet Motors
SC/CC SSI CompleteCBTC Installation
Q1 2021 – Rogers Avenue, Reisterstown Plaza, Northwest Yard Interlockings
Continued mixed-mode operation. Other projects must consider SSI rather than Relays
• Coordinate early and often• Flexibility – Permanent Magnet Motors• Plan for changes
Mixed Fleet Operation
Phased Migration Maintain track Circuits while implementing CBTC
Develop Operational Scenarios
Interface to existing TTM followed by migration to new ATS
Training
Training Planning with Contractor
Identify new skillsets required
Early work with Union
Vernon G. Hartsock, PMPDeputy Chief/Chief Engineer
Maryland Transit AdministrationOffice of Engineering & Construction6 Saint Paul Street, Room 736, Baltimore MD 21202Office: 410-767-3323 Fax: [email protected]