Sunderland Faculty of Business & Law Undergraduate ProgrammesSIM 335 MANAGING PROJECTS
Individual Assignment Report
Project management for Juron Ltd. and Jigama Ltd.
in executing business strategyby Pham Trung Hieu, Intake 4 | ISME, National Economics University, 2011
H a n o i , 2 0 1 1
8/11/2019 MP - asm mu (2).docx
2/47
2
SCENARIO 1: Juron Ltd.
From sequence of activities provided, a network diagram is formed properly combined
with detailed explanations of how activities, float, duration and critical path are
identified.
1.1Network diagram (AON)(see Appendix 1)
To complete project, network diagram has START activity and FINISH ac tivity at
the beginning and the end. They are dummy activities.
1.2 Timing of activities
Determining timing of activity concerns about activitys Earliest-Start-Time, Earliest-
Finish-Time, Latest-Start-Time, Latest-Finish-Time. According to Field and Keller
(2005), EST/EFT are calculated using forward passand LST/LFT are determined using
backward pass technique (same as Activity-On-Arrow.) Forward pass must be
accomplished before fulfilling backward pass.
Forward pass:
Starting activity always has EST=0. EFT formula:
EFT(n)=EST(n)+D(n)
EST of each activity (notstart) is equal to EFT of its immediately predecessor.
EST(n)=EFT(n-1)
When multiple tasks converge, next activitys EST equals the highest of preceding EFT
times. Example: G has 5 predecessors: B,C,D,E,F and EFT(F)=13>EFT(B,C,D,E); hence
EST(G)=13. The reason is activity F needs to be completed before beginning activity G.
8/11/2019 MP - asm mu (2).docx
3/47
8/11/2019 MP - asm mu (2).docx
4/47
4
1.4 Calendaring project
Projects EFT is 93 days. With a 5-day-work-week (no holidays), it takes 18 weeks and 3
days to complete. If project starts on Monday, 16th
January 2012 then EFT will be
Wednesday, 23rd
May 2012(see appendix 4).
1.5 Effect of delaying activities
1.5.1 If delaying activity B 2 days, it will not affect to the entire project because this
activity has 4-day-float (more than 2 days delayed) and it is not on critical path.
1.5.2 Because activity P has zero float and on critical path hence if delaying P 2 days, it
delays project2 days.
1.5.3 Because O has no float and on critical path thus if activity O is delayed 1 day, it
delays project1 day.
(see Appendix 5)
1.6 Advantages and limitations
From Field and Keller (2005) and own ideas two advantages and three limitations of
network diagram are:
Helps project manager determining total time for projectand assessing whether the
planned timing match with total time allowed.
Because of graphical present, it is easy to identify logical relationships between
activities and flow of activities to accomplish project.
Much time and resources needed to generate large networks, hence start of project
can be behind scheduled.
8/11/2019 MP - asm mu (2).docx
5/47
5
There are difficulties in estimating duration. The managers objective opinions
normally underestimate time for activities. It leads to behind schedule and costs are
doubled.
Non-flexibility in controllingthe balance of projects time, cost and qualitybecause of
over-emphasis the importance of critical paths.
(Word count: 600 words)
8/11/2019 MP - asm mu (2).docx
6/47
APPENDICES FOR SCENARIO 1
Appendix 1
8/11/2019 MP - asm mu (2).docx
7/47
: Continuous
Critical path
Noncritical path
EST: earliest start time.
D: duration (days)EFT: earliest finish time.
LST: latest start time.
LFT: latest finish time.
EST EFTD
LFTFloatLST
Activity Identifier
1
62 719
71062
M
49 6213
62049
L
79 889
88079
P
75 794
79075
O
71 754
75071
N
88 935
93088
Q
93 930
93093
FINISH1
4
9
5
1348
B
0 44
400
A
4 128
1315
D
4 84
1359
C
4 106
1337
E
4 139
1304
F
34 406
41135
J
34 417
41034
I
26 348
34026
H
13 2613
26013
G
41 498
49041
K
0
00
000
START
8/11/2019 MP - asm mu (2).docx
8/47
8
Appendix 2
According to Field and Keller(2005), network diagram has two types of activities: activities
in series and activities in parallel.
Total float and project float for each activity are calculated as below:
Activity Total Float
A 0
B 4
C 5
D 1
E 3
F 0
G 0
H 0
I 0
J 1
K 0
L 0
M 0
N 0
O 0
P 0
Q 0
Project f loat 14
8/11/2019 MP - asm mu (2).docx
9/47
9
Appendix 3
The terminology critical path can be defined in many different ways, understand
comprehensively this term is necessary in developing a complete and integrated perspective.
A path is any route comprised of one or more arrow (activities) connected in
sequence. The longest path from the origin node to the terminal node is called the critical
path; this gives the expected project duration.(Nicholas and Heinemann, 2004)
Longest sequence of activities in a projectplan which must be completed on time for the
project to complete on due date. An activity on the critical path cannot be started until its
predecessor activity is complete; if it is delayed for a day, the entire project will be
delayed for a day unless the activity following the delayed activity is completed a day
earlier. (BusinessDictionary)
The critical path is defined as the series of activities that have zero float. The critical
path always runs through the project from the first activity to the last activity. Activities
with zero float are on critical path. (Burke, 2003)
Appendix 4
Here we will look into calendar to see the timing of the process and how we can approach the
earliest finish date of the project on Wednesday, 23rd
May 2012.
http://www.businessdictionary.com/definition/plan.htmlhttp://www.businessdictionary.com/definition/day.htmlhttp://www.businessdictionary.com/definition/day.htmlhttp://www.businessdictionary.com/definition/plan.html8/11/2019 MP - asm mu (2).docx
10/47
10
Monday Tuesday Wednesday Thursday Friday Week
January 2012
16 17 18 19 20 1
23 24 25 26 27 2
30 31
February 2012
1 2 3 3
6 7 8 9 10 4
13 14 15 16 17 5
20 21 22 23 24 6
27 28 29
March 2012
1 2 7
5 6 7 8 9 8
12 13 14 15 16 9
19 20 21 22 23 10
26 27 28 29 30 11
April 2012
2 3 4 5 6 12
9 10 11 12 13 13
16 17 18 19 20 14
23 24 25 26 27 15
30
May 2012
1 2 3 4 16
7 8 9 10 11 17
14 15 16 17 18 18
21 22 23
8/11/2019 MP - asm mu (2).docx
11/47
11
Earliest Finish Time = 93 days = 18 x 5 day weeks + 3 days = Wednesday, 23rd
May 2012
Or the projects finish date can be determined through the length of activities on critical path
as below:
Activity Duration Earliest finish date
Start 0 Monday, 16t
January 2012
A 4 Thursday, 19t
January 2012
F 9 Wednesday, 1stFebruary 2012
G 13 Monday, 20t
February 2012
H 8 Thursday, 1s
March 2012
I 7 Monday, 12t
March 2012
K 8 Thursday, 22n
March 2012
L 13 Tuesday, 10 April 2012
M 9 Monday, 23r
April 2012
N 4 Friday, 27 April 2012
O 4 Thursday, 3r
May 2012
P 9 Wednesday, 16t
May 2012
Q 5 Wednesday, 23r
May 2012
8/11/2019 MP - asm mu (2).docx
12/47
12
Or Gantt Chart is also employed to calculate the earliest finish time of the project:
Legend: activities on critical path activities on non-critical path
8/11/2019 MP - asm mu (2).docx
13/47
13
Appendix 5a. If activity B is delayed 2 days
2
62 719
71062
M
49 6213
62049
L
79 889
88079
P
75 794
79075
O
71 754
75071
N
88 935
93088
Q
93 0
093
FINISH
6 115
1348
B
0 44
400
A
4 128
1315
D
4 84
1359
C
4 106
1337
E
4 139
1304
F
34 406
41135
J
34 417
41034
I
26 348
34026
H
13 2613
26013
G
41 498
49041
K
0
00
000
START
2 da s dela edA B
: Contingency effect
8/11/2019 MP - asm mu (2).docx
14/47
14
Appendix 5b. If activity P is delayed 2 days
62 719
71062
M
49 6213
62049
L
81 909
90081
P
75 794
79075
O
71 754
75071
N
90 955
95090
Q
95 0
095
FINIS
4 95
1348
B
0 44
400
A
4 128
1315
D
4 84
1359
C
4 106
1337
E
4 139
1304
F
34 406
41135
J
34 417
41034
I
26 348
34026
H
13 2613
26013
G
41 498
49041
K
0
00
000
START
2 da s dela edO P
8/11/2019 MP - asm mu (2).docx
15/47
15
Appendix 5c. If activity O is delayed 1 day
62 719
71062
M
49 6213
62049
L
80 899
89080
P
76 804
80076
O
71 754
75071
N
89 945
94089
Q
94 0
094
FIN
4 95
1348
B
0 44
400
A
4 128
1315
D
4 84
1359
C
4 106
1337
E
4 139
1304
F
34 406
41135
J
34 417
41034
I
26 348
34026
H
13 2613
26013
G
41 498
49041
K
0
00
000
START
1 da dela edN O
8/11/2019 MP - asm mu (2).docx
16/47
16
SCENARIO 2: Jimaga Ltd.
EXECUTIVE SUMMARY
Jimaga Ltd. is a SME company specializing in the design and supply of promotional brochures. As part
of a strategy of expansion, Jimaga Ltd. has been implementing a project for setting a warehouse.
Initially, before bring the new warehouse in operating, a precise project must have to come out to
successfully manage this new initiative at the feasibility stage. From a perspective of managing project,
this report is generated to identify crucial tasks for achieving an efficient warehouse.
The report presents in details plan, skills and competencies for the project manager including:
All the tasks related to each stage of the project life-cycle.
Concerns, stages, processes, leadership, administration and control problems associated with
managing the lifecycle of this major project.
It really helps project manager to successfully manage this project, ensuring on time and within budget.
8/11/2019 MP - asm mu (2).docx
17/47
17
MAJOR FINDINGS
2.1 Warehouse project life-cycle:
To manage the project efficiently, manager should follow strictly steps in project life-cycle (PLC).
According to Weiss and Wysocki (1994), the basic project life-cycle has five stages: define, plan,
organize, execute, and close. Because of large project, this 5-stage PLC is appropriate, precise and easy
to manage activities (see Appendix 1.)
2.1.1 Stage 1: Define
a. Functional specification
Follow Tompkins and White(1984), a warehouse directly serves for traditional purposes(see Appendix
2.)Apart from that, additionally, functions of this warehouse are also implied in the corporate strategy
which focuses on targeting and r esponding to demands of l arge global organizations in marketing
campaigns.
b.
Scenario development
Scenario development comprises a range of processes which is useful for setting project objectives as
well as assessing possible risks. This also allow project manager to cover alternative circumstances that
project can operate flexibly. According to Paul Shoemaker (1993), process to develop scenario for
project is identifyingscope of time, layout ratio, and decision var iabl es; major stakeholders;current
trends; and key uncertainties(see Appendix 3.)
c. Cost-benefit analysis
It simply identifies, specifies and evaluates an assumption costs and benefits (Field and Keller, 2005.)
Financial management tools can vary according to complexity: Payback Period, Net Present Value,
8/11/2019 MP - asm mu (2).docx
18/47
18
Internal Rate of Return, etc. Because payback period does not calculate time value of money and IRR
method is complex, hence NPV is suggested for the project. According to observation of same projects
for setting up warehouses, cost is estimated 40,000. (see Appendix 4.)
d. Setting objectives
Beside the objectives set up by manager of delivering the project on time and withi n budget, a
successful project must commit beyond those factors, quality in the long run(Field and Keller, 2005.)
Those objectives must strictly follow 5 indicators of SMART model (see Appendix 5.)This guarantees
satisfactions to all stakeholders and building ima[ge for the company.
e. Appointing project team:
To forming a good team, the project manager should concern about nature of works. According toField
and Keller (2005), there are four common models: function team, single team, matrix team, and
contract team. However, it can be perfect if the project have a mixed team. Because existing
warehouses staffs are experienced and acquaint with routine tasks, an assistan t manager, an
administration staff and two others warehouse staffs can be employed as supervisors and designers.
Apart from that, in a functional hierarchy in aspects of cost and labor, staffs at Financial Department
and HRM should involve into the project. For other small activities, to save budget, company can
outsource staffs. This step must be implemented precisely through interviewing skills, job description,
psychometric testing, and assessment testing (Field and Keller, 2005.)
2.1.2 Stage 2: Pl an
a. Warehouse design
8/11/2019 MP - asm mu (2).docx
19/47
19
First step in this phase provides work breakdown structur e(WBS) for constructing the warehouse, to
ensure that no activity is missing. As stated by Rook (1991), WBS is a product-oriented task
hierarchy of all the work to be performed to accomplish the project contractual objectivesthat are
required to reach the final outcomes. The suggested WBS contains four major steps: developing a
warehouse prototype, operating warehouse in emulation, evaluating and reviewing the warehouse, and
finalizing the project (Gross & Associates, 2003) (see Appendix 6.)
b. Sequencing tasks
Based on work packages of WBS, the project manager with the whole team need together list all
activities in chronological orders, assume each tasks timing. Network diagram and Gantt-chart are
useful techniques in project scheduling. (see Appendix 7.) According to schedule, project manager sets
4 main milestones to trace back and review what are accomplished. This project is optimally finished in
72 days from Monday, 2nd
January 2012 to Tuesday, 10th
April 2012.
c. Time management:
Project time management is method of controlling and monitoring the time spent for each activity by
staffs (Jason Westland, 2007.) By recording on a timesheet memorandum, the project manager can
clarify and update all timing of activities, then quickly response to time management issues and make
positive changes.
d. Cost management:
Project cost management is all referred to control financial resources in objectives of efficiency and
economy. Hence, planning cost carefully is very important because you cannot control the cost of an
8/11/2019 MP - asm mu (2).docx
20/47
20
item when the money has already been spent or irrevocably committed (Field and Keller, 2005.) Total
project budget is the aggregation of costs, expenditures and overheads allocated to the project. There
are three ways in assuming approximate budget for each activity: ballpark estimate, budget estimate
(top-down) and definitive estimate (bottom-up) (Joseph Phillips, 2010). Because of specialization and
objectives of this project, manager is recommended taking both the defi ni tive estimation (f ir st) and the
budget estimation (second). (see Appendix 8.)
e. Risk Planning
Risk assessment and management can be defined as analysis of specific risks (Field and Keller, 2005)
and identification of countermeasures necessary to meet the requirements identified in risk analysis
(PRINCE, 1993). Risks can cause a range of effects in terms of importance and urgency. It lengthens
times, increases costs, and reduces the outcome of delivery. Hence, there are models to identify risks
(see Appendix 9) and possible responses (see appendix 10) for the manager plan and give quick
decision when encountering. A tabular lists potential risks and suggested responses for project manager
is provided inAppendix 11.
8/11/2019 MP - asm mu (2).docx
21/47
21
2.1.3 Stage 3: Organize
a. Organize team
Project human resources usually acquires experienced, skillful, and especially responsible in the field
of project. With a large project for opening new warehouse, company can allocate 1 project manager, 1
assistant manager, 1 human resource manager, 1 financial manager, 1 warehouse administration, 2
warehouse staffs from the company itself and other contracted labors. It is important that information
about plan is communicated thoroughly among project team to ensure project on schedule. Moreover,
apply good conditions, well-informed combined with motivation (monetary and non-monetary) will
create ownership, responsibility of staffs, hence increasing the performance and outcome of the project
(Field and Keller, 2005.)
b. Assign works
After organizing team, the project manager with 4 sub-managers should stand together to discuss,
appoint, and take responsible of specific tasks for sub-teams. In the roundtable, project manager
establishes framework for project organization and give each sub-team an identity to work and right to
report. Apart from that, all required documents such as schedules, procedures, checklist, budget,
manuals, etc. will be provided (Field and Keller, 2005.)
Project organization can be divided into 3 levels of management and 4 divisions of work under the
project manager. (see Appendix 12.)
2.1.4 Stage 4: Execute
a. Issue change orders
8/11/2019 MP - asm mu (2).docx
22/47
22
In implementing phase, project team may encounter with unpredicted problems, differences in terms of
timing, resources or even companys requirements. Hence, project involves planning changes to closely
approach the objectives. Before doing anything further, it requires manager gathering all the planned
and actual results to compare. The variances are then taken into consideration whether they are positive
or negative. The project manager after all can develop project control loop to generate appropriate
responses (Field and Keller, 2005.)
b. Review project status
Project status is the step that simply measuring and aggregating all information taken from different
divisions in the project. As the previous stage mentioned, to track current position and improving
accuracy, the project manager should determine based on milestones. Furthermore, an automated
reporting softwarefor the project is the best supporter for manager to have a quick overview.
c. Monitoring staff, schedule and costs
Monitori ng and controll ing activities:different level of manager may have different reporting line
and schedule. Periodic reports can be submitted daily from warehouse staff to warehouse
administrator and from warehouse administrator to assistant manager can review weekly or
monthly. Another method to keep a good communication and motivation among project team is
organize progress review meetings. Though this is costly but it can help the manager improve
efficiency and quality of project works. (Field and Keller, 2005)
Monitori ng and controll ing costsee many constraints include allowable project budget, extra costs,
under costs. The manager can base on normally accounting systems but it is inappropriately and
imprecisely clarifying cost already spent according achievement and how much money for work
8/11/2019 MP - asm mu (2).docx
23/47
23
left.To solve this problem, referring to Field and Keller (2005), there is a method called earned
value systemor budgeted cost of work performed to monitor project cost.
d. Controlling quality
Quality management for warehouse is crucial when there may have potential risks (planning phase)
occur during the operation. This regards to loss of goods, machinery, legally binding with staffs
(injuries, deaths), efficiency in operation, and the companys reputation. The project manager therefore
must assure quality based on WBS checklists in which warehouse design is concerned. Using quality
control techniques, the project manager can perform this frequently until the end of the project to
ensure outcome delivered meets stakeholders requirements.
2.1.5 Stage 5: Close
In this stage, before the warehouse delivered to the company, it needs to re-check and must be accepted
by the companys manager. All the documents is completed and signed off; relieving labors and
resources; informing and disclosing warehouse to stakeholders (Weiss and Wysocki, 1994.)
According to Spirer(1983), project closure should be concern as a small plan which also has problems
itself in aspects of emotion for project staffs, clients and intellection for internal, external organizations
(see Appendix 13.) This will help to maintain the outcome warehouse and develop inspiration for every
stakeholders in future business.
8/11/2019 MP - asm mu (2).docx
24/47
24
2.2 Project manager skills and competencies
A project manager involves in project from very first stage to the completion of project. Before doing
any actions, this selected person initially must have characteristics of:
Pioneer who acquires outstanding energy levels, enthusiastic and challenge problems
Stakeholders who interested in and concernsabout the project and absolutely compulses with
the outcomes
Politician who create vision, transparent objectives, communicating, persuading, influencing,
integrating and leading people, especially truthful.
All of those will create extraordinary competencies for a project manager, supporting he/she in
implementing project successfully (example see Appendix 14.)
Beside essential personality, the project manager must comprehensively understand main duties along
with every stagesof the project life-cycle in his specialization. According toField and Keller(2005),
he/she with the supporting of an assistant firstly starts with the identification of objectives, planning the
flow of activities step-by-step and estimating how much time, resources, what skills needed to complete
the project.
The manager then must assembling a team byemploying people with right knowledge, right skills,
right attitude to form sub-teams to complete different project areas. This stage require the project
managers skillof leadershipto unite, motivate and communicate everyone contribute to teamwork and
feel like they are a part of the project success. It also takes into account ability to delegate and appoint
tasks for specific staffs. It is not simply giving away works irresponsibly but the project manage must
show processeslike an usersguide includes time, resources and detailed methods to implement. For
8/11/2019 MP - asm mu (2).docx
25/47
25
example, when the sub-manager appoints warehouse staffs to measuring merchandise in advance
without guidance, they fail to do this and consequently the problem takes overtime and much cost to
handle. This leads to the destruction in merchandising and totally destroy project.
In execution stage, the project manager must ensure to monitoring and controlling any changes related
to project itself, clients and stakeholders to re-planning the project to a new baseline. It is required
skills of making judgments and adjustments and it is when computer-aided software engineering
(CASE) tools is placedcorrectly.
Apart from the main project duties (internally), the project manager usually also has responsible to
report and liaise with different level of management from general director, clients, sponsors to
stakeholders and this is when skills of using reporting-line is applied.
Follow through all the competencies and skills in the whole project life-cycle is definitely essential for
success of project manager. Whether the project fails or succeeds, it totally lies under the responsibility
of manager.
8/11/2019 MP - asm mu (2).docx
26/47
26
CONCLUSION
To support the project manager for Jimaga Ltd. project, this report is written as a good plan includes
detailed phases in the project life-cycle, concurrent with contemporary skills and competencies needed
for project manager in controlling project. Hence, the manager should see this as a serious user
manual to set up the new warehouse efficiency and meeting the objectives requirements of the
corporate.
(Word count: 2183 words)
8/11/2019 MP - asm mu (2).docx
27/47
27
APPENDICES FOR SCENARIO 2
Appendix 1
The Basic Warehouse Project Life-cycle (referring to Weiss and Wysocki, 1994)
Appendix 2
Traditional purposes of a warehouse:
receiving;
identification and sorting;
dispatching to storage;
placing in storage;
storage;
retrieval from storage;
order accumulation;
packing;
shipping; and
record keeping.
Define
Issues analysis
Feasibility study
Functionalspecification
Scenariodevelopment
Cost-benefitanalysis
Set objectives Team
appointing
Plan
Warehousedesign
Identify criticalactivities, time,
Time, costmanagement
Risk analysis Quality
assuranceplanning
Organize
Organize team
Assign work
Execute
Issue changeorders
Review projectstatus
Report onproject
Reviewschedule andbudget
Qualifying
Close
Obtain clientacceptance
Completedocumentation
Sign off
Conduct postimplementation
audit Maintenance
Valueassessment
Sequence tasks
Recruit staff
Establish control
tools
Install deliverables
8/11/2019 MP - asm mu (2).docx
28/47
28
When constructing a new warehouse, the manager should also take into consideration of storing goods
in adequate spacewith the proper equipmentby well trainedpersonnelin a properly planned layout
results in maximum protectionof items. (Tompkins et al., 1996)
Appendix 3
Scenario development stage:
Identify the scope of time, layout ratio, and decision variables.
Assuming that when Jimaga Ltd. operating this strategy to integrate with global environment, the
company accept the standard time for constructing and finalizing a new warehouse. Hence,
referring to the statistic of World Bank for time required to build a warehouse , the average time
required is 207 days. Because the company has already acquired a building, there no need time for
construction, but they must redesign structure more or less. Assuming that construction takes a two-
third of total time, hence the optimal time for this project (redesign & setting up) is 72 days.
Country Name Country Code Days (2010)
Arab World ARB 152
East Asia & Pacific (all income levels) EAS 161
East Asia & Pacific (developing only) EAP 181
Euro area EMU 221Europe & Central Asia (all income levels) ECS 216
Europe & Central Asia (developing only) ECA 233
European Union EUU 199
Heavily indebted poor countries (HIPC) HPC 246
High income HIC 169
High income: non OECD NOC 176
High income: OECD OEC 165
Latin America & Caribbean (all income levels) LCN 220
Latin America & Caribbean (developing only) LAC 220
Least developed countries: UN classification LDC 250
Low & middle income LMY 221Low income LIC 290
Lower middle income LMC 199
Middle East & North Africa (all income levels) MEA 156
Middle East & North Africa (developing only) MNA 181
Middle income MIC 200
North America NAC 58
8/11/2019 MP - asm mu (2).docx
29/47
29
OECD members OED 164
South Asia SAS 241
Sub-Saharan Africa (all income levels) SSF 240
Sub-Saharan Africa (developing only) SSA 240
Upper middle income UMC 201
World WLD 207
There is no optimal ratio for office and warehouse, but depends on human and land resource, the
administrative office may acquire a small area for work room, customer services room, file room,
lunch/rest room and other special rooms.
After feasibility stage, decision for withdrawal is no longer valid. But within the objectives of time
and budget, Jimagas manager can still decide how much resources the company willing to invest.
Identify major stakeholders. Boddy and Buchanan (1992) developed a process of stakeholder
mapping. It generally is a category of people directly/indirectly, strongly/weakly influent to the
project. They are interest people, sponsor, champion, client, customer, or the owner. They have
aims, expectations and influence to the project
Curr ent trendin warehouse management: this small step is essentially taken to support for planning
stage, ensuring the best efficient and economic way in building warehouse. According to Lee Yan
Ni, Roland Tok, See Yi Lin, and Seet Hui Ling(2009), current trends for warehouse setting up are:
o Installation of RFID/WMS/EDI
o Advanced material handling systems
o Increase height allowance as land
o Adopting cross-dock activities
Identify key uncertaintiescome from decision-making progress, modeling, analyzing activities for
project.
8/11/2019 MP - asm mu (2).docx
30/47
30
Appendix 4
Example for IRR,NPV, and ROI calculation
Initial Investment (40,000)
Projected cash flow
Year 1 5,000Year 2 10,000
Year 3 15,000
Year 4 25,000
Year 5 20,000
Total 75,000
IRR 20%
NPV (at 5%) 63,028
Payback Period (Years) 3.40
ROI (NPVInvestment) 23,028
Appendix 5
According toAmy Maranowicz, 2011
Appendix 6
8/11/2019 MP - asm mu (2).docx
31/47
31
Work Breakdown Structure for Opening new Warehouse (referred to Gross & Associates, 2003)
Level 4Level 3Level 2Level 1
Opening newwarehouse
Developing a
prototype
Measuring
merchandise
Classifyingmaterials
Spaceallowances
Building &Services
Determinefeatures
Equipment &Handling
Layout
Organization &people
Job
descriptions
Jobapportionate
Training
Security &
Safety
Emergency,lock systems
Protectionclothes
Operatingwarehouse in
emulation
Evaluating &reviewing the
warehouse
Finalizing thewarehouse
8/11/2019 MP - asm mu (2).docx
32/47
32
Measur ing merchandise takes initiative to classify kinds of goods based on their features to
adapt with condition in the warehouse. To the case of Jimaga, goods are not only promotional
brochures but they can be carton boxes, work-in-process, raw materials (inks, papers, glues, films, etc.),
or office facilities (computers, stationary, staff uniforms, etc.)
Consequently the space for each kind is calculated and how they would be stored. For specialization,
cubic feet unit is used to measure. Apart from useful space, additional areas should be left for
overstock, expansion or warehouse traffic.
The second step concerns about determining physical characteri stics of the new bui ldingand
space for off iceto manage service activities in the warehouse.
With a few staffs in the large warehouse area, the assistance of equipment and handling
machines is significant in lifting and picking products efficiently. Depending on kinds, volume and
speed, appropriate methods should be applied manually or automatically as trucks, conveyors, racks or
pallets.
Next step, a detail gr id layout for the warehouse included merchandise, building, services,
equipment and machines, security and safety is visualized.
The warehouse worth nothing without putting peoplein. As Jimagasplan, staffing structure is
the same as the existing structure in existing site. Hence, the manager should invest more on handling
in and out methods to improve efficiency and training people to accommodate with the new warehouse.
In any building, secur i ty and safety are very important issues, especially for warehouse to
prevent thief, robbery, injury, fire or toxicity. There are many solutions include alarm system, guard,
protection clothing for staffs.
Next, the warehouse prototype is operating in trial to test the smoothness and efficiency as well
as other potential risks and changes needed to evaluate and review in the following step.
8/11/2019 MP - asm mu (2).docx
33/47
33
Lastly, the warehouse is finalized, assessed and accepted by the companys manager. It then
will be put into operation.
Appendix 7
Activity
IdentifierActivity Description
Duration
(days)
Human
ResourcesPredecessor
A Identify goods store in warehouse 1 1 -
B Classify goods 1 1 A
C Identify goods space 1 2 B
D Goods conditioning 1 1 B
E Determining building characteristics 7 3 -
F Clarifying warehouse and office spaces 2 2 E
GList equipment and handling machines
for warehouse and office1
1-
HDetermine space, necessity, volume for
equipment and machines3
2G
I Purchasing equipment and machines 14 2 H
J Assessing security and safety 2 1 D, F, I
KPurchasing equipment for security and
safety7
2J
L Visualize detail grid layout 7 2 C, K
M Work/job description 1 1 -
N Work/job apportion 1 1 M
O Staff employment 15 2 N
P Training 7 2 O
QReconstructing building in necessary
15 5 L, P
8/11/2019 MP - asm mu (2).docx
34/47
34
areas
RPutting equipment and machines to
warehouse and office2
5Q
S Putting equipment for security and safety 1 2 Q
T Putting goods to inventory 2 5 R
U Putting people to warehouse and office 1 17 S, T
V Running prototype 5 17 U
W Review the delivery 2 5 V
X Adjusting and finalize the delivery 5 5 W
Y Companys manager check and accept 1 2 X
ZCompleting document, sign off,
delivering outcome5
4Y
8/11/2019 MP - asm mu (2).docx
35/47
35
49 6213
62049
L
79 889
88079
P
75 794
79075
O
4 128
1315
D
4 84
1359
C
4 139
1304
F
34 406
41135
J
34 417
41034
I
41 498
49041
K
62 719
71062
M
71 754
75071
N
4
9
5
1348
B
0 44
400
A
4 106
1337
E
26 348
34026
H
13 2613
26013
G
0
00
000
START
1
2
88 935
93088
Q
88 935
93088
R
88 935
93088
S
88 935
93088
T
88 935
93088
U
88 935
93088
V
88 935
93088
W 3
88 935
93088
X
88 935
93088
Y
93 930
93093
FINISH
88 935
93088
Z3
8/11/2019 MP - asm mu (2).docx
36/47
36
Appendix 8
Joseph Phillips(2010) gives out three models to estimating costs for a project as follow:
The Ballpark Estimatecomes from corporate objectives, normally draws a birds eyeviewof the
project outcomes, and has lots of wiggle room.
The Budget Estimate(or top-down estimate) is most often based on analogous estimating budget
experience from a similar project and applying them to the current project.
The Defin iti ve Estimate (or bottom-up estimate) though takes time but this method provide an
accurate calculation for project total budget. The definitive estimate bases on a work breakdown
structure (WBS).
Above all, in order to have better cost management for the whole project, suggested cost breakdown
structure is provided below:
8/11/2019 MP - asm mu (2).docx
37/47
37
20% 40% 20% 10% 5% 5%
Estimate cost proportion of opening the warehouse
Appendix 9
Source:Energy Institute
Layout areas
Redesign floor,ceiling, wall,door
Machines
Shelves, bins
Preservation
Computers
Softwares
Print, fax
8/11/2019 MP - asm mu (2).docx
38/47
38
Appendix 10
Source: The Business Owner, 2009
Appendix 11
Example for a warehouse risk identifications:
8/11/2019 MP - asm mu (2).docx
39/47
39
8/11/2019 MP - asm mu (2).docx
40/47
40
8/11/2019 MP - asm mu (2).docx
41/47
41
8/11/2019 MP - asm mu (2).docx
42/47
42
Source:Health and Safety Executive, 2007
Appendix 12
A proposed work assignment for warehouse project:
8/11/2019 MP - asm mu (2).docx
43/47
43
According toField and Keller(2005)
Appendix 13 (According to Spirer, 1983)
Projectmanager
Warehouseadministrator
Warehousestaffs
Contracted
labors
Humanresourcemanager
Contracted staff
Financialmanager
Contracted staff
Assistant
manager
Operating,supporting
reporting
Documenting,scheduling,
servicing meeting,
facilities
Developing prototype,controlling, analyzing
& reviewing
Managing wholeproject: people,
process, warehouse
controlling
supportingsupporting
Constructing
, operating
Recruiting, staffing,contracting, payroll
Financialinformation, cash
flow, budgeting
Project termination
problems
internalclientstaff
intellectualemotional
external
-fear no future work-loss of interest in tasks remaining-loss of project-delivered
motivation
-loss of team identity-selection of personnel to bereassigned
-reassignment methodology-diversion of effort
-change in attitude-loss of interest in project-change of personnel dealing with
project
-unavailability of key personnel
-identification of remainingdeliverables-certification needs
-identification of outstanding
commitments-control of changes to project-screening of uncompleted tasks
not needed-closure of work orders and work
packages-identification of physical facilities
assigned to project-identification of project personnel-accumulation and structuring of
project historical data
-dis osin of material of ro ect
-agreement with client oremaining deliverables-obtaining needed certif
-agreement with supplie
outstanding commitmen-communicating closure-closing down physical
facilities-determining externalre uirements for audit t
8/11/2019 MP - asm mu (2).docx
44/47
44
Appendix 14
For the project managers competencies, itshould be referred to the case of a senior vice president of a
Fortune 500 organization which he endeavored to construct a program for discipline, innovation,
structure, training, leadership and an important visual feedback system that his team was able to reduce
15% to 25% of project life-cycle and cut-down 10% cost. And secrets are revealed:
Encourage work through innovation
Logical process and clear structure
Follow discipline
Did not allow shortcut
Dont let deadline decide work
Create visual feedback system
o Everything clarity
o Focus
o People accountability
(According toDeborah Bigelow, 2000.)
8/11/2019 MP - asm mu (2).docx
45/47
45
REFERENCES
Books
Bigelow, D. (2000) What makes a good Project Manager, Expert Series, PM Solutions, April 2000,
Vol. 14, number 4
Boddy, D. and Buchanan, D. (1999) Take the Lead: Interpersonal skills for Project Managers, Prentice
Hall, New York
Burke, R. (2003)Project Management, Planning and Control Techniques. John Wiley and Sons
Field, M., Keller, L. (2005), 6th
ed., Project management. Open university, Thomson, London, pp. 35-
289
Nicholas, J.M and Heinemann E. B. (2004) Project management for business and engineering
(Principles and practice), 2nd
ed., Linacre House, Jordan Hill, Oxford, UK
Paul Shoemaker (1993)Multiple Scenario Development: its conceptual and behavioral foundation,
Strategic Management Journal, 1993:14, pp193-213)
Rook, P. (1991) Project planning and control in McDermid, J.A. (ed.) Software Engineers Reference
Book, Butterworth Heinemann, Oxford
Spirer, H. F. (1983) Phasing out the project in Cleland and King op. cit.
Tompkins, James A. and White, John A.Facilities Planning, John Wiley and Sons, New York, 1984.
Tompkins et al.Facilities Planning,2nd. ed., John Wiley and Sons, New York, 1996.
Westland, J. (2007) The project management life cycle, AEW Services, Vancouver, BC, p. 7
Weiss, J. W. and Wysocki, R. (1994) 5-Phase Project Management: A Practical Planning and
Implementation Guide, Addison-Wesley, Reading, Mass
http://www.amazon.com/Facilities-Planning-John-White/dp/0471002526/ref=ed_oe_h/002-9056060-6602426http://www.amazon.com/Facilities-Planning-John-White/dp/0471002526/ref=ed_oe_h/002-9056060-6602426http://www.amazon.com/Facilities-Planning-John-White/dp/0471002526/ref=ed_oe_h/002-9056060-6602426http://www.amazon.com/Facilities-Planning-John-White/dp/0471002526/ref=ed_oe_h/002-9056060-66024268/11/2019 MP - asm mu (2).docx
46/47
46
Internet
BusinessDictionary (N.D) [Critical Path][online] (cited 20th
December 2011)
Energy Institute [Risk assessment matrixBring it to Life] [online] (cited 16th
December 2011)
Gross and Associate (N.D) [Planning a Warehouse Move: Intelligent Planning Needed for Efficient,
Economical Move][online] (cited 15th
December 2011)
Heath and Safety Executive [Example Risk Assessment for a Warehouse] [online] (cited 21
st
December
2011)
Lee, Y. N., Roland, T., See, Y. L., Seet, H. L. (2009) [Trend and challenge of warehouse and
distribution center: Questions & Answers] [online] (cited 20th
December 2011)
Maranowicz, A. (2011) [The SMART model for setting goals] [online] (cited 16thDecember 2011)
Phillips, J. (2010)[Project Cost Management] [online] (cited 15th
December 2011)
The Business Owner (2009) [Eleven steps to smart risk management value enhancement] [online]
(cited 21stDecember 2011)
http://www.businessdictionary.com/definition/critical-path.htmlhttp://www.eimicrosites.org/heartsandminds/ram.phphttp://www.grossassociates.com/articles/move.htmhttp://www.hse.gov.uk/risk/casestudies/http://welovedcm.blogspot.com/2009/01/question-answer.htmlhttp://theinsidegoodblog.blogspot.com/2011/01/smart-model-for-setting-goals.htmlhttp://www.projectsmart.co.uk/project-cost-management.htmlhttp://www.thebusinessowner.com/business-guidance/risk-management/2008/11/eleven-steps-to-smart-risk-management-value-enhancementhttp://www.thebusinessowner.com/business-guidance/risk-management/2008/11/eleven-steps-to-smart-risk-management-value-enhancementhttp://www.thebusinessowner.com/business-guidance/risk-management/2008/11/eleven-steps-to-smart-risk-management-value-enhancementhttp://www.thebusinessowner.com/business-guidance/risk-management/2008/11/eleven-steps-to-smart-risk-management-value-enhancementhttp://www.projectsmart.co.uk/project-cost-management.htmlhttp://theinsidegoodblog.blogspot.com/2011/01/smart-model-for-setting-goals.htmlhttp://welovedcm.blogspot.com/2009/01/question-answer.htmlhttp://www.hse.gov.uk/risk/casestudies/http://www.grossassociates.com/articles/move.htmhttp://www.eimicrosites.org/heartsandminds/ram.phphttp://www.businessdictionary.com/definition/critical-path.html8/11/2019 MP - asm mu (2).docx
47/47
Wideman, M. (19th
December 2002) [Project cost system-to-Project leader][online] (cited 20th
December 2011)
World Bank (2011) [Time required to build a warehouse (days)] [online] (cited 19th
December 2011)
http://www.maxwideman.com/http://data.worldbank.org/indicator/IC.WRH.DURShttp://data.worldbank.org/indicator/IC.WRH.DURShttp://www.maxwideman.com/Top Related