MODERN General Meetings Plenary sessions
Version: 1.0
Jan van Gerwen
2CONFIDENTIALPlenary sessionsCatania, Nov. 9 & 10, 2010
Contents
Agenda Tuesday
Agenda Wednesday– Tuesday 09:00 – 10:00 Kick off– Request to WP meetings: prepare for tomorrow– First Year Review– Gantt chart
Agenda Wednesday– Wednesday 08:30 - 10:00 MODERN Status– Consortium– Amendments– Overview of deliverables and milestones status– Funding problems– First Year Review– Plan for remainder of the project– Wrap up
3CONFIDENTIALPlenary sessionsCatania, Nov. 9 & 10, 2010
Tuesday Nov. 9, 09:00 – 18.00 hours09:00 Kick off (JvG) – all (see next slide for dial-in details)
– Welcome– House keeping and other practical information– Request to WP meetings: prepare for General Meeting tomorrow
• Review Feedback• Exchange of results between WPs• Plan for remainder of the project
10:00 WP1 (GG) – all– Address (as preparation for the meeting tomorrow):
• Show link between all the separate tasks and the overall project goals• Show link between the various tasks contributing to the demonstrators
– WP1 agenda
10:30 Separate WP2 (AJ), WP3 (WH) and WP4 (DP) meetings (in parallel)– Address (as preparation for the meeting tomorrow):
• Show link between all the separate tasks and the overall project goals• Show link between the various tasks contributing to the demonstrators
– WP agenda
12:00 Lunch
13:30 Continued WP2, WP3 and WP4 meetings (in parallel)
15:30 Coffee break
16:00 Continued WP2, WP3 and WP4 meetings (in parallel)
18:00 Closure
4CONFIDENTIALPlenary sessionsCatania, Nov. 9 & 10, 2010
Wednesday Nov. 10, 08:30 - 17:0008:30 MODERN Status (JvG) - all
– Project management: consortium, progress, amendments and funding problems– Overview of deliverables and milestones status– First Year Review
• Consolidated review report• Feedback from reviewers• Discussion: link between all the separate tasks and the overall project goals and link
between the various tasks contributing to the demonstrators (Gantt chart)– Plan for remainder of the project
10:00 Exchange of results between WPs (each 30 min.)– 10:00 WP1 (GG)– 10:30 WP2 (AJ)– 11:00 WP3 (WH)– 11:30 WP4 (DP)
12:00 Lunch
13.30 WP5 meeting (LV) – all– WP5 agenda (reviewers: structuring, goal and objectives of demonstrators; show
capabilities and innovative aspects)
16:00 Wrap up (JvG), Other issues, Q&A – all
17:00 Closure
5CONFIDENTIALPlenary sessionsCatania, Nov. 9 & 10, 2010
Tuesday 09:00 – 10:00 Kick off
Welcome– Giuliana absent– Loris will dial in
House keeping and other practical information– Agata general support– WP2: Valeria ([email protected], +39-095-7403180) – WP3: Angelo ([email protected], +39-095-7402491)– WP4: Carmelo ([email protected], +39-095-7404376)– WP5 (plenary): Valeria and Angelo– lunch, coffee break etc.
6CONFIDENTIALPlenary sessionsCatania, Nov. 9 & 10, 2010
Request to WP meetings: prepare for tomorrow
1st Year Review:– Reviewers feedback (next slides)
Exchange of results between WPs
WP Plan for remainder of the project
7CONFIDENTIALPlenary sessionsCatania, Nov. 9 & 10, 2010
7
First Year Review
Overall recommendation
WP5
JvG: see Techn. Annex page 20
Gantt chart
8CONFIDENTIALPlenary sessionsCatania, Nov. 9 & 10, 2010
8
Relationship between workpackages
9CONFIDENTIALPlenary sessionsCatania, Nov. 9 & 10, 2010
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36WP1T1.1,T1.2D1.1T1.3D1.2 D1.1T1.4D1.4 D1.2,D1.3T1.5D1.3 D1.2
Year 1 Year 1 Year 1ID
Predecessor
Gantt chart
Provide link between the various tasks, deliverables and demonstrators by specifying the predecessor(s) for each deliverable. Please do this in the column predecessor in MODERN_Gantt_v1.1.xls
10
CONFIDENTIALPlenary sessionsCatania, Nov. 9 & 10, 2010
Wednesday Nov. 10, 08:30 - 17:0008:30 MODERN Status (JvG) - all
– Project management: consortium, progress, amendments and funding problems– Overview of deliverables and milestones status– First Year Review
• Consolidated review report• Feedback from reviewers• Discussion: link between all the separate tasks and the overall project goals and link
between the various tasks contributing to the demonstrators (Gantt chart)– Plan for remainder of the project
10:00 Exchange of results between WPs (each 30 min.)– 10:00 WP1 (GG)– 10:30 WP2 (AJ)– 11:00 WP3 (WH)– 11:30 WP4 (DP)
12:00 Lunch
13.30 WP5 meeting (LV) – all– WP5 agenda (reviewers: structuring, goal and objectives of demonstrators; show
capabilities and innovative aspects)
16:00 Wrap up (JvG), Other issues, Q&A – all
17:00 Closure
11
CONFIDENTIALPlenary sessionsCatania, Nov. 9 & 10, 2010
Wednesday 08:30 - 10:00 MODERN Status
Consortium
Amendments
Overview of deliverables and milestones status
Funding problems
First Year Review– Consolidated review report– Feedback from reviewers– Discussion: link between all the separate tasks and the overall project goals
and link between the various tasks contributing to the demonstrators (Gantt chart)
Plan for remainder of the project
12
CONFIDENTIALPlenary sessionsCatania, Nov. 9 & 10, 2010
Consortium
CSEM withdraw because of lack of national funding as of 29-06-2010
9 Countries27 Partners 9 Countries9 Countries27 Partners27 Partners27 Partners
13
CONFIDENTIALPlenary sessionsCatania, Nov. 9 & 10, 2010
Amendments
1. NXP Semiconductors has taken over the project leadership of the ENIAC MODERN project [Project number: 120003] from STMicroelectronics as of June 23rd,, 2009. The legal entity ST-Crolles (short name ST-F) that was delivering the previous project leader is replaced by the legal entity ST-Grenoble.
2. To remove some inconsistencies in the inter-dependencies between the deliverables D2.2.2, D2.2.4, D2.5.1 and D2.5.2 it is proposed to change these items from the WP2 deliverables list by re-phrasing the deliverables contents for D2.2.2, D2.2.4, D2.5.1 and D2.5.2. This change prevents that a three months delay will propagate through all involved deliverables without changing the total contents of these deliverables.
3. The MODERN Consortium accept that the University of Glasgow will be sub-contracting work to the spin-out venture Gold Standard Simulations Ltd to complete tasks in relation to the deliverables to be provided by the university to the consortium.
4. The Swiss partner Centre Suisse d’Electronique et Microtechnologie CSEM partner # 3 withdraws from the project due to lack of national funding as of 29-06-2010.
5. To account for the leaving of some NXP employees involved and a related change in direction of the NXP PDM group the contribution of NXP to Task 3.1, Task 5.3 and the related deliverables D5.3.2 and D5.3.3 will (slightly) change.
Change (no amendment): the Thales contribution is moved from D4.3.2 to D4.3.3
The latest TA that includes the updates above is MODERN_PartB Rev3.2.pdf and is available from section WP6 of the MODERN website
14
CONFIDENTIALPlenary sessionsCatania, Nov. 9 & 10, 2010
Overview of deliverables and milestones statusdue M13 – M18
Milestone number
Milestone name Work package(s) involved
Expected date (proj.
month)
Actual / Forecast
delivery date
Achieved Means of verification Comments
M2.1 PV aware compact models available for bulk planar CMOS technologies down to 45nm, TCAD/hardware based
2 M18 20-10-2010 Yes D2.1.1, D2.2.2, D2.3.1, D2.5.1
M6.2 Second project review by ENIAC all M14 29-06-2010 Yes Reviewer’s feedback
Del. no. Deliverable name WP no. Task lead
Nature Disseminationlevel
Delivery date
(proj. month)
Contributors (lead)
Actual / Forecast
delivery date
Delivered Comments
D1.3 Integration Specifications 1 ST-I R PP M18 ST-I, AMS, IFXA, NMX, NXP, THL
12-11-2010 Delayed
D2.1.1 First version of process simulator including treatment of PV for mainstream CMOS technologies, and Discrete Power Device,SiC,GaN/AlGaN technologies, interfaced to commercial TCAD tools
2 ST-I R CO M15 ST-I, AMS, TUW
15-06-2010 yes
D2.2.3 Device simulation analysis of dominant variability sources in state-of-the-art Non-Volatile-Memory technologies
2 UNGL R CO M18 UNET, UNGL, NMX, SNPS
14-10-2010 Yes
D2.3.2 Characterization of major sources of PV in SiC technologies/devices, and AlGaN/GaN HEMT devices.Report on 1/f noise dispersion behavior in 45nm bulk CMOS
2 NXP R CO M18 ST-I, NXP 12-11-2010 Delayed
D2.5.1 PV-aware circuit-level models for standard CMOS technologies (down to 45nm), and Non-Volatile-Memory technologies. State-of-the-art based statistical models, based on hardware and/or TCAD.
2 UNET R CO M18 UNGL, UNET, NXP, POLI, ST-I, STF2, NMX
20-10-2010 Yes
D5.1.2 Design of test structures for analog design parameter monitoring
5 AMS R CO M18 TUGI, AMS 28-09-2010 Yes
D6.1.6 Semi-annual project progress report 6 NXP R CO M18 NXP, all 02-11-2010 YesD6.2.3 First report on dissemination activities 6 UNET R CO M18 ST-I, all 12-11-2010 DelayedD6.2.4 First update of public part of the project web-site 6 UNET D PU M18 ST-I 11-10-2010 YesD6.3.1 Dissemination and use plan (first version) 6 NXP R CO M18 UNET, NXP,
all11-10-2010 Yes
15
CONFIDENTIALPlenary sessionsCatania, Nov. 9 & 10, 2010
Funding problems
Italy: status ??
Spain: seem solved
???
16
CONFIDENTIALPlenary sessionsCatania, Nov. 9 & 10, 2010
First Year ReviewDate: June 30th, 2010
Present: – From MODERN: Giuliana Gangemi, André Juge, Wilmar Heuvelman,
Fabio Campi (repr. Davide Pandini), Loris Vendrame, Jan van Gerwen– From ENIAC: Paul Merkus (external expert, Philips Research), Christian
de Prost (external expert, ATMEL), Anton Chichkov (ENIAC PO, reviewer), Eric Mottin (from the French National Authorities), Yves Gigase (PM, ENIAC, observer), Andreas Wild (ED, ENIAC, observer)
Very successful: thank you all
Consolidated review report (see next slides)
17
CONFIDENTIALPlenary sessionsCatania, Nov. 9 & 10, 2010
Review report
18
CONFIDENTIALPlenary sessionsCatania, Nov. 9 & 10, 2010
Recommendation
19
CONFIDENTIALPlenary sessionsCatania, Nov. 9 & 10, 2010
19
Discussion: Gantt chart
Overall recommendation
WP5
JvG: see Techn. Annex page 20
Gantt chart
20
CONFIDENTIALPlenary sessionsCatania, Nov. 9 & 10, 2010
Plan for remainder of the project
March 1st, 2011: Second review concerning the 2010 activities. So this second review period will overlap quite al lot with the first period and only one deliverable was planned in the second half of 2010.
Discussion
21
CONFIDENTIALPlenary sessionsCatania, Nov. 9 & 10, 2010
Wednesday Nov. 10, 08:30 - 17:0008:30 MODERN Status (JvG) - all
– Project management: consortium, progress, amendments and funding problems– Overview of deliverables and milestones status– First Year Review
• Consolidated review report• Feedback from reviewers• Discussion: link between all the separate tasks and the overall project goals and link
between the various tasks contributing to the demonstrators (Gantt chart)– Plan for remainder of the project
10:00 Exchange of results between WPs (each 30 min.)– 10:00 WP1 (GG)– 10:30 WP2 (AJ)– 11:00 WP3 (WH)– 11:30 WP4 (DP)
12:00 Lunch
13.30 WP5 meeting (LV) – all– WP5 agenda (reviewers: structuring, goal and objectives of demonstrators; show
capabilities and innovative aspects)
16:00 Wrap up (JvG), Other issues, Q&A – all
17:00 Closure
22
CONFIDENTIALPlenary sessionsCatania, Nov. 9 & 10, 2010
Wednesday Nov. 10, 08:30 - 17:0008:30 MODERN Status (JvG) - all
– Project management: consortium, progress, amendments and funding problems– Overview of deliverables and milestones status– First Year Review
• Consolidated review report• Feedback from reviewers• Discussion: link between all the separate tasks and the overall project goals and link
between the various tasks contributing to the demonstrators (Gantt chart)– Plan for remainder of the project
10:00 Exchange of results between WPs (each 30 min.)– 10:00 WP1 (GG)– 10:30 WP2 (AJ)– 11:00 WP3 (WH)– 11:30 WP4 (DP)
12:00 Lunch
13.30 WP5 meeting (LV) – all– WP5 agenda (reviewers: structuring, goal and objectives of demonstrators;
show capabilities and innovative aspects)
16:00 Wrap up (JvG), Other issues, Q&A – all
17:00 Closure
23
CONFIDENTIALPlenary sessionsCatania, Nov. 9 & 10, 2010
Wednesday Nov. 10, 08:30 - 17:0008:30 MODERN Status (JvG) - all
– Project management: consortium, progress, amendments and funding problems– Overview of deliverables and milestones status– First Year Review
• Consolidated review report• Feedback from reviewers• Discussion: link between all the separate tasks and the overall project goals and link
between the various tasks contributing to the demonstrators (Gantt chart)– Plan for remainder of the project
10:00 Exchange of results between WPs (each 30 min.)– 10:00 WP1 (GG)– 10:30 WP2 (AJ)– 11:00 WP3 (WH)– 11:30 WP4 (DP)
12:00 Lunch
13.30 WP5 meeting (LV) – all– WP5 agenda (reviewers: structuring, goal and objectives of demonstrators; show
capabilities and innovative aspects)
16:00 Wrap up (JvG), Other issues, Q&A – all
17:00 Closure
24
CONFIDENTIALPlenary sessionsCatania, Nov. 9 & 10, 2010
Wrap up
Other issues
Q&A
25
CONFIDENTIALPlenary sessionsCatania, Nov. 9 & 10, 2010
Closure
Thank you all
Thank you ST Catania
Thank you Valeria, Angelo, Carmelo and Agata
26
CONFIDENTIALPlenary sessionsCatania, Nov. 9 & 10, 2010
Top Related