April 18, 2023Board of Trustees Meeting
Vision:The Neurosciences Research Building is a continuation of the School of Medicine and Indiana University's focus on expanding and strengthening the biomedical and life sciences research capability of the university.
Aerial View
April 18, 2023Board of Trustees Meeting
Proposed Clinic
Clarian People Mover
Existing Garage
Proposed Clarian Garage
Methodist Hospital
IU Research
15th Street
16th Street
Mis
sour
i St
I-65
Building Section
April 18, 2023Board of Trustees Meeting
Building Concepts:• Layered N/S Plan and Section• Vertical Integration of Lab Support Functions• Modular Design (Lab, Support, Office)• Behavior Lab Module Stacked
April 18, 2023
South Elevation
Board of Trustees Meeting
Precast Concrete A
Research BuildingClinic
Precast Concrete B
Fritted Glass A & B
Metal Panel A
Clear Glass
Metal Panel B
Fritted Glass A & B
Precast Concrete B
Fritted Glass A & B
Metal Panel A
April 18, 2023
East Elevation
Board of Trustees Meeting
Precast Concrete B
Precast Concrete A
Clear Glass
Fritted Glass C
Research Building
Clinic
Precast Concrete B
Metal Panel B
Clear Glass
April 18, 2023
North Elevation
Board of Trustees Meeting
Precast Concrete A
Metal Panel A
Sustainability
April 18, 2023Board of Trustees Meeting
LEED Mission: A leading edge system for certifying the greenest performing buildings in the world.
1. Sustainable Sites• Urban site previously developed
2. Efficient use of Water• 35% water use reduction
3. Energy and Atmosphere•Heat Recovery wheel
Sustainability
April 18, 2023Board of Trustees Meeting
4. Materials and Resources• Divert 50% of construction waste from disposal
5. Indoor Environmental Quality• Provide occupant controls for airflow, temperature and lighting
6. Innovative Design• Paperless Construction Administration Process
Project Goal: LEED Silver
Schedule
April 18, 2023Board of Trustees Meeting
• End of Design Development: December 10th, 2010
• IU Review Comments due: December 23rd, 2010
• End of Construction Documents: March 31st, 2011
• IU Review Comments due : April 8th, 2011
• Bidding: April 8th 2011 – May 5th 2011
• Construction: June 6th 2011-July 11th 2013
• Commissioning: July 11th 2013-Sept. 11th 2013
• Close-out: Sept.11th 2013-Nov. 11th 2013
• Occupied: January 2014