Managing A Migration Project

Neil Phinney

EMS Users Group

June 7, 1999

Page 2: Managing  A Migration Project

First Rule of Project ManagementFirst Rule of Project Management

Choose from the following

• Low Cost• Fast Delivery• Quality SystemBut you can’t have all three !

Page 3: Managing  A Migration Project

Generation & Transmission Generation & Transmission CooperativeCooperative

Serving >650,000 Customers Facilities in 45 Counties Winter Peaking 1999 Peak Demand > 3,100 MW 350+ miles of Transmission 91.5% of Load Outside CA

10 members

Page 4: Managing  A Migration Project

Delivered in 1986 2 - 300 MB Disks Aydin Display Generators 108 RTUs Mosaic Mapboard

Legacy EMS

Hardware Gould \ SEL \ Encore CPUs

Page 5: Managing  A Migration Project

Load Estimation Demand Side Management Forecasting Interchange Scheduling Member Billing

Legacy EMS

Applications

Data Exchange

Page 6: Managing  A Migration Project

EMS Support Staff

Small Staff - 6 people 2- Analysts

1 - Engineer 3- Technicians No Formal Project

Team No Additional Staff

Page 7: Managing  A Migration Project

Replacement Approaches

Phased

Migration

Fork Lift

Page 8: Managing  A Migration Project

Bid Process

Bids Mailed - 4/15/98 6 vendors 5 Bids Received 3 Evaluated

Bid Awarded - 9/10/98 First Project Meeting - 10/2/98

RFI - FALL 1996

Page 9: Managing  A Migration Project

SECI’s Decision

Reasons For Selection

No project team Gain experience Cash flow spread Logical contract terminated Overall project cost less

Applications delivered as required

Page 10: Managing  A Migration Project

Project Implementation Plan

Stage 1 Real Time Data Interface

L A N I U D L Duplicate data base

Gateway

Page 11: Managing  A Migration Project

Project Implementation Plan Stage 2 Transaction Evaluation

Standalone UC/TE

Page 12: Managing  A Migration Project

Project Implementation Plan

Stage 3 Scheduling & Accounting

Historian

Control Criteria

I T S

Page 13: Managing  A Migration Project

Project Implementation Plan

Stage 4 System Stage

Integrated

Interfaced

Page 14: Managing  A Migration Project

Project Implementation Plan Stage 5 AGC and SCADA

DSM

Load Estimation

Load Forecasting

Listening &

Parallel

Page 15: Managing  A Migration Project

Project Implementation Plan

Stage 6 Mapboard

3 X 2 Video

Board

Page 16: Managing  A Migration Project

Project Implementation Plan

Stage 7 System Acceptance

RTU Cut Over

System Testing

Page 17: Managing  A Migration Project

Status of Project

Stage 2 - Transaction

Evaluation

Stage 3 - Scheduling &

Accounting

Stage 1 - Real Time Interface

Page 18: Managing  A Migration Project

Lessons Learned

Managing

Expectations

Project Coordination

Maintaining Schedule

Scope of Work

Page 19: Managing  A Migration Project

Lessons Learned

Legacy Work

Project

Control

Training

Office Space

Testing

Page 20: Managing  A Migration Project

Overall Conclusion

Migration Complex

Advantages Outweigh

Reservations

Overall Pleased

Page 21: Managing  A Migration Project

The Money Theorem

Power = Work / Time

Postulate 1: Knowledge is Power Postulate 2: Time is Money

Knowledge = Work /Money

Then Less You Know The More You Earn

Money = Work / Knowledge