1) What happened?
2) What did we do?
3) What are our experiences?
Facts in short
Reisa National Park (803km²)
Raisduottarhaldi Protected Landscape (80km²)
Protected in 1986
Aims for protection :
-protect large nature areas and landscapes with mountains and valleys
-protect geological values, flora and fauna
-opportunity for outdoor life in such areas
Three groups of people –
norwegian-sami-kven
2 reindeer husbundry districts summertime
5 reindeer husbundry districts move through
area spring and autumn
Status management plan
Working group made a draft management plan
Two areas – one management plan
Prepare to hand it over to the local board this autumn
Local board will do the public hearing
Local board will finish the plan
Environmental Directorate will approve the plan
1) What happened ?
Protected in 1986
No approved management plan Plans on public hearing in 1993 and 1996 Started again in 2003……
Agreement between National authorities and Sami Parliament in 2005 – consultations
Agreement between Environmental Department and Sami Parliament 2007 – guidelines new protected areas and
management plans
2) What did we do? Restarted prosess 2007-2008 Started to clarify the process (who involved, how to work) Made a strategy to produce the plan Meetings to discuss the strategy Made it clear it was a new process Made it clear we wanted a different kind of process
Agreement between County Governor and Sami Parliament based on the plan strategy
Established - working group - mandate for the working group
Arbeidsmøte 1Oppstart:- AUs arbeid- Rammer for arbeidet
Arbeidsmøte 2Innledning:- bakgrunn for verneplan og planarbeid
Arbeidsmøte 3Nåsituasjon:- naturfaglig- kulturfaglig- bruk
Arbeidsmøte 4Strategi:- beskrivelse av framtid
Arbeidsmøte 5Forvaltning:- bruk og vern
Arbeidsmøte 6Oppgaver og ansvar:- saksbehandling- oppsyn osv
Arbeidsmøte 7 - befaring?- flere møter på tema? osv
Konsultasjon prosess /Agreement Sami parlamentMøter med involverte inkl samiske rettighetshavereKonsultasjon Sametinget
Organization
Oppdragsgiver:MD/Direktoratet for naturforvaltning via Fylkesmannen i Troms - DN godkjenner forvaltningsplanen, FM forv.myndighet og ansvarlig for å utarbeide plan
Working group ”Reisagruppa”:
Ann-Heidi Johansen (County Gov. Troms) Leader of group, write plan Members of group6+1 secretary to write protocol
Prosessansvarlig:Knut Nergård (fagsjef FM)- kontrollerer framdrift, oppfølging budsjett, sørge for at prosessen går som planlagt
Other participants:Experts and specialists , different interests in the area, locals, reindeer husbundry districts not in working group-take part in meetings, discussions, «open office», e-mail, and so on
Rådet:Medlemmer i ”Rådet for Reisa np”- bistå med råd i forvaltningsspørsmål til forvaltningsmyndigheten
Reisagroup - members from local council (1), local interests (1), landowner (1), reindeer husbundury districts (2+1), secretary (1)
3) What are our experiences?
People involved:Clarify process before it starts (who is involved, how to work, the content of the plan)
Clarify how to move on if you meet problems in the process, how to solve conflicts
For interests and individuals outside the group, important to know we also want their opinion, and how they can take part and when in the process.
Predictable process - creates confidence, creates peace to work
Openness in process - opens for more participation, opens for more information - wish public involved themselves more!
Discussions before public hearing, hopefully not big conflicts during public hearing, know what are the disagreements no surprises…..
3) What are our experiences?
Working group, Reisagruppa:Small group, all practical arrangements easier, meetings a.s.o
Talk about how you want the discussions to be - Everyone can say what they mean, not afraid of the others reaction
- Talk about the case, not person, respect others opinion
Clear mandate for the working group
Dynamic process - Participants can change their opinions - «Nothing is set before it is set», back and forth
Mechanisms that ensures progress in spite of disagreements - Opportunity to suggest alternatives - Opportunity to consult with Sami Parliament if we could not solve conflict - No voting at meetings - voting if disagreements and entry to the protocol - Everyone sign protocol from last meeting – moving forward
Everyone wants to achieve something, have the best intentions
Find the right pace, some want to speed things up, some need more time
They are proud of the job! Think they have done an important job
3) What are our experiences?Management system / authorities:A process will take time! Need patient impatience – «muddling through», step by step
A process means lof of work!
More than 1 person to lead the process
Process means knowledge, theoretical and practical - be clear what you know something about, what you don’t know
Know what the real conflicts are and why
Clarify process with superior authorities - resources (time and money) - understand the process
Not a project, but a process
Be brave!
Outdoor meetings
“Making a management plan is like climbing a mountain.
Earlier, it was like this:You said: “let us start!”, and you ran off, heading to the top. When you were there, you said: “we have reached the top!”. But we were still struggling in the steep slope.
We have to walk together and wait for each other. We have not reached the top before everyone is safely there.”