Ver.22.05.2015
LNG Projects
Çimtaş Precision Machining
Cimtas Group Company Locations
Cimtas Fabrication Shop Locations, Gemlik/Turkey
Cimtas Gemlik Works
Cimtas Pipe
Cimtas Precision Machining
Cimtas Pipe Fabrication and Trading Ltd. Co.
• Power, Process and OEM Piping Systems• Integrated Design & Engineering, Material Procurement
Fabrication, Surface Treatment, Packing, Framing• Induction Bending (2 machines, 40 and 108 mm thk. P92)• ASME NPT, NS, NA, KTA1401 Nuclear Certificates• 22 Bays, 49 Overhead Cranes• Fenced Area: 93,000 sqm • Covered Shop Area: 38,000 sqm• 3,500 tons/month Fabrication Capacity
LNG Projects
Project Name Location Tonnage *Plant Capacity Year
ELNG Egypt 5,350 7.2 2003-2004
EGLNG Equatorial Guinea 2,500 3.4 2005-2006
Angola LNG Angola 7,250 5.2 2009-2010
Queensland LNG Australia 10,100 8.5 2012-2013
Gladstone LNG Australia 12,500 7 2012-2013
AP LNG Australia 6,900 4.5 2012-2013
Sabine Pass LNG Train 1-2 U.S.A. 14,250 9 2013-2014
Sabine Pass LNG Train 3-4 U.S.A. 13,700 9 2014-2015
Angola LNG (Additional) Angola 1,300 5.2 2014-2015
Corpus Christi LNG Train 1-2 U.S.A. 14,250 4.5 2015TOTAL 88,100 63.5
*Total of 16 trains with 63.5 million tons per annum capacity
LNG Projects Size and Metallurgy Breakdown
Metalurgy Dia Inch Range Tonnage Material
CS2" and below 1,850 CS1
3" - 24" 29,200 CS2
>24" 37,900 CS3
Sub Total 68,950
SS2" and below 980 SS1
3" - 24" 7,700 SS2
>24" 10,470 SS3
Sub Total 19,150
Grand Total 88,100
PMP® certified project managers and coordinators support the objectives to implement solutions with the lowest overall risk and highest customer satisfaction.
Project Management
• Integrated change control to centrally manage and document change orders
• Communication Plan to clearly define how to communicate the right information to the
right stakeholder at the right time
• Integrating, communicating and managing technical changes
• Managing suppliers and sub-contractors through cost, schedule and quality baselines
Logistics
• Procurement, material handling, storage, packing
• Crating, Bundling, Containerizing, Framing
• 21 Portal & Semi-Portal cranes up to 30 tons capacity
• 49 Overhead cranes up to 25 tons capacity
• 100 logistics staff
• 2 hrs/ 200 kms from Istanbul
• 2 kms from 4 International Deep Sea Ports
• 50,000 sqm stock area
Procurement
• Pipes• Pipe Supports• Fittings• Flanges• Valves• Instruments• Process Equipment Packages
• Cost-efficient supply chain management
• Global sourcing
• Knowledge of local and int.’l markets and customs
• Wide range of approved well known suppliers
• Multi location central managed sourcing
• Experienced sourcing and procurement engineers
• Supplier qualification and evaluation
Butterfly steam control valveVendor Inspection
Scope
Packing Types
• Regular weekly 500 tons of bulk spool shipments
on priority basis worldwide.
Crating, Bundling, Containerizing
2008- 2014 Total : $ 270 MGlobal Sourcing
Worldwide Deliveries Over 40 countries
www.cimtaspipe.com