LAGUINDINGAN AIRPORT DEVELOPMENT PROJECTOur Northern Gateway to Mindanao
7/29/2019 Laguindingan Airport Development Project (LADP) Status as of 15 March 2013
2/13
A. Civil Works and Building Component
Substantially completed
Remaining works are the interfacing items with the Air Navigation System and Support
Facilities (ANSSF) component for the testing and commissioning of equipment installed in
all buildings
98.66%
B. Air Navigation System and Support Facilities (ANSSF) Component
Notice of Award was issued on 14 January 2013 to SKY-KR Consortium, the winning bidder
The Contract Agreement with SKY-KR Consortium was signed on 18 February 2013 and it
was concurred by EDCF on 07 March 2013 The Notice to Proceed was issued on 12 March 2013
The project is expected to be completed in the 2nd Quarter of 2014
C. Operation and Maintenance (O&M) of the Laguindingan Airport
The DOTC is considering the inclusion of possible development in the O&M for reason that
the Lumbia airport has already surpassed the design annual passenger movement of the
Laguindingan airport for the year 2020
D. Planned Commercial Opening of the Laguindingan Airport
The airport is planned to open on 30 April 2013 using Visual Flight Rule (VFR)
7/29/2019 Laguindingan Airport Development Project (LADP) Status as of 15 March 2013
3/13
Pavement Markings Pavement MarkingsPavement Markings
ApronTaxiway
Storm Drainage
Runway
Perimeter Fence & Road
Sodding
7/29/2019 Laguindingan Airport Development Project (LADP) Status as of 15 March 2013
4/13
Passenger Terminal Bldg
Operation & Control Tower Bldg
Administration BldgCrash Fire & Rescue Bldg
Cargo Terminal Bldg
Power House Bldg
Maintenance Bldg
Cold Water Receiving Station
Guard House
7/29/2019 Laguindingan Airport Development Project (LADP) Status as of 15 March 2013
5/13
Car Parking Area Car Parking Area Sewage Treatment Plant
Landscaping
Landscaping
LandscapingLandscaping
Landscaping Landscaping
7/29/2019 Laguindingan Airport Development Project (LADP) Status as of 15 March 2013
6/13
Ambulance
Grass Cutter
Tractor & Cart
7/29/2019 Laguindingan Airport Development Project (LADP) Status as of 15 March 2013
7/13
Departure Area
Escalator
Initial Security Check
Automated Weighing Scale &
Conveyors
Wicket Counters
Elevator @ Departure Area
CCTV Camera Final Security Check
Check-in Counters
7/29/2019 Laguindingan Airport Development Project (LADP) Status as of 15 March 2013
8/13
Inspection Benches
Departure Lounge
Gang Chair
Gate 1Gate 2 Gate 3
Boarding BridgeCIP Lounge VIP Lounge
7/29/2019 Laguindingan Airport Development Project (LADP) Status as of 15 March 2013
9/13
Hallway @ Boarding/Arrival Elevator @ Arrival Baggage Handling Carousel
Baggage Handling Carousel CCTV Camera @ Arrival AreaDome Type CCTV Camera @
Arrival Area
Arrival Exit
Information Counters FIDS @ Arrival Arrea
7/29/2019 Laguindingan Airport Development Project (LADP) Status as of 15 March 2013
10/13
7/29/2019 Laguindingan Airport Development Project (LADP) Status as of 15 March 2013
11/13
Weather Instruments
VHF Dipole Antenna
7/29/2019 Laguindingan Airport Development Project (LADP) Status as of 15 March 2013
12/13
ACTIVITIES STATUS REMARKS1. Power Supply The airport facility was energized by MORESCO-1 on
21 February 2013. The testing and commissioning ofinstalled equipment commenced on the same day andwill last until 15 April 2013.
Initially, MORESCO-1 is supplying
power to the airport using 1MVAduring the testing of equipment withtheir 10MVA substation in Moog,Laguindingan. They are capable of
providing the 4MVA requirement ofthe airport.
2. Water Supply A newly drilled well and rehabilitation of the existing
well is 80% completed. Completion of the system is
scheduled by the end of March 2013.
3. Telephone System The PLDT has already accomplished 80% of its cablingactivity from the national highway to the airport.
CAAP to sign an agreement with PLDT for the
connection .
Target date of completion includingthe connection to the airport facilityis by the 1st week of April 2013.
4. Transport System DOTC Planning Service conducted site visit & survey atLaguindingan airport on 06 March 2013 relative to theestablishment of the airports transport system.
LTFRB requested DOTC for the lifting of moratorium forthe granting of franchises.
LTFRB-10 will further explainregarding this matter.
5. CommunicationSystem
CAAP installed VHF & HFSSB for an interimcommunication facility.
Tested already.