KPI Project Progress Report (Project I: Key Performance Indicator
Methodology for Auditing IT Programs)
China National Audit Office
January, 2012
1. Background
2. Project history
3. Project objectives
4. Project scope
5. Project plan
6. PKI beta database
Contents
1. Background
the 19th of the INTOSAI Working Group on
IT Audit
Development of IT Performance Indicators
Performance measures of IT Solutions
implemented in government organizations
Index System about IT Performance Audit
1. Background
the 19th of the INTOSAI Working Group on
IT Audit
The above three projects were put into a new
one. “Key Performance Indicator Methodology
for Auditing IT Programs”.
China volunteered to be the team leader.
team members : SAI Bhutan, China, Ecuador,
Japan, Kuwait, Malaysia, Pakistan, Poland,
Russia and USA.
1. Background
2. Project history
3. Project objectives
4. Project scope
5. Project plan
6. PKI beta database
Contents
2. Project history
the first group meeting on Apr 16, 2010 in
Beijing.
a new name for the project, “Key
Performance Indicator Methodology for
Auditing IT Programs”.
the minutes of the first team meeting.
2. Project history
SAI Russia, Japan , USA , Kuwait and
Ecuador explained their own understanding
about the project.
the project initiation document.
2. Project history
SAI Kuwait submitted the beta database of
KPI indicators.
the original framework for comments.
SAI Kuwait, Bhutan and Japan gave their
comments and suggestion.
a new framework.
2. Project history
the Second group meeting on Apr 16th,
2011 in South Africa
the minutes of the second team meeting
2. Project history
SAI Kuwait submitted KPI beta database
categorized.
SAI Bhutan gave comments on draft framework of
KPI.
SAI China composed the draft of indicators based
on the team members’ deliverables and send it to
the team members for comments by the end of
November.
SAI Kuwait and Japan gave their comments and
suggestion.
1. Background
2. Project history
3. Project objectives
4. Project scope
5. Project plan
6. PKI beta database
Contents
3. Project objectives
develop the mechanisms
implement a KPI’s in the SAI’s
exchange views, know-how, and information
two principal outcomes of the project
1. Background
2. Project history
3. Project objectives
4. Project scope
5. Project plan
6. PKI beta database
Contents
4. Project scope
a set of specific and measurable IT-related
indicators
the ideas of KPIs application
feasible KPI setting and evaluation
methodology
audit case studies of IT projects using KPIs
Investigation and development of possible
areas of performance indication
Analysis, conclusions and decision making
based on results of performance
measurement
Analysis, conclusions and decision making
based on results of performance
measurement.
4. Project scope
1. Background
2. Project history
3. Project objectives
4. Project scope
5. Project plan
6. PKI beta database
Contents
5. Project plan
Milestone
the project framework
the beta database
the draft project Guidance
the final project Guidance
5. Project plan
Next detailed work plan
By the end of April 2012, SAIs submit their own
draft project guidance.
Before June 15, 2012, SAI China composes the
first draft project guidance.
By the end of August 2012, SAIs give comments
and suggestions.
Before October 15, 2012, SAI China composes
the second draft project guidance.
By the end of November 2012, SAIs give further
comments and suggestions.
By the end of January 2013, SAI China composes
the final project guidance.
1. Background
2. Project history
3. Project objectives
4. Project scope
5. Project plan
6. PKI beta database
Contents
6. Framework of PKI project
11 parts, 712 indicators.
1. Decision (20 indicators) Compliance with the laws (21 indicators)
Feasibility study (5 indicators)
Participation in decision (4 indicators)
6. Framework of PKI project
2. Requirement analysis (17 indicators) Organization target (9 indicators)
Core business coverage (1 indicator)
Response/change (7 indicators)
3. Design / Planning (95 indicators) Requirement coverage (10 indicators)
Time limit (2 indicators)
Capacity Planning (18 indicators)
Cost estimation (42 indicators)
IT risks (Added sub-category, 22 indicators)
Not decided(1 indicator).
6. Framework of PKI project
4. Procurement/Development (102 indicators)
Selection for partner or supplier (12 indicators)
Cost control(16 indicators)
Process Control(12 indicators)
Code control(2 indicators)
Selection for software and hardware(1 indicator)
Outsourcing (3 indicators)
Quality Control (26 indicators)
Testing (10 indicators)
Training (19 indicators)
Upgrading (1 indicator)
6. Framework of PKI project
5. Product (41 indicators)
User satisfaction(2 indicators)
Price (3 indicators)
Delivery (5 indicators)
Performance (26 indicators)
Integration (1 indicator)
Technology applicability(4 indicators)
6. Framework of PKI project 6. Maintenance (281 indicators)
Follow the management rules (23 indicators)
Incident management (57 indicators)
Easy to be used (5 indicators)
Availability (18 indicators)
IT Continuity (9 indicators)
Maintenance cost (12 indicators)
Website (54 indicators)
Monitoring(42 indicators)
Change Management (34 indicators)
Data Center (12 indicators)
Configuration management (Added sub-category, 12 indicators)
Not decided(3 indicators)
6. Framework of PKI project
7. Security (27 indicators)
Security plan
Identity management
User account management
Security testing monitoring
Security incident definition
Malicious software prevention
Network security
6. Framework of PKI project
8. Backup and Disaster Recovery (14
indicators)
Backup plan
Recovery plan
Backup operation management
Recovery operation management
6. Framework of PKI project
9. Service (56 indicators)
Response (41 indicators)
Usage by user(0 indicator)
Ratio of performance to price (0 indicator)
Satisfaction (11 indicators)
Service request(Added sub-category, 4
indicators)
6. Framework of PKI project
10. Effectiveness (38 indicators)
Coverage of the core business (7 indicators)
Usage of the employees for the certain application(1
indicator)
Output (6 indicators)
Benefit (10 indicators)
Internal Management optimizing (6 indicators)
Leaning and growth capability for the organization (1
indicator)
Public Service(3 indicators)
Not decided(3 indicators)
11. Others (21 indicators)