Information Technology Department
Bond Program Implementation Plan
January 8, 2013
1
West Contra Costa Unified School District
Agenda
• Project Selection Drivers• Fund Allocation and Schedule Determinants• Funding Need Schedule• Budget for 2013• Project Implementation Schedule
2
Project Selection Drivers
• Compliance• Instructional Technology• Infrastructure
3
Fund Allocation and Schedule Determinants
• Online Assessment compliance by 2014• Common Core requirements• Curriculum & Technology Integration• Digital Equity
4
Funding Need Schedule
5
Year Amount ($M) Cumulative ($M)
2013 20 20
2015 8 28
2017 5 33
2019 2 35
Budget for 2013
6
Scheduled Technology Projects for the First Two (2) Years
Project Sites Projected Budget
Wireless All $ 6,775,000.00
Refresh of Student Desktop Computers All $ 800,000.00
Virtual Desktop Infrastructure (VDI) All $ 5,300,000.00
Cloud Initiative All $ 1,150,000.00
Professional Development * All $ 1,000,000.00
Educational Software All $ 900,000.00
Help Desk Management All $ 600,000.00
Single- Sign -On (Completion) All $ 250,000.00
Website Enhancements All $ 100,000.00
Resource Augmentation * All $ 270,000.00
Document SOP All $ 540,000.00
Relocate Data Center All $ 1,000,000.00
Upgrade Wiring to Fire Code Standards All $ 300,000.00
Project Management $ 1,015,000.00 Projected Total: $20,000,000.00
* Requires legal vetting
Budget for 2013 (Cont’d)
7
Supporting Facilities Projects
Project Sites Cost
Security Cameras 10 $ 3,250,000.00
Card Access 10 $ 2,250,000.00
Project Management $ 612,500.00
Total: $6,112,500.00
Project Implementation Schedule
8
No. Project Start End Duration
Days
1 Wireless 1/1/2013 7/31/2015 720.00
3 Refresh of Student Desktop Computers 1/1/2013 12/29/2013 150.00
2 Single Sign-On 1/1/2013 8/1/2013 212.00
4 Help Desk Management 1/1/2013 7/31/2014 941.00
5 Upgrade All Wiring to Fire Code Standards 8/1/2013 12/31/2013 152.00
6 Professional Development 8/1/2013 7/31/2015 729.00
7 Website Enhancements 8/1/2013 7/31/2015 729.00
8 Resource Augmentation 8/1/2013 7/31/2015 729.00
9 Document SOP 8/1/2013 7/31/2014 364.00
10 Relocate Data Center 8/1/2013 7/31/2015 729.00
11 Educational Software 9/1/2013 12/31/2014 486.00
12 Virtual Desktop Infrastructure (VDI) 1/1/2014 12/31/2014 360.00
13 Cloud Initiative 8/1/2014 7/31/2015 364.00
Thank You
9