INDIANOLA MIDDLE SCHOOL
INDIANOLA MIDDLE SCHOOLJuly 12, 2011
ARCHITECTS
AREA A Steel framing being set
at new Main Entry to school.
ARCHITECTS
AREA A Steel framing being set
and block wall being laid at new Main Entry to school.
ARCHITECTS
AREA A Demo work
proceeding at new Guidance Counselor waiting area.
ARCHITECTS
AREA C Foundation walls
being set and concrete being poured at new Fieldhouse Gym.
ARCHITECTS
AREA C Foundation walls
being set and concrete being poured at new Fieldhouse Gym.
ARCHITECTS
AREA C Foundation walls
being set and concrete being poured at new Fieldhouse Gym.
ARCHITECTS
AREA C Site grading
complete and light poles being set at new bus lane drive aisle.
ARCHITECTS
AREA D Selective demo and
floor slabs being removed at old competition gym.
ARCHITECTS
AREA D New block wall
being laid and door and window frames being set at new multipurpose room.
ARCHITECTS
ALT #1 Site demo and
grading completed and new entry drive pour started at road connection to Highway 92.
ARCHITECTS