GRID MANAGEMENT ASPECT OF RENEWABLES
Sandip Sharma Manager, Operations Planning ERCOT RMEL 2019 Spring Conference May 20 – 22, 2019 Phoenix, Arizona
PUBLIC 2
Outlines
• Background information of ERCOT • Renewable Integration Practices and Solutions at ERCOT
– Grid Code – Forecasting – Ancillary Services – Risk Assessment – Real-Time Operations
PUBLIC 3
What is ERCOT?
The Texas Legislature restructured the Texas electric market in 1999 and assigned ERCOT four primary responsibilities: • System Reliability • Competitive Wholesale
Market • Open Access to
Transmission • Competitive Retail Market
ERCOT is a nonprofit organization and regulated by the Public Utility Commission of Texas, with oversight by the Texas Legislature. ERCOT is not a market participant and does not own generation or transmission/distribution wires.
PUBLIC 4
Current Records
Peak Demand Record: 73,473 megawatts (MW) • July 19, 2018, 4-5 p.m.
Weekend Peak Demand Record: 71,445 MW • Sunday, July 22, 2018, 5-6 p.m.
Winter Peak Demand Record: 65,915 MW • Jan. 17, 2018, 7-8 a.m.
Wind Generation Records (instantaneous) • Output: 19,672 MW
‒ Jan. 21, 2019, 7:19 p.m.
• Penetration (load served): 56.16% ‒ January 19, 2019, 3:10 a.m. ‒ Total MW Served by Wind = 17,406 MW
Recent Monthly Peak Demand Records 2019 • March: 60,692 MW (March 5, 7-8 a.m.) 2018 • January: 65,915 MW (Jan. 17, 7-8 a.m.)
• May: 67,265 MW (May 29, 4-5 p.m.)
• June: 69,123 MW (June 27, 4-5 p.m.)
• July: 73,473 MW (July 19, 4-5 p.m.)
• November: 56,317 MW (Nov. 14, 7-8 a.m.)
PUBLIC 5
Changing Resource Capacity Mix
Late 1990s 2018
[CATEGORY NAME] [VALUE]
[CATEGORY NAME] [VALUE]
[CATEGORY NAME] [VALUE]
[CATEGORY NAME] [VALUE]
[CATEGORY NAME] [VALUE]
[CATEGORY NAME] [VALUE]
[CATEGORY NAME] [VALUE]
[CATEGORY NAME] [VALUE]
[CATEGORY NAME] [VALUE]
[CATEGORY NAME] [VALUE]
[CATEGORY NAME] [VALUE]
[CATEGORY NAME] [VALUE]
[CATEGORY NAME] [VALUE]
[CATEGORY NAME] [VALUE]
[CATEGORY NAME] [VALUE]
[CATEGORY NAME] [VALUE]
PUBLIC 8
Outlines
• Background information of ERCOT • Renewable Integration Practices and Solutions at ERCOT
– Grid Code – Forecasting – Ancillary Services – Risk Assessment – Real-Time Operations
PUBLIC 9
Renewable Integration at ERCOT
1. Grid Code 2. Renewable Forecast
3. Ancillary Services
4. Risk Assessment
5. Real-time Operations
PUBLIC 10
IRR (Intermittent Renewable Resources)
Frequency Response (governor actions)
Reactive Capability
and Voltage Ride-through
Ramp Rate Limitation
Short Circuit Ratio
Secondary Frequency Response
Primary Frequency Response
Large Wind Ramp
Interconnection Requirements
System Impacts
PUBLIC 11
Integrating Renewables – Frequency Control
• All generation in ERCOT is required to provide governor response with a 5% droop setting with a deadband of 17 mHZ.
• Renewable resources started to assist in frequency control (by having an automatic response to frequency deviations) after 2010. – NERC’s BAL-001-TRE regional standard was implemented starting April 1,
2015. This reduced Governor Dead-band for most resources including renewables from 36 mHz to 17 mHZ.
PUBLIC 12
Voltage Ride-through Requirements
• Renewable resources that interconnected after 2008 are required to ride through i.e. stay online during abnormal disturbances in voltage and frequency.
No Tripping
00.10.20.30.40.50.60.70.80.91.01.11.2
-1 0 1 2
Volta
ge (p
er u
nit)
@ P
OI
0.15(9 cycles)
Pre-fault Period Voltage Recovery Period
Fault Clearing Period
Time (Seconds)
PUBLIC 13
Ramp Rate Limitation
• Renewable resources that were installed after 2009 are required to implement controls which limit per minute ramping to 20% of the unit’s nameplate rating.
6.5.7.10 Intermittent Renewable Resource Ramp Rate Limitations 1) Each Intermittent Renewable Resource (IRR) that is part of a Standard Generation Interconnection
Agreement (SGIA) signed on or after January 1, 2009 shall limit its ramp rate to 20% per minute of its nameplate rating (MWs) as registered with ERCOT when responding to or released from an ERCOT deployment.
2) The requirement of paragraph (1) above does not apply during a Force Majeure Event or during intervals in which a decremental deployment instruction coincides with a demonstrated decrease in the available IRR.
3) Each IRR that is part of an SGIA signed on or before December 31, 2008 and that controls power output by means other than turbine stoppage shall limit its ramp rate to 20% per minute of its nameplate rating (MWs) as registered with ERCOT when responding to or released from an ERCOT deployment.
PUBLIC 14
Renewable Integration at ERCOT
1. Grid Code 2. Renewable Forecast
3. Ancillary Services
4. Risk Assessment
5. Real-time Operations
PUBLIC 15
Wind Forecasting at ERCOT
WIND GENERATION RESOURCE (WGR)
• Asset Registration
Information
• Outage/De-rate Schedule
• Real Time Telemetry
WIND FORECAST SERVICE
• Two Forecast Service
Providers each provide:
• Hourly Forecast for each WGR for each hour of next week, updated hourly
• Intra-hour Forecast for
next 2-hr, at 5-min resolution, updated every 15-min
• Extreme Event Forecasts and Probabilistic Forecasts, used for risk assessment
ERCOT SYSTEMS
• ERCOT Control Room can select “active forecast” for every hour and every 5-min.
• Hourly Forecast Used in all Look Ahead Studies (ex. Outage Coordination, Reliability Unit Commitment, Next Day Study)
• Intra-hour Forecast To be used in Real Time Dispatch
• Extreme Event Forecasts and Probabilistic Forecasts, used for risk assessment
* WGR Operators can reduce the Current Operating Plan (COP) High Sustained Limit (HSL) to reflect operating condition changes.
PUBLIC 20
Renewable Integration at ERCOT
1. Grid Code 2. Renewable Forecast
3. Ancillary Services
4. Risk Assessment
5. Real-time Operations
PUBLIC 21
• SCED sends dispatch instruction every 5 minutes.
• LFC sends Regulation signals to generation resources every 4 second service to move up or down to maintain frequency at nominal.
Ancillary Services – Regulation Service
PUBLIC 24
Ancillary Services – Non-Spinning Reserve Service (NSRS) • Non-spinning Reserve Service
– 30 minute product that can be provided by unloaded capacity, offline Generators, and Load Resources
– Wind power and load forecast error is one of the inputs used for calculating the requirement for this service
– The net forecast error uncertainty that NSRS will be used to mitigate will depend on the risk of net load ramp.
– During higher net load ramp risk hours, we procure NSRS to cover up to 95th percentile of net forecast uncertainty.
– During low net load ramp risk hours, we may only procure NSRS to cover 70th percentile of net forecast uncertainty.
PUBLIC 26
Ancillary Services – Responsive Reserves
• Responsive Reserves are procured to ensure sufficient capacity is available to respond to frequency excursions due to unit trips ‒ Capacity reserved from generators to provide governor response
‒ Up to 60% of Responsive requirement can be provided by Load
Resources on under-frequency relays (to trip when frequency decreases to 59.7 Hz for .5s) once minimum 1150 MW has been procured from Generators proving PFR
• Since 2015, the Responsive Reserve procurement is based on
expected system inertia.
PUBLIC 27
Inertial Effect
Initial rate of change of frequency (prior to any resource response) is solely a function of inertia
PUBLIC 28
Frequency Response Times
• Load Resources providing RRS have underfrequency relays that respond in about 0.5s after the frequency drops below the trigger level (currently 59.7Hz)
• Governors of thermal generating units begin to respond “immediately” but will take 1-3 seconds to provide significant response (requires more steam or more combustion)
PUBLIC 29
Current RRS Studies
Case1 Case2 Case 3 Case4 Case5 Case6 Case7 Case8 Case9 Case10 Case11 Case12 Case13 Case14 Case15 Case16
Inertia (GW∙s) 130 140 150 160 170 180 190 200 220 230 260 270 290 300 359 376
LRs/PFR 2.39:1 2.17:1 1.85:1 1.85:1 2.00:1 1.71:1 1.53:1 1.43:1 1.55:1 1.30:1 1.10:1 1.10:1 1.00:1 1.20:1 1.00:1 0.89:1
PFR Requirement
(No LRs) 5691 5056 4388 4295 4550 3972 3445 3224 3475 2970 2745 2580 2450 2650 2300 2085
PFR min 1150 1150 1150 1150 1150 1150 1150 1150 1150 1150 1150 1150 1150 1150 1150 1150
LRs 1900 1800 1750 1700 1700 1650 1500 1450 1500 1400 1450 1300 1300 1250 1150 1050
Combined Total 3050 2950 2900 2850 2850 2800 2650 2600 2650 2550 2600 2450 2450 2400 2300 2200
PUBLIC 31
Renewable Integration at ERCOT
1. Grid Code 2. Renewable Forecast
3. Ancillary Services
4. Risk Assessment
5. Real-time Operations
PUBLIC 34
Renewable Integration at ERCOT
1. Grid Code 2. Renewable Forecast
3. Ancillary Services
4. Risk Assessment
5. Real-time Operations
PUBLIC 35
Real Time System Wide Wind Generation Curtailment
0
100
200
300
400
500
600
700
800
4000
4500
5000
5500
6000
6500
7000
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Win
d C
urta
ilmen
t (M
W)
Win
d G
ener
atio
n (M
W)
Hour
Base Point Telemetry MW HDL Curtailment MW
PUBLIC 37
164
166
168
170
172
174
176
178
180
59.85
59.875
59.9
59.925
59.95
59.975
60
60.025
60.05
13:25 13:28 13:31 13:34 13:37 13:40
WIND RESOURCE RESPONSE TO LOW FREQUENCY 07/13/2016
Frequency Nominal Frequency MW
Integrating Renewables – Frequency Control
• Renewable resources started to assist in frequency control (by having an automatic response to frequency deviations) after 2010.
80
90
100
110
120
130
140
59.925
59.944
59.963
59.981
60.000
60.019
60.038
60.056
60.075
16:13 16:16 16:19 16:22 16:25 16:28
WIND RESOURCE RESPONSE TO HIGH FREQUENCY 08/25/2015
Frequency Nominal Frequency MW