Download - Grand Junction Multi-use Path Design Working Group Meeting ......GRAND JUNCTION MULTI-USE PATH DESIGN PROJECT WORKING GROUP #2 - JULY 22, 2019 Working Group Meeting #2 1 . MEETING

Transcript
Page 1: Grand Junction Multi-use Path Design Working Group Meeting ......GRAND JUNCTION MULTI-USE PATH DESIGN PROJECT WORKING GROUP #2 - JULY 22, 2019 Working Group Meeting #2 1 . MEETING

CITY OF CAMBRIDGE

GRAND JUNCTION MULTI-USE PATH DESIGN PROJECT WORKING GROUP #2 - JULY 22, 2019

Working Group Meeting #2 1

Page 2: Grand Junction Multi-use Path Design Working Group Meeting ......GRAND JUNCTION MULTI-USE PATH DESIGN PROJECT WORKING GROUP #2 - JULY 22, 2019 Working Group Meeting #2 1 . MEETING

MEETING

AGENDA

Working Group Meeting #2 2

Page 3: Grand Junction Multi-use Path Design Working Group Meeting ......GRAND JUNCTION MULTI-USE PATH DESIGN PROJECT WORKING GROUP #2 - JULY 22, 2019 Working Group Meeting #2 1 . MEETING

Meeting agenda

WORKING GROUP MEETING #2

Welcome! Introductions and welcome (10 min)

Recap meetings held to date (20 min) Working Group Meeting #1 Public Meeting #1 Other updates

Group input s ession: Visual photo tour (55 min)

Group feedback and homework (15 min) Stakeholder outreach through Working Group Members visit Grand Junction Park before next meeting

Public comment (10 min)

Upcoming meetings schedule (5 min)

Next steps (5 min) Working Group Meeting #2 3

Page 4: Grand Junction Multi-use Path Design Working Group Meeting ......GRAND JUNCTION MULTI-USE PATH DESIGN PROJECT WORKING GROUP #2 - JULY 22, 2019 Working Group Meeting #2 1 . MEETING

INTRODUCTIONS

AND

WELCOME

Working Group Meeting #2 4

Page 5: Grand Junction Multi-use Path Design Working Group Meeting ......GRAND JUNCTION MULTI-USE PATH DESIGN PROJECT WORKING GROUP #2 - JULY 22, 2019 Working Group Meeting #2 1 . MEETING

Introductions and Welcome

REFRESHER: WHAT IS A WORKING GROUP?

Working groups assist the City and project teams to understand the sentiment of Cambridge residents, workers, and visitors.

People who live, work, or

play in Cambridge

Design Working Group

Project team

Note: members of the public will have opportunities at the end of each working group meeting to raise issues and comment on the discussion.

Working Group Meeting #2 5

Page 6: Grand Junction Multi-use Path Design Working Group Meeting ......GRAND JUNCTION MULTI-USE PATH DESIGN PROJECT WORKING GROUP #2 - JULY 22, 2019 Working Group Meeting #2 1 . MEETING

Working Group Overview

MEETING GUIDELINES & GROUND RULES

General working group meeting guidelines:

Prepare before each meeting: read agenda and materials

Start meeting on time & end on time

Help us stay on schedule

Working Group “Ground Rules”:

Have only one person speak at a time

Members should not repeat topics (an “air knock” was suggested to signal agreement with comments said)

Be aware of your air time

If you want to speak, turn your tent card on its end (a version of hand raise)

Limit use of cell phones/distraction – Silencing phones is ideal, however if members need to take a phone call or text/email, that is OK with the members.

• Use restroom as needed (don’t have to ask)

Working Group Meeting #2 6

Page 7: Grand Junction Multi-use Path Design Working Group Meeting ......GRAND JUNCTION MULTI-USE PATH DESIGN PROJECT WORKING GROUP #2 - JULY 22, 2019 Working Group Meeting #2 1 . MEETING

Working Group Overview

MEETING GUIDELINES & GROUND RULES

Working Group “Ground Rules” (cont.):

Respect others

Assume good intentions

• Have an expectation that everyone speaks

Step up to be heard and step back if talking to much

Don’t criticize other members – listen even if you don’t agree

What ways can be created to have everyone be more comfortable to speak within group? Perhaps use map tools to put comments (WIKIMAPS)

Send out notes to the members

If members have comments after the meeting, staff send comments out to everyone and add into notes before posting

NOTE: Members of the public are welcome to listen and comment. As a rule, we ask members of the public that your comments be related to topics on the agenda and be made during the public comment period, so that the focus of the meeting is on facilitating input from working group members.

NOTE: If a Design Working Group member cannot attend, they are welcome to ask someone to attend as a member of the public and report back. Working group members cannot be substituted and alternates are not allowed.

Working Group Meeting #2 7

Page 8: Grand Junction Multi-use Path Design Working Group Meeting ......GRAND JUNCTION MULTI-USE PATH DESIGN PROJECT WORKING GROUP #2 - JULY 22, 2019 Working Group Meeting #2 1 . MEETING

RECAP OF

MEETINGS HELD

TO DATE

Working Group Meeting #2 8

Page 9: Grand Junction Multi-use Path Design Working Group Meeting ......GRAND JUNCTION MULTI-USE PATH DESIGN PROJECT WORKING GROUP #2 - JULY 22, 2019 Working Group Meeting #2 1 . MEETING

Recap of Meetings Held to Date

REVIEW OF APRIL 30 WORKING GROUP MEETING

Miller's River, Paul Dudley Existing Somerville White/Mem Grand border Drive Junction Park

Allston I90 Interchange Project

MIT / 77 Mass Ave

GLX Project

Project Purpose

Fully design and create construction documents for a multi-use path adjacent to the existing rail tracks in the Grand Junction corridor from the Boston University Bridge to Somerville

Working Group Meeting #2 9

Page 10: Grand Junction Multi-use Path Design Working Group Meeting ......GRAND JUNCTION MULTI-USE PATH DESIGN PROJECT WORKING GROUP #2 - JULY 22, 2019 Working Group Meeting #2 1 . MEETING

10

Recap of Meetings Held to Date

REVIEW OF APRIL 30 WORKING GROUP MEETING

Visions for Grand Junction Path

Commuting corridor

Recreational/exercise resource for

students, residents, and families

Infrastructure to support Vision Zero policy

Active transportation connection between

neighborhoods

Working Group Meeting #2

Page 11: Grand Junction Multi-use Path Design Working Group Meeting ......GRAND JUNCTION MULTI-USE PATH DESIGN PROJECT WORKING GROUP #2 - JULY 22, 2019 Working Group Meeting #2 1 . MEETING

Recap of Meetings Held to Date

REVIEW OF APRIL 30 WORKING GROUP MEETING

Likes and Dislikes from Urban “Rail with Trail” Case Studies

Case Studies that Received the Most Comments: • Duwamish, Waterfront, Burke-Gilman Trails (Washington State) • Burlington Greenway (Vermont) • Springwater on the Willamette Trail (Oregon) • Libba Cotton Bikepath (North Carolina) • East Boston Greenway (Massachusetts)

Liked Element of the Case Studies: Wayfinding/Signage; Separation of railroad from trail/path with mid-height fencing; separation of bicycles and pedestrians on paved path

Disliked Elements of the Case Studies: Poor lighting under highway overpasses and bridges (feels unsafe); path crossings over railroad tracks; no barrier between path and rail

Burlington Greenway

East Boston Greenway

Working Group Meeting #2 11

Page 12: Grand Junction Multi-use Path Design Working Group Meeting ......GRAND JUNCTION MULTI-USE PATH DESIGN PROJECT WORKING GROUP #2 - JULY 22, 2019 Working Group Meeting #2 1 . MEETING

Recap of Meetings Held to Date

JUNE 4 PUBLIC MEETING Legend: R Y G

Public Input Exercise - Visual Preference Survey

Likes: Barrier/Separation from Rail and Trail, Wayfinding signage not like roadway signage, well designed path crossings over railroad tracks, using landscaping to create destinations(parklets), well designed lighting

Dislikes: Overuse of public art; high chain link fencing, rubberized railroad crossings; path paving differ from road

Needs: Benches, trash bins and water stations Working Group Meeting #2 12

Page 13: Grand Junction Multi-use Path Design Working Group Meeting ......GRAND JUNCTION MULTI-USE PATH DESIGN PROJECT WORKING GROUP #2 - JULY 22, 2019 Working Group Meeting #2 1 . MEETING

Other Updates

OUTREACH WITH MAYOR'S SUMMER YOUTH WORKERS

Door-to-door Flyering

Working Group Meeting #2 13

Page 14: Grand Junction Multi-use Path Design Working Group Meeting ......GRAND JUNCTION MULTI-USE PATH DESIGN PROJECT WORKING GROUP #2 - JULY 22, 2019 Working Group Meeting #2 1 . MEETING

Other Updates

ONGOING COORDINATION

Continuing coordination with MassDOT, MBTA and MIT

Completed MAPC Pathway Benefits study – summary to be shared soon

Kendall Square Association distribution of Transport Kendall report distribution (advocating for Grand Junction multi-use path and future passenger transit)

RailVision in process of analyzing alternatives

Cambridge Bike Plan Update – in community outreach stage

GLX team working with advocates to not preclude a future regional path connection

Allston I90 Interchange Project MEPA process updates:

Final Notice of Project Change (NPC) in late 2020 Final EIR in 2021

Working Group Meeting #2 14

Page 15: Grand Junction Multi-use Path Design Working Group Meeting ......GRAND JUNCTION MULTI-USE PATH DESIGN PROJECT WORKING GROUP #2 - JULY 22, 2019 Working Group Meeting #2 1 . MEETING

GROUP

INPUT

SESSION

Working Group Meeting #2 15

Page 16: Grand Junction Multi-use Path Design Working Group Meeting ......GRAND JUNCTION MULTI-USE PATH DESIGN PROJECT WORKING GROUP #2 - JULY 22, 2019 Working Group Meeting #2 1 . MEETING

Can--b · Harvard Sq.

.,, rtdgest

(I)

\

(I) Central Sq.

Cambridgeport / / /

/ /

< /

Future path connections to Paul Dudley White, Allston

Future connections to Community Path and Minuteman bikeway

Wellington-Harrington

~ ),

;j'? · /,,,

The Port

(9~ ~

Main St

Gore St East

Cambridge

Binney St

Lechmere (I)

(I) Kendall Longfellow Bridge

Area 2/MIT

Key

II II

r - , L - _,

N

C)

Two Existing Tracks

Single Existing Track

Future Regional Connections

Path Not Funded

City Borders

History & Policies

VISUAL PHOTO TOUR OF CORRIDOR

Working Group Meeting #2 16

Page 17: Grand Junction Multi-use Path Design Working Group Meeting ......GRAND JUNCTION MULTI-USE PATH DESIGN PROJECT WORKING GROUP #2 - JULY 22, 2019 Working Group Meeting #2 1 . MEETING

Group Input Session

IDEAL CROSS-SECTION DESIGN OF GRAND JUNCTION MULTI-USE PATH

Working Group Meeting #2 17

Page 18: Grand Junction Multi-use Path Design Working Group Meeting ......GRAND JUNCTION MULTI-USE PATH DESIGN PROJECT WORKING GROUP #2 - JULY 22, 2019 Working Group Meeting #2 1 . MEETING

Group Input Session

PHOTO TOUR – MASSDOT-OWNED SECTION

Near Henry and Waverly

Likely furthest west possible terminus in near-term

Working Group Meeting #2 18

Page 19: Grand Junction Multi-use Path Design Working Group Meeting ......GRAND JUNCTION MULTI-USE PATH DESIGN PROJECT WORKING GROUP #2 - JULY 22, 2019 Working Group Meeting #2 1 . MEETING

Group Input Session

PHOTO TOUR – MASSDOT-OWNED SECTION

Near Henry and Waverly

Likely furthest west possible terminus in near-term

Working Group Meeting #2 19

Page 20: Grand Junction Multi-use Path Design Working Group Meeting ......GRAND JUNCTION MULTI-USE PATH DESIGN PROJECT WORKING GROUP #2 - JULY 22, 2019 Working Group Meeting #2 1 . MEETING

Group Input Session

PHOTO TOUR – MASSDOT-OWNED SECTION

Near Fort Washington Park

Working Group Meeting #2 20

Page 21: Grand Junction Multi-use Path Design Working Group Meeting ......GRAND JUNCTION MULTI-USE PATH DESIGN PROJECT WORKING GROUP #2 - JULY 22, 2019 Working Group Meeting #2 1 . MEETING

Group Input Session

PHOTO TOUR – MASSDOT-OWNED SECTION

Near Fort Washington Park

Working Group Meeting #2 21

Page 22: Grand Junction Multi-use Path Design Working Group Meeting ......GRAND JUNCTION MULTI-USE PATH DESIGN PROJECT WORKING GROUP #2 - JULY 22, 2019 Working Group Meeting #2 1 . MEETING

Group Input Session

PHOTO TOUR – MASSDOT-OWNED SECTION

Near Fort Washington Park

Working Group Meeting #2 22

Page 23: Grand Junction Multi-use Path Design Working Group Meeting ......GRAND JUNCTION MULTI-USE PATH DESIGN PROJECT WORKING GROUP #2 - JULY 22, 2019 Working Group Meeting #2 1 . MEETING

Group Input Session

PHOTO TOUR – APPROACHING MIT-OWNED SECTION

Approximate boundary of MassDOT and MIT sections

Pacific Street crossing is another access point

Working Group Meeting #2 23

Page 24: Grand Junction Multi-use Path Design Working Group Meeting ......GRAND JUNCTION MULTI-USE PATH DESIGN PROJECT WORKING GROUP #2 - JULY 22, 2019 Working Group Meeting #2 1 . MEETING

Group Input Session

PHOTO TOUR – APPROACHING MIT-OWNED SECTION

Approximate boundary of MassDOT and MIT sections

Pacific Street crossing is another access point

Working Group Meeting #2 24

Page 25: Grand Junction Multi-use Path Design Working Group Meeting ......GRAND JUNCTION MULTI-USE PATH DESIGN PROJECT WORKING GROUP #2 - JULY 22, 2019 Working Group Meeting #2 1 . MEETING

Group Input Session

PHOTO TOUR – MIT-OWNED SECTION

Pacific Street crossing

Working Group Meeting #2 25

Page 26: Grand Junction Multi-use Path Design Working Group Meeting ......GRAND JUNCTION MULTI-USE PATH DESIGN PROJECT WORKING GROUP #2 - JULY 22, 2019 Working Group Meeting #2 1 . MEETING

Group Input Session

PHOTO TOUR – MIT-OWNED SECTION

Pacific Street crossing

Working Group Meeting #2 26

Page 27: Grand Junction Multi-use Path Design Working Group Meeting ......GRAND JUNCTION MULTI-USE PATH DESIGN PROJECT WORKING GROUP #2 - JULY 22, 2019 Working Group Meeting #2 1 . MEETING

Group Input Session

PHOTO TOUR – MIT-OWNED SECTION

Between Pacific Street crossing and Mass Ave

Working Group Meeting #2 27

Page 28: Grand Junction Multi-use Path Design Working Group Meeting ......GRAND JUNCTION MULTI-USE PATH DESIGN PROJECT WORKING GROUP #2 - JULY 22, 2019 Working Group Meeting #2 1 . MEETING

Group Input Session

PHOTO TOUR – MIT-OWNED SECTION

Between Pacific Street crossing and Mass Ave

Working Group Meeting #2 28

Page 29: Grand Junction Multi-use Path Design Working Group Meeting ......GRAND JUNCTION MULTI-USE PATH DESIGN PROJECT WORKING GROUP #2 - JULY 22, 2019 Working Group Meeting #2 1 . MEETING

Group Input Session

PHOTO TOUR – MIT-OWNED SECTION

Approaching Mass Ave, adjacent to NW12 and Metropolitan Storage Warehouse

Working Group Meeting #2 29

Page 30: Grand Junction Multi-use Path Design Working Group Meeting ......GRAND JUNCTION MULTI-USE PATH DESIGN PROJECT WORKING GROUP #2 - JULY 22, 2019 Working Group Meeting #2 1 . MEETING

Group Input Session

PHOTO TOUR – MIT-OWNED SECTION

Approaching Mass Ave, adjacent to NW12 and Metropolitan Storage Warehouse

Working Group Meeting #2 30

Page 31: Grand Junction Multi-use Path Design Working Group Meeting ......GRAND JUNCTION MULTI-USE PATH DESIGN PROJECT WORKING GROUP #2 - JULY 22, 2019 Working Group Meeting #2 1 . MEETING

Group Input Session

PHOTO TOUR – MIT-OWNED SECTION

Crossing the Massachusetts Avenue intersection

Working Group Meeting #2 31

Page 32: Grand Junction Multi-use Path Design Working Group Meeting ......GRAND JUNCTION MULTI-USE PATH DESIGN PROJECT WORKING GROUP #2 - JULY 22, 2019 Working Group Meeting #2 1 . MEETING

Group Input Session

PHOTO TOUR – MIT-OWNED SECTION

Between Mass Ave and Main Street

Working Group Meeting #2 32

Page 33: Grand Junction Multi-use Path Design Working Group Meeting ......GRAND JUNCTION MULTI-USE PATH DESIGN PROJECT WORKING GROUP #2 - JULY 22, 2019 Working Group Meeting #2 1 . MEETING

Group Input Session

PHOTO TOUR – MIT-OWNED SECTION

Between Mass Ave and Main Street

Working Group Meeting #2 33

Page 34: Grand Junction Multi-use Path Design Working Group Meeting ......GRAND JUNCTION MULTI-USE PATH DESIGN PROJECT WORKING GROUP #2 - JULY 22, 2019 Working Group Meeting #2 1 . MEETING

Group Input Session

PHOTO TOUR – MIT-OWNED SECTION

Adjacent to N16 Co-generation Plant, viewing Co-gen Plant Addition

Working Group Meeting #2 34

Page 35: Grand Junction Multi-use Path Design Working Group Meeting ......GRAND JUNCTION MULTI-USE PATH DESIGN PROJECT WORKING GROUP #2 - JULY 22, 2019 Working Group Meeting #2 1 . MEETING

Group Input Session

PHOTO TOUR – MIT-OWNED SECTION

Adjacent to N16 Co-generation Plant, viewing Co-gen Plant Addition

Working Group Meeting #2 35

Page 36: Grand Junction Multi-use Path Design Working Group Meeting ......GRAND JUNCTION MULTI-USE PATH DESIGN PROJECT WORKING GROUP #2 - JULY 22, 2019 Working Group Meeting #2 1 . MEETING

Group Input Session

PHOTO TOUR – MIT-OWNED SECTION

Albany/Vassar Street crossing

Working Group Meeting #2 36

Page 37: Grand Junction Multi-use Path Design Working Group Meeting ......GRAND JUNCTION MULTI-USE PATH DESIGN PROJECT WORKING GROUP #2 - JULY 22, 2019 Working Group Meeting #2 1 . MEETING

Group Input Session

PHOTO TOUR – MIT-OWNED SECTION

Albany/Vassar Street crossing

Working Group Meeting #2 37

Page 38: Grand Junction Multi-use Path Design Working Group Meeting ......GRAND JUNCTION MULTI-USE PATH DESIGN PROJECT WORKING GROUP #2 - JULY 22, 2019 Working Group Meeting #2 1 . MEETING

Group Input Session

PHOTO TOUR – MIT-OWNED SECTION

Approaching Brain and Cognitive Sciences Complex

Working Group Meeting #2 38

Page 39: Grand Junction Multi-use Path Design Working Group Meeting ......GRAND JUNCTION MULTI-USE PATH DESIGN PROJECT WORKING GROUP #2 - JULY 22, 2019 Working Group Meeting #2 1 . MEETING

Group Input Session

PHOTO TOUR – MIT-OWNED SECTION

Approaching Brain and Cognitive Sciences Complex

Working Group Meeting #2 39

Page 40: Grand Junction Multi-use Path Design Working Group Meeting ......GRAND JUNCTION MULTI-USE PATH DESIGN PROJECT WORKING GROUP #2 - JULY 22, 2019 Working Group Meeting #2 1 . MEETING

Group Input Session

PHOTO TOUR – MIT-OWNED SECTION

Underneath Brain and Cognitive Sciences Complex

Working Group Meeting #2 40

Page 41: Grand Junction Multi-use Path Design Working Group Meeting ......GRAND JUNCTION MULTI-USE PATH DESIGN PROJECT WORKING GROUP #2 - JULY 22, 2019 Working Group Meeting #2 1 . MEETING

Group Input Session

PHOTO TOUR – MIT-OWNED SECTION

Underneath Brain and Cognitive Sciences Complex

Working Group Meeting #2 41

Page 42: Grand Junction Multi-use Path Design Working Group Meeting ......GRAND JUNCTION MULTI-USE PATH DESIGN PROJECT WORKING GROUP #2 - JULY 22, 2019 Working Group Meeting #2 1 . MEETING

Group Input Session

PHOTO TOUR – MIT-OWNED SECTION

Underneath Brain and Cognitive Sciences Complex

Working Group Meeting #2 42

Page 43: Grand Junction Multi-use Path Design Working Group Meeting ......GRAND JUNCTION MULTI-USE PATH DESIGN PROJECT WORKING GROUP #2 - JULY 22, 2019 Working Group Meeting #2 1 . MEETING

Group Input Session

PHOTO TOUR – MIT-OWNED SECTION

Intersection at Main Street

Working Group Meeting #2 43

Page 44: Grand Junction Multi-use Path Design Working Group Meeting ......GRAND JUNCTION MULTI-USE PATH DESIGN PROJECT WORKING GROUP #2 - JULY 22, 2019 Working Group Meeting #2 1 . MEETING

Group Input Session

PHOTO TOUR – MIT-OWNED SECTION

Intersection at Main Street

Working Group Meeting #2 44

Page 45: Grand Junction Multi-use Path Design Working Group Meeting ......GRAND JUNCTION MULTI-USE PATH DESIGN PROJECT WORKING GROUP #2 - JULY 22, 2019 Working Group Meeting #2 1 . MEETING

Group Input Session

PHOTO TOUR – MIT-OWNED SECTION

Intersection at Main Street

Working Group Meeting #2 45

Page 46: Grand Junction Multi-use Path Design Working Group Meeting ......GRAND JUNCTION MULTI-USE PATH DESIGN PROJECT WORKING GROUP #2 - JULY 22, 2019 Working Group Meeting #2 1 . MEETING

Group Input Session

PHOTO TOUR – GRAND JUNCTION PARK SECTION

At Main Street facing North, where multi-use path constructed adjacent to roadway

Working Group Meeting #2 46

Page 47: Grand Junction Multi-use Path Design Working Group Meeting ......GRAND JUNCTION MULTI-USE PATH DESIGN PROJECT WORKING GROUP #2 - JULY 22, 2019 Working Group Meeting #2 1 . MEETING

Group Input Session

PHOTO TOUR – GRAND JUNCTION PARK SECTION

At Main Street facing North, where multi-use path constructed adjacent to roadway

Working Group Meeting #2 47

Page 48: Grand Junction Multi-use Path Design Working Group Meeting ......GRAND JUNCTION MULTI-USE PATH DESIGN PROJECT WORKING GROUP #2 - JULY 22, 2019 Working Group Meeting #2 1 . MEETING

Group Input Session

PHOTO TOUR – GRAND JUNCTION PARK SECTION

At Main Street facing North, where multi-use path has been constructed adjacent to roadway

Working Group Meeting #2 48

Page 49: Grand Junction Multi-use Path Design Working Group Meeting ......GRAND JUNCTION MULTI-USE PATH DESIGN PROJECT WORKING GROUP #2 - JULY 22, 2019 Working Group Meeting #2 1 . MEETING

Group Input Session

PHOTO TOUR – BINNEY STREET PARK SECTION

Just north of Broadway

Will be new Binney Park

Working Group Meeting #2 49

Page 50: Grand Junction Multi-use Path Design Working Group Meeting ......GRAND JUNCTION MULTI-USE PATH DESIGN PROJECT WORKING GROUP #2 - JULY 22, 2019 Working Group Meeting #2 1 . MEETING

Group Input Session

PHOTO TOUR – BINNEY STREET PARK SECTION

Just north of Broadway

Will be new Binney Park

Working Group Meeting #2 50

Page 51: Grand Junction Multi-use Path Design Working Group Meeting ......GRAND JUNCTION MULTI-USE PATH DESIGN PROJECT WORKING GROUP #2 - JULY 22, 2019 Working Group Meeting #2 1 . MEETING

Group Input Session

PHOTO TOUR – MASSDOT/ARE-EASEMENT SECTION

Crossing "Little" Binney

Working Group Meeting #2 51

Page 52: Grand Junction Multi-use Path Design Working Group Meeting ......GRAND JUNCTION MULTI-USE PATH DESIGN PROJECT WORKING GROUP #2 - JULY 22, 2019 Working Group Meeting #2 1 . MEETING

Group Input Session

PHOTO TOUR – MASSDOT/ARE-EASEMENT SECTION

Crossing "Little" Binney

Working Group Meeting #2 52

Page 53: Grand Junction Multi-use Path Design Working Group Meeting ......GRAND JUNCTION MULTI-USE PATH DESIGN PROJECT WORKING GROUP #2 - JULY 22, 2019 Working Group Meeting #2 1 . MEETING

Group Input Session

PHOTO TOUR – MASSDOT/ARE-EASEMENT SECTION

North of "Little" Binney, adjacent to 399 Broadway/garage and "Met Pipe" site

Working Group Meeting #2 53

Page 54: Grand Junction Multi-use Path Design Working Group Meeting ......GRAND JUNCTION MULTI-USE PATH DESIGN PROJECT WORKING GROUP #2 - JULY 22, 2019 Working Group Meeting #2 1 . MEETING

Group Input Session

PHOTO TOUR – MASSDOT/ARE-EASEMENT SECTION

Between Wellington-Harrington and East Cambridge neighborhoods

Working Group Meeting #2 54

Page 55: Grand Junction Multi-use Path Design Working Group Meeting ......GRAND JUNCTION MULTI-USE PATH DESIGN PROJECT WORKING GROUP #2 - JULY 22, 2019 Working Group Meeting #2 1 . MEETING

Group Input Session

PHOTO TOUR – MASSDOT/ARE-EASEMENT SECTION

Between Wellington-Harrington and East Cambridge neighborhoods

Working Group Meeting #2 55

Page 56: Grand Junction Multi-use Path Design Working Group Meeting ......GRAND JUNCTION MULTI-USE PATH DESIGN PROJECT WORKING GROUP #2 - JULY 22, 2019 Working Group Meeting #2 1 . MEETING

Group Input Session

PHOTO TOUR – MASSDOT/ARE-EASEMENT SECTION

Crossing Cambridge St, facing Miller's River Property

Working Group Meeting #2 56

Page 57: Grand Junction Multi-use Path Design Working Group Meeting ......GRAND JUNCTION MULTI-USE PATH DESIGN PROJECT WORKING GROUP #2 - JULY 22, 2019 Working Group Meeting #2 1 . MEETING

Group Input Session

PHOTO TOUR – MASSDOT/ARE-EASEMENT SECTION

Crossing Cambridge St, facing Miller's River Property

Working Group Meeting #2 57

Page 58: Grand Junction Multi-use Path Design Working Group Meeting ......GRAND JUNCTION MULTI-USE PATH DESIGN PROJECT WORKING GROUP #2 - JULY 22, 2019 Working Group Meeting #2 1 . MEETING

Group Input Session

PHOTO TOUR – CHA TO SOMERVILLE SECTION

North of Cambridge street

Adjacent to Miller's River parking lot

Working Group Meeting #2 58

Page 59: Grand Junction Multi-use Path Design Working Group Meeting ......GRAND JUNCTION MULTI-USE PATH DESIGN PROJECT WORKING GROUP #2 - JULY 22, 2019 Working Group Meeting #2 1 . MEETING

[ __ ..,.. __ , ,-.-o ...,. __ ,,.

Bicycle Network Vision with Key Destinations

Infrastructure recommendations in the Bicycle Network Vision take the form of a "level-of accommodation· for each street or path. These recommendations do not propose specific facility types, rather they provide infrastructure goals for each street or path which be reached through a variety of design trea s. Specific bicycle facility types will be rmined through a design process for each str r path, including public outreach and informe e latest best practices in bicycle infrastr re design at that time.

-----

Group Input Session

PROPOSED BICYCLE FACILITIES

Working Group Meeting #2 59

Page 60: Grand Junction Multi-use Path Design Working Group Meeting ......GRAND JUNCTION MULTI-USE PATH DESIGN PROJECT WORKING GROUP #2 - JULY 22, 2019 Working Group Meeting #2 1 . MEETING

• ·········• Grand Junction Path ~:-=..~

Bus Routes Intersecting with Grand Junction

MBTA Routes

II a a O I 64

- 68 - 69

Other Routes

- 85 CTl CT2

EZRide Shuttle (Main St & Mass Ave)

MASCO M2 Shuttle (Mass Ave)

MIT Boston Daytime Shuttle (Mass Ave)

MIT Tech Shuttle (adjacent to Grand Junction

Path on Vassar St)

MIT Safe Ride Shuttle (Main St, Mass Ave,

Gore St)

s, Main St RedUne

------ --~-#' _____ .-- - ----- ----

~ l?

I

--

Cllarteo s,

a.,, Sr

Middlesex County

Courthouse

CambridgeSide Shuttle 0 Ken<lall/M IT­

CambndgeS1de Galleria 617-621-8666

www.cambridgesidegalleriacom/ ~ Guest-Services

-tD-EZRide Shuttle

cambndg&-North Stabon 617-SEZlnfo

www.ch8l1esrivertmaorg

Group Input Session

TRANSIT INTERSECTIONS WITH GRAND JUNCTION

Working Group Meeting #2 60

Page 61: Grand Junction Multi-use Path Design Working Group Meeting ......GRAND JUNCTION MULTI-USE PATH DESIGN PROJECT WORKING GROUP #2 - JULY 22, 2019 Working Group Meeting #2 1 . MEETING

GROUP FEEDBACK AND

HOMEWORK

Working Group Meeting #2 61

Page 62: Grand Junction Multi-use Path Design Working Group Meeting ......GRAND JUNCTION MULTI-USE PATH DESIGN PROJECT WORKING GROUP #2 - JULY 22, 2019 Working Group Meeting #2 1 . MEETING

Or which organizations?

Group Feedback and Homework

ORGANIZATIONS

Which organizations should the team should reach out to…

for group presentations?

to get the word out?

62 Working Group Meeting #2

Page 63: Grand Junction Multi-use Path Design Working Group Meeting ......GRAND JUNCTION MULTI-USE PATH DESIGN PROJECT WORKING GROUP #2 - JULY 22, 2019 Working Group Meeting #2 1 . MEETING

Group Feedback and Homework

FIELD VISIT

Visit Grand Junction Park

Examine design elements

Rate likes and dislikes

Complete by next Working Group meeting on October 1, 2019

Working Group Meeting #2 63

Page 64: Grand Junction Multi-use Path Design Working Group Meeting ......GRAND JUNCTION MULTI-USE PATH DESIGN PROJECT WORKING GROUP #2 - JULY 22, 2019 Working Group Meeting #2 1 . MEETING

PUBLIC

COMMENT

Working Group Meeting #2 64

Page 65: Grand Junction Multi-use Path Design Working Group Meeting ......GRAND JUNCTION MULTI-USE PATH DESIGN PROJECT WORKING GROUP #2 - JULY 22, 2019 Working Group Meeting #2 1 . MEETING

NEXT STEPS

Working Group Meeting #2 65

Page 66: Grand Junction Multi-use Path Design Working Group Meeting ......GRAND JUNCTION MULTI-USE PATH DESIGN PROJECT WORKING GROUP #2 - JULY 22, 2019 Working Group Meeting #2 1 . MEETING

Project Scope & Schedule

PROJECT SCHEDULE

Schedule Overview

Working Group Meeting #2 66

Page 67: Grand Junction Multi-use Path Design Working Group Meeting ......GRAND JUNCTION MULTI-USE PATH DESIGN PROJECT WORKING GROUP #2 - JULY 22, 2019 Working Group Meeting #2 1 . MEETING

Public Comment

MEETING DATES (SUBJECT TO CHANGE)

• First Working Group, Tuesday 4/30/2019 • First Public Meeting, Tuesday, June 4, 2019 • Second Working Group, Tuesday 7/22/2019 • Third Working Group, October 1, 2019 • Second Public Meeting, October 29, 2019 • Fourth Working Group, December 3, 2019 • Fifth Working Group, February 2020 • 25% Design Public Meeting, March 2020 • Sixth Working Group, April 2020 • 75% Design Public Meeting, February 2021

Working Group Meeting #2 67

Page 68: Grand Junction Multi-use Path Design Working Group Meeting ......GRAND JUNCTION MULTI-USE PATH DESIGN PROJECT WORKING GROUP #2 - JULY 22, 2019 Working Group Meeting #2 1 . MEETING

Next Steps

PROJECT WEBSITE

The online website will be one important venue for providing input:

Most recent updates

Much historical information

Will document this Design Working Group Process

Opportunity to comment

What is most useful for you?

CambridgeMA.gov/GrandJunction

Working Group Meeting #2 68

Page 69: Grand Junction Multi-use Path Design Working Group Meeting ......GRAND JUNCTION MULTI-USE PATH DESIGN PROJECT WORKING GROUP #2 - JULY 22, 2019 Working Group Meeting #2 1 . MEETING

THANK YOU Tegin Teich, Transportation Planner

Cambridge Community Development Department [email protected]

(617) 349-4615

Working Group Meeting #2 69