EHS-GBP-05 GBF-09
APPLICABILITY
This booklet comprises the checklists for various elements of the green building regulations and is meant to be used by the stakeholders concerned for providing accurate information on the project. It comprises the following parts
Part-1 Project Summary
Part-2 Checklist for Green Building Submission
Part-3 Green Building Compliance Statement
Part-4 Envelope Commitment Sheet
Part-5 AC System Compliance Sheet
DisclaimerThis checklist has been developed for project teams to use when compiling the submission documentation for EHS Review / Assessment
A completed version of this checklist must be included within the Main Submission.
The accuracy and completeness of the submission is entirely the responsibility of the project team. EHS will not be held accountable for incorrect or incomplete submissions sent for assessment.
Revision: 00 July 2015 Page 1 of 14
SUBMISSION
BOOKLETRegulation : GB 8. Green Building Regulations-Villas & Residential Developments up to 3 habitable
Floors
Procedure : EHS-GBP-09 Procedure for NOC-BP Green Building Submission (Villas)
Phase : NOC-BP
EHS-GBP-05 GBF-09
PART-1
PROJECT SUMMARY
Project Name:Click here to enter text. GB Consultant: Click here to enter text.
Plot No: Click here to enter text. Commissioning: Click here to enter text. specialist
Project: Click here to enter text. Engineer of: Click here to enter text.description record
Project Contact Name: Click here to enter text.
Contact E-Mail: Click here to enter text.
I, the Project Contact, hereby confirm that:
a. I have reviewed the submission checklist and the contents therein and ascertained that they align with the main submission package provided to EHS
b. I understand that EHS reserve the right to not assess a submission that is inconsistent with the Regulations, submission procedures and the guidelines
c. I take complete responsibility for the accuracy and completeness of the submission.
Name: Click here to enter text.
Signature: Date: Click here to enter text.
Revision: 00 July 2015 Page 2 of 14
EHS-GBP-05 GBF-09
PART- 2
CHECKLIST FOR GREEN BUILDING SUBMISSION [NOC-BP]Project Name: Click here to enter text.
S.NO DOCUMENT DETAILS ATTACHED(Yes / No) REMARKS
1 Proof of Payment of Green Building Review Fee
2 A detailed Green Building Project plan with detailed strategy for complying with the credits targeted for the project.
3 Supporting documents for “ Category A-General Requirements” as highlighted under the section “Evidence Required at Design Stage” of Regulation GB-8
4 Supporting documents for “ Category B-Envelope & Energy” as highlighted under the section “Evidence Required at Design Stage of Regulation GB-8
5 Supporting documents for “Category C-Lighting” as highlighted under the section “Evidence Required at Design Stage of Regulation GB-8
6 Supporting documents for “Category D- Control Systems” as highlighted under the section “Evidence Required at Design Stage of Regulation GB-8
7 Supporting documents for “Category E- Water” as highlighted under the section “Evidence Required at Design Stage of Regulation GB-8
8Supporting documents for “Category F- Environment & Internal Air Quality” as highlighted under the section “Evidence Required at Design Stage of Regulation GB-8
9 Supporting documents for “Category G- Sustainable Site” as highlighted under the section “Evidence Required at Design Stage of Regulation GB-8
Revision: 00 July 2015 Page 3 of 14
EHS-GBP-05 GBF-09
S.NO DOCUMENT DETAILS ATTACHED(Yes / No) REMARKS
10Supporting documents for “Category H- Operational Sustainability” as highlighted under the section “Evidence Required at Design Stage of Regulation GB-8
11 Justification for Non Compliance to any specific credit (if any)
12Have you completed the Accreditation “Regulatory Awareness” on Green Buildings?Have you attached the certificate?
Notes
1) The above check-list should be filled up in a professional manner devoid of inconsistencies2) It should be ensured that ONLY the latest / most recent version of the forms as reflected in the portal are used for the
submissions. Forms bearing the earlier revisions or those that have been superseded will not be accepted.
Revision: 00 July 2015 Page 4 of 14
EHS-GBP-05 GBF-09
PART- 3
GREEN BUILDING COMPLIANCE STATEMENT [NOC-BP]Project Name: Click here to enter text.
ITEMDESCRIPTION
TY
PE COMPLIANCE REQUIREMENTCOMPLIE
DYes / No
LIST OF SUPPORTING DOCUMENTS ATTACHED.
A: General Requirements
1
Integrated Design Approach for achieving energy savings
M AS HIGHLIGHTED IN SECTION A1 OF THE REGULATION GB-8
2
Post Contract Green Briefing.Sustainability Kick-off
M AS HIGHLIGHTED IN SECTION A2 OF THE REGULATION GB-8
B: Envelope and Energy
1
Compliance with Thermal Insulation System and Best Practices Energy conservation methods
M AS HIGHLIGHTED IN SECTION B1 OF THE REGULATION GB-8
2 LIMITING / M AS HIGHLIGHTED IN SECTION B2 OF THE
Revision: 00 July 2015 Page 5 of 14
1. This form has to be filled up after thorough understanding of the Regulation and incorporating them into the design 2. Supporting documents demonstrating compliance should be attached under separate folders as part of submission.3. This should be in line with "Evidence Required at Construction Stage NOC-BCC" of the Regulation GB-8.0
EHS-GBP-05 GBF-09
ITEMDESCRIPTION
TY
PE COMPLIANCE REQUIREMENTCOMPLIE
DYes / No
LIST OF SUPPORTING DOCUMENTS ATTACHED.
REVERSING THERMAL BRIDGES
REGULATION GB-8
3
Envelope Tightness (Prescriptive based) THERMAL IMAGING TECHNIQUE
M AS HIGHLIGHTED IN SECTION B3 OF THE REGULATION GB-8
4
Envelope Tightness (Performance based)BLOWER DOOR TEST TECHNIQUE
V AS HIGHLIGHTED IN SECTION B4 OF THE REGULATION GB-8
5 Efficient SIZING of the HVAC systems M AS HIGHLIGHTED IN SECTION B5 OF THE
REGULATION GB-8
6
Central air conditioning units equipped with Energy Recovery Units and regulated air intake system (Where Applicable)
M AS HIGHLIGHTED IN SECTION B6 OF THE REGULATION GB-8
7
Selection of A/C unit with HIGH Energy Efficiency Ratio (EER)
M AS HIGHLIGHTED IN SECTION B7 OF THE REGULATION GB-8
8Energy Efficient Auxiliary Systems of HVAC systems-
NOT APPLICABLE
Revision: 00 July 2015 Page 6 of 14
EHS-GBP-05 GBF-09
ITEMDESCRIPTION
TY
PE COMPLIANCE REQUIREMENTCOMPLIE
DYes / No
LIST OF SUPPORTING DOCUMENTS ATTACHED.
9 INTERIOR LIGHTING LEVELS M AS HIGHLIGHTED IN SECTION B9 OF THE
REGULATION GB-8
10 EXTERIOR LIGHTING LEVELS M AS HIGHLIGHTED IN SECTION B10 OF THE
REGULATION GB-8
11Use of Renewable sources of energy for domestic heating
MAS HIGHLIGHTED IN SECTION B11 OF THE REGULATION GB-8
12Use of Renewable sources of energy for power
V AS HIGHLIGHTED IN SECTION B12 OF THE REGULATION GB-8
13 Energy Sub Metering M AS HIGHLIGHTED IN SECTION B13 OF THE REGULATION GB-8
14 COMMISSIONING M AS HIGHLIGHTED IN SECTION B14 OF THE REGULATION GB-8
15 FOR AIR-CONDITIONED SPACESMORE THAN 2000 SQ.M
M AS HIGHLIGHTED IN SECTION B16 OF THE REGULATION GB-8
BUILDING ENERGY SIMULATIONENERGY
Revision: 00 July 2015 Page 7 of 14
EHS-GBP-05 GBF-09
ITEMDESCRIPTION
TY
PE COMPLIANCE REQUIREMENTCOMPLIE
DYes / No
LIST OF SUPPORTING DOCUMENTS ATTACHED.
MODELING
16
FOR AIR-CONDITIONED SPACESMORE THAN 2000 SQ.M M AS HIGHLIGHTED IN SECTION B16 OF THE
REGULATION GB-8
INDEPENDENT COMMISSIONING AGENT
C: Lighting
1Daylight Strategy
V AS HIGHLIGHTED IN SECTION C1 OF THE REGULATION GB-8
Use of Day lighting Technologies
2Usage of energy saving high performance lamps
M AS HIGHLIGHTED IN SECTION C2 OF THE REGULATION GB-8
3 Usage of Electronic Ballast M AS HIGHLIGHTED IN SECTION C3 OF THE
REGULATION GB-8
D: Control Systems
1Use of programmable thermostats for HVAC system
M AS HIGHLIGHTED IN SECTION D1 OF THE REGULATION GB-8
Revision: 00 July 2015 Page 8 of 14
EHS-GBP-05 GBF-09
ITEMDESCRIPTION
TY
PE COMPLIANCE REQUIREMENTCOMPLIE
DYes / No
LIST OF SUPPORTING DOCUMENTS ATTACHED.
2 Control of External lights M
AS HIGHLIGHTED IN SECTION D2 OF THE REGULATION GB-8
3 Interlock of Toilet / Bathroom fans M
AS HIGHLIGHTED IN SECTION D3 OF THE REGULATION GB-8
4
Use of Occupancy Sensor / Motion Sensor for internal lighting devices
M AS HIGHLIGHTED IN SECTION D4 OF THE REGULATION GB-8
E: Water
1
Usage of Sewage Treatment Plant (STP) for treating Grey Water and reuse of treated water in flushing toilets and other usage not involving human direct contact.
V NOT APPLICABLE
2
Performance Requirements for Sanitary fittings (Low Flow / Low Flush Fittings)
M AS HIGHLIGHTED IN SECTION E2 OF THE REGULATION GB-8
3 Water efficient landscaping and
M AS HIGHLIGHTED IN SECTION E3 OF THE REGULATION GB-8
Revision: 00 July 2015 Page 9 of 14
EHS-GBP-05 GBF-09
ITEMDESCRIPTION
TY
PE COMPLIANCE REQUIREMENTCOMPLIE
DYes / No
LIST OF SUPPORTING DOCUMENTS ATTACHED.
irrigation systemsDrip irrigation methods for vegetation according to climate and seasonal conditions.
4
Water efficient landscaping and irrigation systemsEliminate potable water use or irrigation
V
AS HIGHLIGHTED IN SECTION E4 OF THE REGULATION GB-8
F: Environment and Internal Air Quality
1
Building internal ventilation and Minimum Indoor Air Quality (IAQ)
M AS HIGHLIGHTED IN SECTION F1 OF THE REGULATION GB-8
2 THIS SPACE HAS BEEN INTENTIONALLY LEFT BLANK
3Low Emitting Paints, Coatings, Adhesives and Sealants
M AS HIGHLIGHTED IN SECTION F3 OF THE REGULATION GB-8
4
Usage of Ozone friendly materials in Air Conditioning equipment, thermal insulation, foam & fire fighting equipment.
M AS HIGHLIGHTED IN SECTION F4 OF THE REGULATION GB-8
Revision: 00 July 2015 Page 10 of 14
EHS-GBP-05 GBF-09
ITEMDESCRIPTION
TY
PE COMPLIANCE REQUIREMENTCOMPLIE
DYes / No
LIST OF SUPPORTING DOCUMENTS ATTACHED.
G: Sustainable Site & Management
1 Sustainable Site and Management M AS HIGHLIGHTED IN SECTION G1 OF THE
REGULATION GB-8
2 Heat Island Effect Non-Roof M AS HIGHLIGHTED IN SECTION G2 OF THE
REGULATION GB-8.
3
Heat Island Effect Roof (Use of light and heat reflective colours on roofs)
M AS HIGHLIGHTED IN SECTION G3 OF THE REGULATION GB-8
H: Operational Sustainability
1
Recycling facility -Storage and collection of Recyclables
M AS HIGHLIGHTED IN SECTION H1 OF THE REGULATION GB-8
2 Energy Efficient Eqt. (White Goods) M AS HIGHLIGHTED IN SECTION GH2 OF THE
REGULATION GB-8
3 Building user Guide M AS HIGHLIGHTED IN SECTION H3 OF THE REGULATION GB-8
4 Facility / Building Services Tuning V AS HIGHLIGHTED IN SECTION H4 OF THE
REGULATION GB-8
Revision: 00 July 2015 Page 11 of 14
EHS-GBP-05 GBF-09
PART- 4
ENVELOPE COMMITMENT SHEET [NOC-BP]
Project Name: Click here to enter text.
BUILDING ELEMENT PARAMETER REQUIREMENTS ENVELOPE DATA (DESIGN)
External Walls U – value (Max)0.05 Btu/hr-ft2-⁰f
0.28 W/m2-⁰c
Roof U – value (Max)0.045 Btu/hr-ft2-⁰f
0.2555W/m2-⁰c
Floors U – value (Max)0.1 Btu/hr-ft2-⁰f
0.57 W/m2-⁰c
Glass(Window-wall ratio < 30%)
U – value (Max)0.37 Btu/hr-ft2-⁰f
2.1 W/m2-⁰c
Shading Coefficient (Max)
SHGC (Max)
0.290.252
VLT (Min) 25 %
Revision: 00 July 2015 Page 12 of 14
EHS-GBP-05 GBF-09
BUILDING ELEMENT PARAMETER REQUIREMENTS ENVELOPE DATA (DESIGN)
Glass(Window-wall ratio > 30%)
U – value (Max)0.335 Btu/hr-ft2-⁰f
1.9 W/m2-⁰c
Shading Coefficient (Max)
SHGC (Max)
0.240.209
VLT (Min) 11 %
Glass(for skylights architecture)
U – value (Max)0.335 Btu/hr-ft2-⁰f
1.9 W/m2-⁰c
Shading Coefficient (Max)
SHGC (Max)
0.200.174
VLT (Min) 40 %
Note
1. The envelope values mentioned above should be supported by appropriate calculations 2. It is important to adhere to these values by ensuring proper controls during the construction phase of the project
PART- 5
Revision: 00 July 2015 Page 13 of 14
EHS-GBP-05 GBF-09
AC SYSTEM COMPLIANCE SHEET [NOC-BP]
Project Name: Click here to enter text.
S.NoSpace / Area being Air-conditioned
Design calculationProposed SystemEER
as per EHS Regulation
EERConsidered in
Design
Cooling load (TR)
AirQuantity
Cooling load (TR)
AirQuantity
1
2
3
4
5
6
7
Notes1. The table should be followed for demonstrating compliance to
a. B5 – Efficient Sizing of HVAC systemsb. B7 - Selection of A/C unit with Energy Efficiency Ratio (EER)
2. This table is applicable to all conditioned areas including cases where a single AC unit is catering to multiple spaces and cases
where a single space is being catered by multiple units3. It should be ensured that ONLY the latest / most recent version of the forms as reflected in the portal are used for the
submissions. Forms bearing the earlier revisions or those that have been superseded will not be accepted
Revision: 00 July 2015 Page 14 of 14
Top Related