GROUP No. 3 Members:Team Leader: Agnes, Jelyn A. Bi-Monthly Report of Group No. - (GANTT CHART) 1. Briones, JunreyAsst. Team Leader: Go, Nixon

DESIGN TITLE: Cassava Grater Machine

2. Blanco, RommelSecretary: Gabito, Jan Dhale 3. Canete, Kevin

4. Debalucos, Sotero 5. Marabulas, Jhonrey

6.Sarande, Kenneth

No. ActivitiesActual Results

DECEMBER JANUARY FEBRUARY MARCH Persons Involved RemarksWeek# Week# Week# Week#

1 I. Group Dynamic 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4

Group

d. Selection of design that links in mechanical engineering works.

2. Making Plans / Preparation for Subsequent Events

Group a. Gather information of the design studyb. Materials Selection and Costing c. Data gathering procedures&techniques.

3. Working on project design

a. Sketching and Draftingb. Assembly&detail Component drawing Secretary c. Exploded view All Members

4. Encoding and Editing documentationLeader, Asst.leader

a. Introductionb. Definition of component partsc. Summary, Conclusion&Recommendations

5. Design EvaluationLeader&asst. leader

6. Submission of proposed Project

Legend: Target Date : Actual Date :

1. Brainstorming(Planning&Design Selection)

a. Members assigned to research problem & design.

b. Individually presented a design&discussed its applications.

c. Sharing of opinions in which study will be useful&acceptable.