Proposed minor mineral Mining Project (ML Area: 55.50 ha) Production of Stone along with Associated Minor minerals 15 MTPA
At Village – Dadam, Tehsil –Tosham , District– Bhiwani (Haryana)
Form - I / Appendix – I
M/s. Sunder Marketing Associates 1
APPENDIX I
(See paragraph – 6)
FORM 1
(I) Basic Information
S. No. Item Details
1. Name of the project/s Proposed minor mineral Mining Project (ML Area: 55.50
ha) Production of Stone along with Associated Minor
minerals 15 MTPA.
2. S. No. in the schedule As per EIA Notification dated 14.09.2006 and as amended from time to time, this project falls under Category A , Project or Activity 1(a) – (3).
3. Proposed
capacity/area/length/tonnage
handled/ command
area/lease/number of wells to be
drilled
Area: 55.50 ha
Production capacity: 15 MTPA
4. New/Expansion /Modernization Modernization (Amendment in name of E.C from M/s
KJSL-Sunder (JV) to M/S Sunder Marketing Associates )
5. Existing Capacity /Area etc. 15 MTPA
6. Category of Project i.e.' A' or 'B' Category A
7. Does it attract the general
condition? If yes, please specify.
No, it does not attract the general condition.
8. Does it attract the specific condition?
If yes, please specify.
No, it does not attract the specific condition.
9. Location
10. Plot/Survey/Khasra No 132 (Min.), 133
11. Villages Dadam
12. Tehsil Tosham
13. District Bhiwani
14. State Haryana
15. Nearest railway station/airport
along with distance in kms
Nearest Railway Station: Bawani Khera Railway
station (~18 km in NE direction).
Nearest Airport: Indira Gandhi International Airport,
Proposed minor mineral Mining Project (ML Area: 55.50 ha) Production of Stone along with Associated Minor minerals 15 MTPA
At Village – Dadam, Tehsil –Tosham , District– Bhiwani (Haryana)
Form - I / Appendix – I
M/s. Sunder Marketing Associates 2
New Delhi (~127 km in ESE direction)
16. Nearest Town, city, District Head
quarters along with distance in
kms.
Nearest Town:- Tosham (~ 6.0 km In ESE direction).
Nearest City & District Headquarter: - Bhiwani (~30.0
km in SE direction).
17. Village Panchayats, Zilla Parishad,
Municipal Corporation, Local body
(complete postal addresses with
telephone nos. to be given)
Gram Panchayat Dadam, Tehsil: Tosham, District: Bhiwani
(Haryana).
18. Name of the applicant M/s Sunder Marketing Associates
19. Registered Address M/s Sunder Marketing Associates, 702, Pearls Business
Park, Netaji Subhash Palace, Pitampura
Delhi – 110034
20. Address for correspondence Project Proponent EIA Consultant
21. Name Naveen Goel N/A
22. Designation (Owner/ Partner/
CEO)
Proprietor N/A
23. Address M/s Sunder Marketing
Associates, 702, Pearls
Business Park, Netaji Subhash
Palace, Pitampura
Delhi.
N/A
24. Pin Code 110034 N/A
25. E-mail [email protected] N/A
26. Telephone No 9999666911 N/A
Fax No - N/A
27. Details of Alternative Sites
examined, if any. Location of these
sites should be shown on a topo
sheet.
No alternative site has been examined since it is a site
specific mining project based on availability of mineral
potentiality in the area. E.C for the said site is issued dated
03/07/15 on the name of M/S KJSL-Sunder(JV), but now
the Mining department has allowed for the transfer of
Mining Lease from M/s KJSL- Sunder (JV) to M/s Sunder
Marketing Associates through letter no.
Proposed minor mineral Mining Project (ML Area: 55.50 ha) Production of Stone along with Associated Minor minerals 15 MTPA
At Village – Dadam, Tehsil –Tosham , District– Bhiwani (Haryana)
Form - I / Appendix – I
M/s. Sunder Marketing Associates 3
DMG/HY/ML/Dadam/2013/7024 dated 16/07/2015, by
the Director General, Mines and Geology Department
Haryana.
28. Interlinked Projects No interlinked projects
29. Whether separate application of
interlinked project has been
submitted?
Not Applicable
30. If yes, date of submission Not applicable
31. If no, reason Not applicable.
32. Whether the proposal involves
approval/ clearance under: if yes,
details of the same and their status
to be given.
(a) The Forest (Conservation) Act
1980?
(b) The Wildlife (Protection) Act
1972?
(c) The C.R.Z Notification. 1991?
Not applicable.
33. Whether there is any Government
Order/ Policy relevant/ relating to
the site?
No
34. Forest land involved (hectares) No Forest land is involved in the lease area.
35. Whether there is any litigation
pending against the project and/ or
land in which the project is
proposed to be set-up.
(a) Name of the Court
(b) Case No
(c) Orders/ Directions of the court,
If any and its relevance with the
proposed project
No litigation is pending.
Proposed minor mineral Mining Project (ML Area: 55.50 ha) Production of Stone along with Associated Minor minerals 15 MTPA
At Village – Dadam, Tehsil –Tosham , District– Bhiwani (Haryana)
Form - I / Appendix – I
M/s. Sunder Marketing Associates 4
(II) Activity
1. Construction, operation or decommissioning of the Project involving actions, which will
cause physical changes in the locality (topography, land use, changes in water bodies, etc.)
S. No Information/Checklist
confirmation
Yes
/No
Details thereof (with approximate
quantities/rates, wherever possible) with
source of information data
1.1 Permanent or temporary
change in land use, land cover
or topography including increase
in intensity of land use (with
respect to local land use plan)
Yes Total Mining area is 55.50 ha. It is Govt. land (as per
revenue record)
The topography of the area is hilly and having sharp
slopes. There will be a permanent change of land
use of mining activity area. The mining activity will
leave excavated area which will be converted into
reservoir.
Dense green belt/plantation will be developed along
the lease boundary, near mine office etc.
1.2 Clearance of existing land,
vegetation and buildings?
Yes There is no building & structure which need to be
demolished/ removed from mining lease area
except some shrubs existing on the lease area which
will be cleared when required
1.3 Creation of new land uses? Yes Mining activity will involve excavation of the area,
which will be converted into water reservoir.
Dense green belt/plantation will be developed along
the lease boundary, haul roads, around mine office
etc.
1.4 Pre-construction investigations e.g.
bore houses, soil testing?
Yes Pre-construction investigations like Exploratory
Drilling has already been carried out and found
satisfactory.
1.5 Construction works? Yes Being a mining project it requires very little
construction work.
1.6 Demolition works? No No demolition work shall be there.
1.7 Temporary sites used for
construction works or housing of
construction workers?
No As the project involves only minor construction of
mines office, haul roads thus there is no need of
temporary sites for housing of construction
Proposed minor mineral Mining Project (ML Area: 55.50 ha) Production of Stone along with Associated Minor minerals 15 MTPA
At Village – Dadam, Tehsil –Tosham , District– Bhiwani (Haryana)
Form - I / Appendix – I
M/s. Sunder Marketing Associates 5
workers.
Local Laborers will be employed on need basis from
the nearby villages. Amenities / Facilities will be
provided to construction workers.
1.8 Above ground buildings, structures
or earthworks including linear
structures, cut and fill or
excavations.
Yes There will be excavation, cut and fill during
construction of mines office, within the mining lease
area. Excavation during mining operation will be
carried out. Voids will be formed by excavation of
mineral.
1.9 Underground works including
mining or tunneling?
No No underground works including mining or
tunneling is required.
1.10 Reclamation works? Yes There will be a permanent change of land use of
mining activity area. The mining activity will leave
excavated area which will be converted into
reservoir.
Dense green belt/plantation will be developed along
the lease boundary, near mine office etc.
1.11 Dredging? No There will be no dredging.
1.12 Offshore structures? No There are no offshore structures.
1.13 Production and manufacturing
processes?
Yes The mining operations will be by mechanized
opencast method which include blasting, excavation,
sorting of mineral & transportation by trucks to the
existing crushers.
1.14 Facilities for storage of goods or
materials?
Yes Facilities will be required for storage of goods and
materials as per mining plan.
1.15 Facilities for treatment or
disposal of solid waste or liquid
effluents?
Yes No OB Waste will be generated.
Small quantities of liquid effluent will be
generated from the workshop, which will be
treated by oil water separator. And waste water
generated from mine office (Drinking, office
toilets etc.) will be disposed off via soak pit/
septic tank.
1.16 Facilities for long term housing of No Permanent workers and staff members will be
Proposed minor mineral Mining Project (ML Area: 55.50 ha) Production of Stone along with Associated Minor minerals 15 MTPA
At Village – Dadam, Tehsil –Tosham , District– Bhiwani (Haryana)
Form - I / Appendix – I
M/s. Sunder Marketing Associates 6
operational workers? mostly residents of nearby villages. Thus, no land
will be used for residential purposes within mining
area. Technical supervisors will be provided
accommodations in nearby village close to the area
1.17 New road, rail or sea traffic during
construction or operation?
No No new road, rail or sea traffic will be required
during construction or operation of the proposed
mining project.
Haul roads and other internal roads will be
constructed within mining lease area for raw
material transport. Existing road network will be
used for transporting stone.
1.18 New road, rail, air waterborne or
other transport infrastructure
including new or altered routes
and stations, ports, airports etc?
No No new road, rail, air, waterborne or other
transport infrastructure including new or altered
routes and stations, ports, airports, etc will be
required.
1.19 Closure or diversion of existing
transport routes or infrastructure
leading to changes in traffic
movements?
No Closure or diversion of existing transport routes or
infrastructure leading to changes in traffic
movements is not involved.
1.20 New or diverted transmission
lines or pipelines?
No No new or diverted transmission lines or pipelines
are proposed.
1.21 Impoundment, damming,
culverting, realignment or other
changes to the hydrology of
watercourses or aquifers?
No There will be no impoundment, damming,
culverting, realignment or other changes to the
hydrology of watercourses or aquifers.
1.22 Stream crossings? No There is no stream crossing through the mine site.
1.23 Abstraction or transfers of water
from ground or surface waters?
Yes The total water requirement for mining project is
estimated 100 KLD. Water for dust suppression,
Green belt, and drinking water will be used from
nearby villages. C.G.W.B has given us the permission
for that.
1.24 Changes in water bodies or the No There is no surface water body within in the Lease
Proposed minor mineral Mining Project (ML Area: 55.50 ha) Production of Stone along with Associated Minor minerals 15 MTPA
At Village – Dadam, Tehsil –Tosham , District– Bhiwani (Haryana)
Form - I / Appendix – I
M/s. Sunder Marketing Associates 7
land surface affecting drainage or
run-off?
area. There will be no change in water bodies during
mining operation. There will be a permanent change
of land use of mining activity area. The mining
activity will leave excavated area, which will be
converted into reservoir.
Dense green belt/plantation will be developed along
the lease boundary, near mine office etc.
1.25 Transport of personnel or
materials for construction,
operation or decommissioning?
Yes Mine workers are residing in nearby area hence
does not require any transport. Materials will be
transported by trucks.
1.26 Long-term dismantling or
decommissioning or restoration
works?
No No long-term dismantling or decommissioning or
restoration works is required.
1.27 Ongoing activity during
decommissioning which could
have an impact on the
environment?
No Not applicable, as no such activities are involved.
1.28 Influx of people to an area in
either temporarily or
permanently?
Yes Manpower will be sourced from nearby villages so
there will be influx of people to the area.
1.29 Introduction of alien species? No No, there is no possible source for transportation of
alien species by transport of mineral as the stone
will be transported to the nearby areas.
1.30 Loss of native species or genetic
diversity?
No There will be no loss of native species or genetic
diversity.
1.31 Any other actions? No Not Applicable
Proposed minor mineral Mining Project (ML Area: 55.50 ha) Production of Stone along with Associated Minor minerals 15 MTPA
At Village – Dadam, Tehsil –Tosham , District– Bhiwani (Haryana)
Form - I / Appendix – I
M/s. Sunder Marketing Associates 8
2. Use of Natural resources for construction or operation of the Project (such as land, water,
materials or energy, especially any resources which are non-renewable or in short supply):
S.
No.
Information/checklist
confirmation
Yes/No Details thereof (with approximate
quantities/rates, wherever possible) with
source of information data
2.1 Land especially undeveloped or
agricultural land (ha)
Yes Total Mining area is 55.50 ha. It is total Govt. Land.
The mining area is completely barren.
2.2 Water (expected source &
competing users) unit: KLD
Yes The total water requirement for mining project is
estimated 100 KLD. Water for dust suppression,
Green belt, will be sourced from nearby villages.
C.G.W.B has given us the permission for the same.
2.3 Minerals (MT) Yes 15 MTPA Stone along with Associated Minor
minerals shall be mined and used for Construction
material.
2.4 Construction material – stone,
aggregates, sand/soil (expected
source – MT)
Yes Construction material as available locally will be
used for construction of mine office, workshop &
haul roads.
2.5 Forests and timber (source – MT) No No forests and timber is required.
2.6 Energy including electricity and
fuels (source, competing users)
Unit: fuel (MT), energy (MW)
Yes Electricity will be obtained from Haryana
Electricity Board.
Fuel: Diesel will be used every day for machinery.
2.7 Any other natural resources (use
appropriate standard units)
No Not applicable, as there will not be use of any other
natural resources.
3. Use, storage, transport, handling or production of substances or materials, which could be
harmful to human health or the environment or raise concerns about actual or perceived
risks to human health.
S. No. Information/Checklist
confirmation
Yes
/No
Details thereof (with approximate
quantities/rates, wherever possible) with
source of information data
3.1 Use of substances or materials,
which are hazardous (as per
MSIHC rules) to human health or
the environment (flora, fauna, and
water supplies)
No Explosives, used for blasting, will be stored in
mines magazine. Safety will be ensured and
eco-friendly blasting will be practiced, the
entire blasting operations will be carried out as
per provisions of MMR, 1961 and Indian
Explosives Act and Rules. MSDS will be
Proposed minor mineral Mining Project (ML Area: 55.50 ha) Production of Stone along with Associated Minor minerals 15 MTPA
At Village – Dadam, Tehsil –Tosham , District– Bhiwani (Haryana)
Form - I / Appendix – I
M/s. Sunder Marketing Associates 9
maintained and followed to avoid any error.
3.2 Changes in occurrence of disease
or affect disease vectors (e.g.
insect or water borne diseases)
No No effect envisaged due to this mining project.
Services of a Mobile dispensary will be
provided to locals of project surrounding area
to improve their health status.
3.3 Affect the welfare of people e.g. by
changing living conditions?
Yes There will be positive impact of the project in
the area as follows :
Providing better employment opportunities,
both direct and indirect, this will enhance
the living standards and economic status of
the local people.
Communication and transport facilities will
be improved
Education facilities will be improved.
Community Health care programmes will
provide better health and medical facilities
not only to the employees but also to
villagers.
3.4 Vulnerable groups of people who
could be affected by the project
e.g. hospital patients, children, the
elderly etc.,
No No effect envisaged.
3.5 Any other causes No None.
4. Production of solid wastes during construction or operation or decommissioning
(MT/month)
S. No. Information/Checklist
confirmation
Yes
/No
Details thereof (with approximate
quantities/rates, wherever possible) with
source of information data
4.1 Spoil, overburden or mine wastes No No OB Waste will be generated.
Top soil where ever available will be carefully
removed and stored (with vegetation cover) and
simultaneously used for green belt
development.
4.2 Municipal waste (domestic and or
commercial wastes)
Yes Only domestic waste will be generated from the
mines office which will be properly disposed off.
Proposed minor mineral Mining Project (ML Area: 55.50 ha) Production of Stone along with Associated Minor minerals 15 MTPA
At Village – Dadam, Tehsil –Tosham , District– Bhiwani (Haryana)
Form - I / Appendix – I
M/s. Sunder Marketing Associates 10
4.3 Hazardous wastes (as per
Hazardous Waste Management
Rules)
Yes Small quantities of oil and grease will be
generated, which will be disposed off via
authorized recyclers.
4.4 Other industrial process wastes No There will be no other industrial process waste
generation.
4.5 Surplus product No There will not be any surplus product.
4.6 Sewage sludge or other sludge
from effluent treatment
No Domestic waste water generated from mine
office will be disposed in soak pits via septic
tank.
4.7 Construction or demolition wastes No No construction waste will be generated.
4.8 Redundant machinery/ equipment No There will be no redundant machinery or
equipment.
4.9 Contaminated soils or other
materials
No There is no contamination of soil or any other
materials.
4.10 Agricultural wastes No There will not be any agricultural wastes
4.11 Other solid wastes Yes There will be very minor scrap from stores/
Office during the operational phase of the mine.
5. Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/hr)
S.
No.
Information/Checklist
confirmation
Yes/
No
Details thereof (with approximate
quantities/rates, wherever possible) with
source of information data
5.1 Emissions from combustion of
fossil fuels from stationary or
mobile sources
Yes The emission of SO2 & NO2 may be due to use of
diesel operated surface miners/Loader/dumper
etc. Vehicular emission will be kept under
control by proper maintenance and by regular
monitoring of fuel and oil consumption of Heavy
Earth Moving equipment as well as auxiliary
equipments. Every effort will be made to
minimize emissions.
5.2 Emissions from production
process
Yes There will be fugitive and gaseous emissions
from HEMMs during excavation of stone.
5.3 Emissions from materials handling
including storage or transport
Yes The loading of material and transportation will
emit some amount of pollutants. Proper
maintenance of HEMMs will help reduce
emissions. The fugitive emission on haul road
Proposed minor mineral Mining Project (ML Area: 55.50 ha) Production of Stone along with Associated Minor minerals 15 MTPA
At Village – Dadam, Tehsil –Tosham , District– Bhiwani (Haryana)
Form - I / Appendix – I
M/s. Sunder Marketing Associates 11
will be suppressed by water spray.
5.4 Emissions from construction
activity including plant &
equipment
Yes Fugitive dust emissions may be generated due
to vehicular movement. These emissions will be
temporary and will be controlled.
5.5 Dust or odours from handling of
materials including construction
materials, sewage and waste
Yes Dust which is generated during excavation,
loading/unloading & transportation will be
suppressed by the sprinkling the water.
5.6 Emission from incineration of
waste
No Incineration activity is not involved in the
project.
5.7 Emissions from burning of waste
in open air (e.g. slash
materials, construction debris)
No There is no burning of waste in open air.
5.8 Emissions from any other sources No There will be no emissions from any other
sources.
6. Generation of Noise and Vibration and Emissions of Light and heat:
S. No. Information/Checklist
confirmation
Yes/
No
Details thereof (with approximate
quantities/rates, wherever possible) with
source of information data with source of
information data
6.1 From operation of equipment e.g.
engines, ventilation plant,
crushers.
Yes There is likelihood of some increase in noise due
to operation of machinery like surface miner,
hydraulic excavators, and loaders at source.
However persons working just close to machine
will be provided with Ear plugs / Ear muffs for
further protection. There will not be continuous
exposure of operators to high noise areas.
All the new HEMMs will be equipped with noise
insulated cabins and all the machines having
acoustic enclosures will only be procured.
Greenbelt will be developed which minimizes
noise level.
6.2 From industrial or similar process No There is no other industrial process.
6.3 From construction or demolition Yes The noise generated from construction will be
temporary in nature.
6.4 From blasting or pilling Yes Generation of Noise and Vibration will be there
Proposed minor mineral Mining Project (ML Area: 55.50 ha) Production of Stone along with Associated Minor minerals 15 MTPA
At Village – Dadam, Tehsil –Tosham , District– Bhiwani (Haryana)
Form - I / Appendix – I
M/s. Sunder Marketing Associates 12
due to drilling & blasting. This will be minimized
by taking precautionary measures such as proper
blasting method, selection of explosive and
quantity of explosive etc.
Green belt all around the mining area serves as
noise barrier.
Workers working in close vicinity of machines
will be provided with personal protective
equipments, etc.
6.5 From construction or operational
traffic
Yes During vehicular movement, the noise is likely to
be high, which is intermittent process. All the
HEMMs are equipped with noise insulated cabins
with very less noise inside the cabin having
acoustic enclosures be procured.
Noise during construction activities will be
temporary & will be resolved.
6.6 From lighting or cooling systems No Not envisaged
6.7 From any other sources No Not envisaged
7. Risks of contamination of land or water from releases of pollutants into the ground or into
sewers, surface waters, groundwater, coastal waters or the sea:
S. No. Information/Checklist
confirmation
Yes/
No
Details thereof (with approximate
quantities/rates, wherever possible) with
source of information data
7.1 From handling, storage, use
or spillage of hazardous
materials
No No use/handling of hazardous material will take
place except periodical oil change, which will be
handled in closed containers. Spillage of
Oil/Grease during maintenance of heavy
vehicles will be controlled by using collection
tray etc. Care will be taken during its use for
lubrication of equipment, so that nothing falls
on ground to contaminate soil. Equipment will
be kept well maintained to keep them leakage
free. The used oil and grease will be sold to
authorized vendors.
7.2 From discharge of sewage or
other effluents to water or the
Yes Domestic waste water generated from mine
office will be disposed in soak pits via septic
Proposed minor mineral Mining Project (ML Area: 55.50 ha) Production of Stone along with Associated Minor minerals 15 MTPA
At Village – Dadam, Tehsil –Tosham , District– Bhiwani (Haryana)
Form - I / Appendix – I
M/s. Sunder Marketing Associates 13
land (expected mode and place of
discharge).
tank.
7.3 By deposition of pollutants
emitted to air into the land or
into water.
No No deposition of pollutants emitted to air, into
the land or into water will take place; as the
emissions are limited to the site itself which will
be mitigated by regular water sprinkling for
dust suppression.
Regular/periodical Ambient Air Quality
Monitoring will be carried out.
7.4 From any other sources. No Not envisaged
7.5 Is there a risk of long term build
up of pollutants in the
environment from these
sources?
No Risk of long term build up of pollutants in the
environment from these sources is not
envisaged.
8. Risk of accidents during construction or operation of the Project, which could affect
human health or the environment
S.
No.
Information/Checklist
confirmation
Yes/
No
Details thereof (with approximate
quantities/rates, wherever possible) with
source of information data
8.1 From explosions, spillages, fires etc
from storage, handling, use or
production of hazardous
substances
No Possibility of accident on account of explosion,
spillages, fire or hazardous substances etc is
very less or negligible. Proper maintenance,
operation and leak proof condition of machinery
eliminates possibilities of fire.
However fire extinguishers will be provided
near workshop, mines office in each vehicles etc.
and all persons shall be properly trained to
quench the fire at source itself. No other major
risks will be involved, as mines will be working
following provisions of mines act, rules and
regulations and under supervision of qualified
persons.
8.2 From any other causes No Not envisaged
8.3 Could the project be affected by
natural disasters causing
environmental damage (e.g. floods,
No The site is generally plain without many
undulations and it falls in Zone-III as per IS:
1893 (Part-1) 2002.
Proposed minor mineral Mining Project (ML Area: 55.50 ha) Production of Stone along with Associated Minor minerals 15 MTPA
At Village – Dadam, Tehsil –Tosham , District– Bhiwani (Haryana)
Form - I / Appendix – I
M/s. Sunder Marketing Associates 14
earthquakes, landslides, cloudburst
etc)?
9. Factors which should be considered (such as consequential development) which could lead
to environmental effects or the potential for cumulative impacts with other existing or
planned activities in the locality
S.
No. Information/Checklist
confirmation
Yes/
No
Details thereof (with approximate
quantities/rates, wherever possible) with
source of information data
9.1 Lead to development of supporting
facilities, ancillary development or
development stimulated by the
project which could have
impact on the environment e.g.:
Supporting infrastructure
(roads, power supply, waste
or waste water treatment,
etc.)
Housing development
Extractive industries
Supply industries
Other
Yes Employment opportunities will increase due to
the requirement of workers for the proposed
project. Local people will be preferred for
employment. This will contribute in raising the
socio-economic status and standard of living of
the nearby villagers.
Greenery of the surrounding area will be
enhanced which will further add the area
aesthetic beauty to the area.
This will contribute in raising the socio-
economic status and standard of living of the
nearby villagers
9.2 Lead to after-use of the site, which
could have an impact on the
environment
Yes The after use of site planned would be helpful to
the society, owing to better greenery and
development of water reservoir supporting the
surrounding localities.
9.3 Set a precedent for later
developments
Yes A better after-use scenario which is likely to
increase aesthetic beauty of area in addition to
benefit of better water regime & greenery would
set a precedence for subsequent entrepreneurs
who venture such projects.
9.4 Have cumulative effects due to
proximity to other existing or
planned projects with similar
effects
No
No cumulative effects as there is no other
existing or planned projects.
Proposed minor mineral Mining Project (ML Area: 55.50 ha) Production of Stone along with Associated Minor minerals 15 MTPA
At Village – Dadam, Tehsil –Tosham , District– Bhiwani (Haryana)
Form - I / Appendix – I
M/s. Sunder Marketing Associates 15
Proposed minor mineral Mining Project (ML Area: 55.50 ha) Production of Stone along with Associated Minor minerals 15 MTPA
At Village – Dadam, Tehsil –Tosham , District– Bhiwani (Haryana)
Form - I / Appendix – I
M/s. Sunder Marketing Associates 16
(III) Environmental Sensitivity
S. No. Areas
Name/
Identity
Aerial distance (within 15 km.)
Proposed project location boundary
1 Areas protected under international
conventions, national or local
legislation for their ecological,
landscape, cultural or other related
value
None No National Park, Wild Life Sanctuary or
any other protected area under
international conventions, national or
local legislation.
2. Areas which are important or
sensitive for ecological reasons -
Wetlands, watercourses or other
water bodies, coastal zone,
biospheres, mountains, forests
Water bodies Some small seasonal village pond exists.
3 Areas used by protected, important
or sensitive species of flora or fauna
for breeding, nesting, foraging,
resting, over wintering, migration
None No such major area is located within the
15 km radius of the mining lease area.
4 Inland, coastal, marine or
underground waters.
None
5 State, National boundaries. None Nil
6 Routes or facilities used by the
public for access to recreation or
other tourist, pilgrim areas.
None Nil
7 Defense installations. None Nil
8 Densely populated or built-up area. Tosham (~6.0 km in ESE direction)
9 Areas occupied by sensitive man-
made land uses (hospitals, schools,
places of worship, community
facilities).
Yes Well established educational, medical &
other facilities exist in nearby area.
10 Areas containing important, high
quality or scarce resources
(Ground water resources, surface
resources, forestry, agriculture,
fisheries, tourism, minerals).
No No such hot spots or scarce resources in
the project vicinity
11 Areas already subjected to pollution None No such areas in the project vicinity.
Proposed minor mineral Mining Project (ML Area: 55.50 ha) Production of Stone along with Associated Minor minerals 15 MTPA
At Village – Dadam, Tehsil –Tosham , District– Bhiwani (Haryana)
Form - I / Appendix – I
M/s. Sunder Marketing Associates 17
S. No. Areas
Name/
Identity
Aerial distance (within 15 km.)
Proposed project location boundary
or environmental damage. (Those
where existing legal environmental
standards are exceeded).
12 Areas susceptible to natural hazard
which could cause the project to
present environmental problems
(Earthquakes, subsidence,
landslides, erosion, flooding or
extreme or adverse climatic
conditions).
None Nil
(IV) PROPOSED TERMS OF REFERENCE FOR EIA STUDIES
As per EIA Notification dated 14th September, 2006 amended as on date; following are proposed
Terms of Reference (ToR) for preparation of Environmental Impact Assessment Report and
Environmental Management Plan:-
1. Introduction
2. Project description
3. Description of the environment
4. Anticipated environmental impacts & mitigation measures-
5. Analysis of alternatives (technology & site)
6. Environmental monitoring program
7. Additional studies
8. Project benefits
9. Environmental cost benefit analysis, if any.
10. Environmental management plan
11. Summary & conclusion.