ESSP support to LPV implementation
Alejandro Fransoy
16/07/2015 GSA Call for Grants info session. 2
Table of Contents
• EGNOS implementation steps and lessons learnt from previous projects:- Recommendations for ANSPs and Airports- Recommendations for Operators
• ESSP offered support
16/07/2015 GSA Call for Grants info session. 3
ESSP support to LPV implementation
Recommendations for ANSPs and airports
16/07/2015 GSA Call for Grants info session. 4
1. Meeting National Authority • Establish regular coordination and planning
• Set the implementation project team
• Define the objectives and scope
• Make a first preliminary assessment
• Review existing regulation and guidance
Plan 1 to 3 months
Set an appointment well in advance
Duration
Costs NA
ESSP support to LPV implementationRecommendations for ANSPs and airports
16/07/2015 GSA Call for Grants info session. 5
1. Meeting National Authority
2. Airport Capabilities Assess.
• Define CAA requirements
• Airport characterization:
• Navaids (missed APCH)
• CNS (radar)
• ATC/AFIS/No ATC
• Meteo
• Airspace (un/controlled, SID/STAR, etc)
• Infrastructure (lighting, strips, etc)
• Traffic and a/c capabilities
1 to 2 months Duration
Costs NA (subcontract)
ESSP support to LPV implementationRecommendations for ANSPs and airports
16/07/2015 GSA Call for Grants info session. 6
1. Meeting National Authority
2. Airport Capabilities Assess.
3. Procedure Design
• Obstacle site survey (update)
• Usually the design is performed by ANSP o Pans Ops 8168 Vol II, Part III; o Annex 14 Vol I; o ICAO 9906 Vol II
• Possibility to subcontract third parties like surveyors, procedure designers or other ANSPs
• Preliminary approval by CAA sometimes req.
2 to 3 months + NSA approvalDuration
Costs 15 – 30k€ for 2 RWY ends
ESSP support to LPV implementationRecommendations for ANSPs and airports
16/07/2015 GSA Call for Grants info session. 7
1. Meeting National Authority
2. Airport Capabilities Assess.
3. Procedure Design
4. Flight Validation
• Ground validation
• Independent review of procedure design package
• GNSS SIS assessment (optional) + interferences
• Procedure impact in operations
• Flight validation (need for FAS DB)
• Obstacles (identification of new ones)
• Navigation data
• Fly-ability (pilot workload)
1 to 3 months Duration
Costs 5 to 40k€
ESSP support to LPV implementationRecommendations for ANSPs and airports
16/07/2015 GSA Call for Grants info session. 8
1. Meeting National Authority
2. Airport Capabilities Assess.
3. Procedure Design
4. Flight Validation
5. Safety Assessment
• CONOPS, EC 2096/2005 and EC 1315/2007
• Eurocontrol Methodology SAM:
• Functional Hazard Assessment (FHA)
• Preliminary System Safety Assessment (PSSA)
• System Safety Assessment (SSA)
2 to 6 monthsDuration
Costs 10 to 40k€
ESSP support to LPV implementationRecommendations for ANSPs and airports
16/07/2015 GSA Call for Grants info session. 9
1. Meeting National Authority
2. Airport Capabilities Assess.
3. Procedure Design
4. Flight Validation
5. Safety Assessment
6. Procedure Approval
• Need for EWA (plan in advance)
• Re-visit:
• Safety assessment
• Procedure design
• Flight validation
1 to 2 monthsDuration
Costs 2 – 4k€
ESSP support to LPV implementationRecommendations for ANSPs and airports
16/07/2015 GSA Call for Grants info session. 10
1. Meeting National Authority
2. Airport Capabilities Assess.
3. Procedure Design
4. Flight Validation
5. Safety Assessment
6. Procedure Approval
7. ATCO Training
• Core training
• RNAV concept
• Performances, GPS, RAIM…
• Flight plan
• ATC procedures
• Contingency procedures, separation minima, mixed equipage, phraseology
• Specific to RNP
• Radar vectoring, APCH minima, T&Y…
1 to 2 monthsDuration
Costs 10 to 20k€
ESSP support to LPV implementationRecommendations for ANSPs and airports
16/07/2015 GSA Call for Grants info session. 11
1. Meeting National Authority
2. Airport Capabilities Assess.
3. Procedure Design
4. Flight Validation
5. Safety Assessment
6. Procedure Approval
7. ATCO Training
• Charting (ARINC 424)
• SBAS Channel number (Eurocontrol)
• AIRAC 56 days
• AIC/AIP
• Data recording and monitoring
• Publication by AIS provider
8. AIP publication
2 – 3 monthsDuration
Costs NA (ANSP effort usually)
ESSP support to LPV implementationRecommendations for ANSPs and airports
16/07/2015 GSA Call for Grants info session. 12
1. Meeting National Authority
2. Airport Capabilities Assess.
3. Procedure Design
4. Flight Validation
5. Safety Assessment
6. Procedure Approval
7. ATCO Training
8. AIP publication
Duration:• 24 months (1st LPV)• 10-15 months otherwise
1 – 3 months; NA
1 – 2 months; NA
2 – 3 months; 15 - 30 k€
1 – 3 months; 5 - 40 k€
2 – 6 months; 10 – 40 k€
1 – 2 months; 2 – 4 k€
1 – 2 months; 10 – 20 k€
2 – 3 months; NA €
Cost: 40 – 140 k€ 2RWY-ends
ESSP support to LPV implementationRecommendations for ANSPs and airports
16/07/2015 GSA Call for Grants info session. 13
ESSP support to LPV implementation
Recommendations for Operators
1. Establish the certification plan • Establishment of Certifying Authority, e.g. EASA• Agreeing the certification basis, e.g. EASA CS-23,
CS-25, etc• Agreeing the compliance summary, e.g. EASA
AMC 20-28• Timeline of deliverables
1 to 2 monthsDuration
Costs NA (subcontracting)
ESSP support to LPV implementationRecommendations for Operators
16/07/2015 GSA Call for Grants info session. 14
1. Establish the certification plan • Part 21 (DOA) or TC Holder (manufacturer)• Aircraft survey• Design data Package• A/C conversion + ground/flight test• Compliance demonstration• STC design approval
STC/SB not available
2. STC/SB elaboration
6 to 10 monthsDuration
Costs 20 to 120 k€ per aircraft
ESSP support to LPV implementationRecommendations for Operators
16/07/2015 GSA Call for Grants info session. 15
1. Establish the certification plan • Part 145 or Manufacturer• Purchase STC• A/C conversion• Airworthiness re-certification
STC/SB not available
2. STC/SB elaboration
STC/SB available
3. Implement changes
3 to 6 monthsDuration
Costs 3 to 120 k€ per aircraft
ESSP support to LPV implementationRecommendations for Operators
16/07/2015 GSA Call for Grants info session. 16
1. Establish the certification plan • Operational Procedures and documentation:
• Operational Procedures Update• Operations Manual Update• Navigation Database Management
• Crew training and training package update• Application for Operational Approval
STC/SB not available
2. STC/SB elaboration
STC/SB available
3. Implement changes
4. Operational approval
2 to 6 monthsDuration
Costs 5 to 20 k€
ESSP support to LPV implementationRecommendations for Operators
16/07/2015 GSA Call for Grants info session. 17
1. Establish the certification plan
STC/SB not available
2. STC/SB elaboration
3. Implement changes
4. Operational approval
1 – 2 months; NA
6 – 10 months; €20k-€120k
3 – 6 months; €3k-€120k
2 – 6 months; €2k-€20k
ESSP support to LPV implementationRecommendations for Operators
• STC/SB available: 6-18 months; €5k-€140k (per a/c) • STC/SB NOT available: 12-24 months; €25k-€160k (per a/c)
16/07/2015 GSA Call for Grants info session. 18
ESSP support to LPV implementation
• LPV implementation status – Published and planned airports, certified & approved operators
• Comprehensive guidance material– ANSPs and airports (Implementation and publication)– Operators (Certification, Training and & Op. Approval)
• Support for EWA signature• Support services catalogue
– Manufacturers, Part 21s, Part 145s– STCs and SBs: available and under development (Part 21 organisations and manufacturers)– Promotion of new (AML) STCs and SBs– Procedure designers and flight validation companies
Awareness Technical support
16/07/2015 GSA Call for Grants info session. 19
• Performance Assessments– EGNOS SoL service performances– EGNOS NOTAMs proposals
• Cost Benefits Analyses– For airports/ANSPs
• Accessibility, navaids rationalisation
– For operators• Avoided DDCs, fuel savings
• Dedicated Workshops• Technical advice on implementation
projects (lessons learnt, PoCs)
Awareness Technical support
Check-out our online EBCAST tool
ESSP support to LPV implementation
16/07/2015 GSA Call for Grants info session. 20
EGNOS User Support websitehttp://egnos-user-support.essp-sas.eu/
• LPV implementation map• Business Case Tool• Guidance material for LPV approval• LPV training package• EGNOS information:
Success stories Brochures Bulletins