April 25, 2017
Dublin High School
Engineering & Science
Project Update #5
Facilities Management
Board Presentation
History – Bond Project Lists
Approved as part of the Measure E Project List in 2013
Measure C/E Bond Re-Prioritization 2015
Measure H Bond Project Priorities 2016
Several Building Options Studied
April 25, 2017
February 14, 2017
New Building Locations
2-Story Option (Original Design)
Original Design: Weight Room – 2,730sf 5 Engineering Classrooms 7 Flexible Science Labs 12 new classrooms
2-Story Option (w/in $25M budget)
Changes from original design:
Weight Room – 2,580sf 4 Engineering Classrooms 6 Flexible Science Labs 10 new classrooms
3-Story Option (with HUB space)
Changes fromoriginal design:
1st Floor - Unchanged 2nd Floor – Breakout
space converted to Flexible Science Lab
3rd Floor – 3 FlexibleScience Labs &8,000sf HUB space.
Project Construction Schedule
Interim Custodial & Weight Rm.
Spring 2017
Demo Building EE
Summer 2017
Grounds Building
Fall 2017 – Spring 2018
Engineering & Science Building
Summer 2018 – Spring 2020
Potential Move-in: Summer 2020
* Schedule based on Board approval April 25, 2017.
Current Building Options Summary
Option DescriptionEstimated
Project Cost
# of Classrooms
Added
Estimated Occupancy
Date*
Additional Notes(All options include weight room, maintenance
shop, & grounds building.)
AANew 2-story Building
($25M max budget)$25M 10 Fall 2020
BBNew 2-story Building (Per original design)
$26.5M 12 Fall 2020
CCNew 3-story Building (with HUB Space)***
$31.5M 15 Fall 2020Board approved authorization to proceed with design in June 2016. Design is Approximately
75% complete.
April 25, 2017
* Schedule based on Board approval April 25, 2017.** Possible estimated $500,000 savings for HUB space in lieu of 4 additional science classrooms.
Next Steps
April 25th Board Meeting Direction on Engineering & Science Building Option
Proceed with re-design for E&S building
Update Schedule per current direction