11 Jan. 2007 G. Rakness (UCLA) 1
CSC commissioningBefore Christmas break• Turned on and checked communication with TMB, DMB, ALCT, and
CFEB for 6 peripheral crates (180o in ) on station 1: VME+1/[4-9]… • Problems (representative of those which will be seen by “Team-A”):
• PROM ID readback 0 and F on two CFEBs likely skew-clear cable problems
• One DMB reading back all zero’s likely firmware reloading• One LVMB temperature readback problem• All ME1/3 and ME1/1 ALCTs read 0 from on-board ADC +5.5V_B
line (N.B. values were OK as read by LVMB)• Found/fixed one set of swapped crate controller fibers at GBit
switch in counting house (VME+1/67)• Found/fixed one crate controller rx/tx swap
• Otherwise: successful communication with all components with final fibers, patch panels, cabling, cooling, LV power...
11 Jan. 2007 G. Rakness (UCLA) 2
CSC commissioning (cont.)Yesterday…• Online computers switched on• Power enabled to Maratons• LV control computer switched on and appears to be operational• Software + GBit driver (used for VME communication) is updated to SLC4
with updates for station 1 (see next slide)
Today…• Cooling began running• Gas began flowing• ME-2 disk was lowered (i.e., no access allowed)
Weekend…• Access tests disables access to experiment (would be breaking interlock,
otherwise)
Recommence commissioning Monday by “Team-C” (i.e., me)
Step A: download new firmware to all components…
11 Jan. 2007 G. Rakness (UCLA) 3
Updates to Online SoftwareUpdates by Jinghua and me include…
• Multiple crates in single xml file
• Remap user access to AFEBs to be from 1 to 18, regardless of how AFEBs are connected to the ALCT
AFEB 1(always)
On ME1/1…
• AFEBs count from 1 to 18 (inner to outer)
• ALCT always mounted with the same orientation (AFEB input #1 to right)
• ALCT slow control firmware the same on all
• ME1/1 mounted on disks with respect to IP as in the picture to the left….
Ordering of AFEBs reversed on
(Plus, forward) and
(Minus, backward)
AFEB 18(always)
AFEB input #1
AFEB input #18
#18
#18#18
#1#1
#1
ME1/1
11 Jan. 2007 G. Rakness (UCLA) 4
Updates to Online Software (cont.)Added xml parameters for TMB
1. clct_stagger = 1/0 = do/don't stagger strip layers (staggering needed for ME1/1)
2. clct_blanking = 1/0 = do/don't blank CLCT output if no valid pattern flag
3. clct_pattern_id_thresh = [0-8] = minimum pattern ID value for CLCT pretrigger
4. aff_thresh = [0-6] = minimum number of hits needed on CLCT pretrigger pattern to send Active FEB Flag to DMB
5. min_clct_separation = [0-255] = minimum 1/2-strip separation between two CLCTs
• Removed clct_distrip_pretrig_thresh (since no di-stripness left…)
11 Jan. 2007 G. Rakness (UCLA) 5
To do…• Clean up simulation drift time analysis for muons
• Remove delta-electrons
• Point source from vertex
• Bin in understandable unit
• Cleanly separate:
• drift time to wire
• minimum drift time to wire for events with multiple wires hit
• drift time from wiregroup
• Make plots in code, not PAW…
• Commission ME+1 chambers
• Write documentation for Team-A