Download - Conducting Effective Visual Inspections

Transcript
Page 1: Conducting Effective Visual Inspections

Conducting Effective Visual Conducting Effective Visual Inspections:Inspections:Mechanical Integrity for Refrigeration Mechanical Integrity for Refrigeration SystemsSystems

Daniel DettmersDaniel DettmersAssociate Researcher, IRCAssociate Researcher, IRC

Page 2: Conducting Effective Visual Inspections

What is an Effective Visual Inspection?What is an Effective Visual Inspection?

• Thorough inspection of the exterior of the refrigeration system– Insulated and uninsulated components– Easily accessible and less than accessible components– No drive-by’s

• What’s included?– Piping & valves– Vessels– Heat exchangers– Ammonia pumps– Etc.

Page 3: Conducting Effective Visual Inspections

Origin of the RequirementOrigin of the Requirement29 CFR 1910.119 (j)(4)29 CFR 1910.119 (j)(4)– (j)(4)(i) Inspections and tests shallshall be performed on

process equipment– (j)(4)(ii) Inspection and testing procedures shall follow

recognized and generally accepted good engineering good engineering practicespractices

– (j)(4)(iii) The frequency of inspections & tests of process equipment shall be consistent with applicable applicable manufacturers‘ recommendationsmanufacturers‘ recommendations and good engineering good engineering practicespractices, and more frequentlymore frequently if determined to be necessary by prior operating experience

Page 4: Conducting Effective Visual Inspections

Good Engineering Practice?Good Engineering Practice?• Manufacturers’ recommendations• Industry standards

– ASME B31.5 or B31.3 • Pre-startup inspection

– NB-23 (National Board Inspection Code)• Refers to ASME Boiler

& Pressure Vessel Code

• Guidelines– IIAR Bulletin 109 – IIAR Bulletin 110– IRC Mechanical Integrity Guidebook

• Currently in trial use

Page 5: Conducting Effective Visual Inspections

IIAR 109 & 110IIAR 109 & 110109:4.7.3109:4.7.3 – “Ammonia piping should be inspected…”109:4.7.4109:4.7.4 – “Uninsulated refrigerant piping should be

inspected…110:6.4.2.1110:6.4.2.1 - While the system is operational, the external

appearance of the surface of vessels or heat exchangers … should be visually inspected weekly by the system operating staff for any departures from normal.”

110:6.4.3110:6.4.3 – “The external surface or the insulation and associated vapor barrier applied to…vessels and heat exchangers should be inspected no less than once every 12 months.”

Page 6: Conducting Effective Visual Inspections

IIAR 109 & 110IIAR 109 & 110110:6.7.1110:6.7.1 – “All uninsulated piping and associated

components…shall be inspected annually for any damage or deterioration…”

110:6.7.2110:6.7.2 – “At least as part of the annual piping inspection, but preferably more frequently, the external condition of the insulation and supports shall be inspected.”

• Additional components for yearly inspection in 110– Ammonia pumps– Shut-off valves

• 6 months for exposed stems

– Relief valves

Page 7: Conducting Effective Visual Inspections

Conducting the InspectionConducting the Inspection• Establish a plan– Identify and categorize equipment within scope of

1910.119 §(j)– Establish prioritized list of appropriate inspections &

tests– Conduct necessary tests and inspections within

prescribed frequencies– Train all personnel –- consistent inspectionsconsistent inspections– Establish “go, no-go” criteria for continued service–– DocumentDocument inspection and tests

Page 8: Conducting Effective Visual Inspections

Conducting the InspectionConducting the Inspection• Assign inspection duties & timeframe– Undesirable:

• All inspection duties fall on 1 person• All inspections are planned for the day they are due

– Desirable:• Diversify inspection duties

– Be certain inspection criteria is consistentconsistent– Incorporate with other inspection/maintenance of valves, valve

tags, vessels, evaporators, etc.– Involve new hires in process as part of OTJ training

• Plan inspection at least 1 month before due• Train all involved and document their training

Page 9: Conducting Effective Visual Inspections

Potential Failure MechanicsPotential Failure Mechanics• Weld Failure• Stress Corrosion Cracking (SCC)• Internal Erosion• External Corrosion– Corrosion Under Insulation (CUI)

Which can we catch in a visual inspection?No

NoNo

Yes!Yes!AlmostAlmost

Page 10: Conducting Effective Visual Inspections

CorrosionCorrosion• “The deterioration of a material, usually a metal,

by reaction with its environment.”- National Association of Corrosion Engineers (NACE)

• An anodic-cathodic reaction– Positive ions travel through

an electrolyte (i.e. water, ice, etc.)

– Material is sacrificed• General (Uniform) Corrosion• Pitting Corrosion

Page 11: Conducting Effective Visual Inspections

CorrosionCorrosion• Positive ions detach at the anode and

travel through a electrolyte (i.e. water, ice, etc.) which acts as a carrier connecting to the cathode the anode and cathodes need to be joined to complete the circuit– Anode => metal of the refrigeration system– Cathode => metal of the refrigeration system– Electrolyte => water

Controlling water is essential!!Controlling water is essential!!

Page 12: Conducting Effective Visual Inspections

Corrosion “Low Risk” AreasCorrosion “Low Risk” Areas• Uninsulated, painted pipe

– Easy to see any corrosion forming

• High temperature pipe– If pipe is on the high side of the

system and insulated (i.e. HPL) there aren’t large driving forces pulling moisture into the insulation system

• “Always Frozen”– Ice is a poor electrolyte slowing

the corrosion process– Be careful of what is defined as

“always frozen”

SolidSolidIceIce

FrozenFrozenInsulationInsulation

WetWetInsulationInsulation

Froz

enFr

ozen

Pipe

Pipe

Page 13: Conducting Effective Visual Inspections

Corrosion Under Insulation (CUI)Corrosion Under Insulation (CUI)• CUI is general corrosion that occurs undetected

under piping insulation– Water infiltrates the insulation system through a

break in the jacket/vapor barrier– Insulation then becomes an enabler which aids in

corrosion by holding the water tight to the pipe

– Pipe must also be without or have a failure in the surface protection (i.e. pipe paint)

Page 14: Conducting Effective Visual Inspections

Corrosion Under Insulation (CUI)Corrosion Under Insulation (CUI)““Vapor Barrier”Vapor Barrier”

Inside InsulationInside Insulation

Outside InsulationOutside Insulation

PipePipe

Rust/InsulationRust/Insulation

Soaked InsulationSoaked Insulation

Page 15: Conducting Effective Visual Inspections

How Does Moisture Enter?How Does Moisture Enter?• Insulation system failures

– Breaches in jacket, vapor retarder and insulation

– Travel under/through the insulation from a breach elsewhere in the system

• Water trapped at time of installation

• Diffusion of water vapor in the air into insulation– Driving forces pull moisture laden

air through cracks, holes and unsealed joints

– Vapor retarder not barrier

Page 16: Conducting Effective Visual Inspections

Corrosion “High Risk” AreasCorrosion “High Risk” Areas• Piping that is near to or above the

freezing point• Piping that cycles temp (defrost

condensate)• Piping that has circumferential

temp distribution (wet suction)• Low points in the piping system

– Dips in line or end/corner of horizontal run

– Bottom of vertical run– Bottom edge of a horizontal pip run

• Piping that is hard to inspect– under supports– Behind walls/piping chases

Page 17: Conducting Effective Visual Inspections

Other TellOther Tell--Tale SignsTale Signs

Corrosion Corrosion of theof theJacketJacket

Biological GrowthBiological Growth

External FrostExternal FrostEspecially in SummerEspecially in Summer

Page 18: Conducting Effective Visual Inspections

Wet Suction ReturnsWet Suction Returns• Vapor sits in bottom of pipe– Bottom always frozen– Top can freeze-thaw

• CUI at mid-pipe or higher• Look for bottom frost/water

CrossCross--sectionsection

VaporVaporNHNH33

Page 19: Conducting Effective Visual Inspections

Ammonia Condensate Defrost LinesAmmonia Condensate Defrost Lines• Large swings in

temperature– Above and below

freezing (32oF)– Large driving

force for moisture – Multiple freeze/thaw cycles

that tear apart the insulation

0

20

40

60

80

2 4 6 8 10 12 14 16 18 20 22 24

Page 20: Conducting Effective Visual Inspections

Physical ImpactPhysical Impact• Physical damage to insulation, pipe or vessel is usually

easy to spot• Equipment susceptible to damage is often located in

areas of heavy traffic, outside (exposed to the elements) or in an area subject to frequent clean-up wash downs

• Look anywhere fork trucks can reach (and areas they can’t)– Behind guards– Ceiling hung evaps– Piping running up or along walls– Vessels in spaces

Page 21: Conducting Effective Visual Inspections

DocumentationDocumentation1910.119 (j)(4)(iv) The employer shall document each

inspection and test that has been performed on process equipment. The documentation shall identify the date of the inspection or test, the name of the person who performed the inspection or test, the serial number or other identifier of the equipment on which the inspection or test was performed, a description of the inspection or test performed, and the results of the inspection or test.

Page 22: Conducting Effective Visual Inspections

Questions?Questions?

• Innovation – Knowledge – Progress

www.irc.wisc.edu