Download - CITY OF LEANDER

Transcript
Page 1: CITY OF LEANDER

CITY OF LEANDER

June 10, 2013

Williamson County Bond Projects

2014-15 Requests

Page 2: CITY OF LEANDER

Williamson County Bond Projects

CITY OF LEANDER

Trails

2014-15 RequestsJune 10, 2013

Page 3: CITY OF LEANDER

WilliamsonCounty Bond

ProjectsTrails

Bagdad Heritage Trail Continuation Phase One TxDOT STP Grant

$1.2 million

Bledsoe Park

Crystal Fa

lls Pkwy

Proposed Trail to connect existing Heritage Trail (constructed in 2006

T-21 grant) at Bledsoe Park to Crystal Falls Parkway

Bagdad Road

TOTAL PROJECT $900,000.00

WILCO Request (80%) $720,000.00City Match (20%) $180,000.00

PRIORITY 1

Page 4: CITY OF LEANDER

WilliamsonCounty Bond

ProjectsTrails

Bagdad Heritage Trail ContinuationPhase One TxDOT STP Grant

$1.2 million

Proposed Trail to connect existing Heritage Trail at Bledsoe Park to

Crystal Falls Parkway

TOTAL PROJECT $900,000.00

WILCO Request (80%) $720,000.00City Match (20%) $180,000.00

PRIORITY 1

Page 5: CITY OF LEANDER

Williamson County Bond ProjectsTrails

183A/Metro Trail

Proposed Trail to

connect existing

183A Trail to Metro

Station to Hwy.183Approx. 7500 ft

Hero Way

Mel

Mat

his B

lvd

FM 2243

Capitol Metro Station

HWY 183A

Hwy 183

TOTAL PROJECT $600,000.00

WILCO Request (80%) $480,000.00City Match(20%) $120,000.00

PRIORITY 2

Page 6: CITY OF LEANDER

Williamson County Bond Projects

CITY OF LEANDER

Roadways

2014-15 RequestsJune 10, 2013

Page 7: CITY OF LEANDER

Williamson County Bond ProjectsRoadways

Hero Way East and WestProposed Roadway

Improvements connect from

Reagan Blvd to Lakeline

Extension FM 2243

Hero Way

Crystal Falls Pkwy

Reagan Blvd

FM 2243

HWY 183A

HWY

183

Lakeline Extension

Bagdad Rd

TOTAL PROJECT (PH 2) $9,000,000.00

WILCO Request (50%) $4,500,000.00City Match (50%) $4,500,000.00

TOTAL PROJECT (PH 1) $17,000,000.00

WILCO Request (50%) $8,500,000.00City Match (50%) $8,500,000.00

PHASE ONEPHASE TWO

PRIORITY 1

Page 8: CITY OF LEANDER

Williamson County Bond ProjectsRoadways

Hero Way WestProposed Roadway

Improvements connect from

Reagan Blvd to Lakeline

Extension

Western Phase heavily

constrained with utility

lines and open drainage

PRIORITY 1

Page 9: CITY OF LEANDER

Williamson County Bond ProjectsRoadways

Hero Way EastProposed Roadway

Improvements connect from

Reagan Blvd to Lakeline

Extension

PRIORITY 1

Page 10: CITY OF LEANDER

Williamson County Bond Projects

Roadways

Bagdad Road North

Proposed Roadway Improvements from FM2243

to CR 280

CR280

FM2243

San Gabriel Pkwy

Halsey Dr

Collaborative Way

High School #6

TOTAL PROJECT $9,000,000.00

WILCO Request (50%) $4,500,000.00City Match (50%) $4,500,000.00

PRIORITY 2

Page 11: CITY OF LEANDER

Williamson County Bond Projects

Roadways

Bagdad Road North

Proposed Roadway Improvements from FM2243

to CR 280

TOTAL PROJECT $9,000,000.00

WILCO Request (50%) $4,500,000.00City Match (50%) $4,500,000.00

PRIORITY 2

Page 12: CITY OF LEANDER

Williamson County Bond ProjectsRoadways

San Gabriel Parkway

Proposed Roadway

Improvements from CR170 to Reagan Blvd.

CR170San Gabriel Pkwy

Reag

an B

lvd

Kittie Hill Airport

TOTAL PROJECT $7.500,000.00

WICO Request (50%) $3,750,000.00City Match (50%) $3,750,000.00

183APRIORITY 3

Page 13: CITY OF LEANDER

Williamson County Bond ProjectsRoadways

San Gabriel Parkway

Proposed Roadway

Improvements from CR170 to Reagan Blvd.

TOTAL PROJECT $7,500,000.00

WICO Request (50%) $3,750,000.00City Match (50%) $3,750,000.00

PRIORITY 3

Page 14: CITY OF LEANDER

CITY OF LEANDER

June 10, 2013

Williamson County Bond Projects2014-15 Requests

Summary

TrailsTotal $1,500,000.00Wilco $1,200,000.00 (80%)City $300,000.00 (20%)

RoadwaysTotal $42,500,000.00Wilco $21,250,000.00 (50%)City $21,250,000.00 (50%)

CombinedTotal $44,000,000.00Wilco $22,450,000.00 (51%)City $21,550,000.00 (49%)