E. KAKO (KEK) 2009' Dec. 03 S1-G Webex meeting
Global Design Effort
1
Cavity String AssemblyProcedure for S1-Global
Eiji Kako (KEK, Japan)
1. Preparation of cavity string assembly (12-21, January 2010)2. String assembly of four cavities (22-26, January 2010)3. Vacuum leak check & Ar slow-leak (27-31, January 2010)
Attention !! Draft Proposal
E. KAKO (KEK) 2009' Dec. 03 S1-G Webex meeting
Global Design Effort
2
Cavity Assembly Team for S1-Global
FNAL Tug Arkan (Leader) Brian Smith
DESY Axel Matheisen (Supervisor) Manuela Schmoekel ???
KEK Shuich Noguchi Eiji Kako
E. KAKO (KEK) 2009' Dec. 03 S1-G Webex meeting
Global Design Effort
3
List of clean room work (1)
1. Preparation for Cavity Assembly (1000 & 10) a. Checking of all tools & jigs for assemblyb. Cleaning of cavity support post & table (1000)c. Cleaning of outside of cavity package (1000)d. Setting a cavity on the support table (1000)e. Rough alignment of 4 cavities (1000)f. Cleaning of 3 bellows between 2 cavities (10)g. Cleaning of 1 gate-valve (10)h. Cleaning of 1 taper beam tube (10)i. Cleaning of 1 blind flange (10)j. Cleaning of bolts and nuts (10)k. Cleaning of Al sealing material (10) l. etc........
E. KAKO (KEK) 2009' Dec. 03 S1-G Webex meeting
Global Design Effort
4
2. Cavity String Assembly (class 10) a. Ar gas slow-leak into a cavity up to 1 atmb. Alignment of cavity rotationc. Introduction of Ar gas flow into #1 cavityd. Installation of a taper beam tube to #1
cavity e. Installation of a gate-valve to #1 cavityf. Connection of #1 - #2 cavities with a
bellowsg. Connection of #2 - #3 cavities with a
bellowsh. Connection of #3 - #4 cavities with a
bellowsi. Attachment of a blind flange to #4 cavityj. Move to class 1000 for pumping & leak
checkk. Ar gas slow-leak into 4 cavities up to 1 atm
List of clean room work (2)
E. KAKO (KEK) 2009' Dec. 03 S1-G Webex meeting
Global Design Effort
5
Clean Room at KEK-STF
Clean room at STF
To cryomoduleassembly area
Air Shower Entrance HPR
Pass-box
Pass-box
Water Shower
16.2 m
5.4
m
7 m
2.2
m
Class 1000
Class 10
E. KAKO (KEK) 2009' Dec. 03 S1-G Webex meeting
Global Design Effort
6
Infrastructure in STF clean room
Entrance of cavity (car washer, 8 MPa)
Exit of string cavities outside CR
Entrance for men & women
Air shower for men & women
E. KAKO (KEK) 2009' Dec. 03 S1-G Webex meeting
Global Design Effort
7
Infrastructure in clean room (c-1000)
Ultra-sonic bath, Ultra-pure water
He leak detector, Pumping system
E. KAKO (KEK) 2009' Dec. 03 S1-G Webex meeting
Global Design Effort
8
Infrastructure in clean room (class-10)
1st Gas line of dry air, Ar, He, N2
Top Gun and Particle counter
Vacuum parts on a table
E. KAKO (KEK) 2009' Dec. 03 S1-G Webex meeting
Global Design Effort
9
Slow-leak procedure for filling Ar gas Class 1000
Flow rate of Ar gas = 60 ~ 100 ml / minFilter = particles > 0.003 um, >99.999999%Release valve = 1/3 PSI
E. KAKO (KEK) 2009' Dec. 03 S1-G Webex meeting
Global Design Effort
10
Schedule of cavity assembly (1)
January 2010, (Preparation by KEK)11 Mon; National Holiday12 Tue; am/pm “”Check of tools and jigs for assembly”“13 Wed; am/pm Rinsing of 9 support posts by car washer Set-up of support posts in class-100014 Thu; am Rinsing of a cavity (outside) by car washer Installation of a cavity on support in c-1000 pm Rinsing of a cavity (outside) by car washer Installation of a cavity on support in c-1000 Rough alignment of 2 cavities in c-1000
E. KAKO (KEK) 2009' Dec. 03 S1-G Webex meeting
Global Design Effort
11
Schedule of cavity assembly (2)
(Preparation by KEK)15 Fri; am Attach. of vacuum parts with #1 cavity in c-10 Ar slow-leak for 24 h (80 ml/min) in c-1000 pm Cleaning of 1 gate-valve (wiping & blower) Cleaning of 3 connection bellows (US & UPW) Cleaning of 1 taper beam tube (US & UPW) Cleaning of 1 blind flange (US & UPW) Cleaning of bolts and nuts (US & UPW)16 Sat; am Movement of #1 cavity from c-1000 to c-10 Attach. of vacuum parts with #2 cavity in c-10 Ar slow -leak for 24 h (80ml/min) in c-1000
E. KAKO (KEK) 2009' Dec. 03 S1-G Webex meeting
Global Design Effort
12
Schedule of cavity assembly (3) (Preparation by KEK) 18 Mon; am Movement of #2 cavity from c-1000 to c-10 Rinsing of a cavity (outside) by car washer Installation of a cavity on support in c-1000 pm Rinsing of a cavity (outside) by car washer Installation of a cavity on support in c-1000 Rough alignment of 2 cavities in c-100019 Tue; am Attach. of vacuum parts with #3 cavity in c-10 Ar slow-leak for 24 h (80 ml/min) in c-100020 Wed; am Movement of #3 cavity from c-1000 to c-10 Attach. of vacuum parts with #4 cavity in c-10 Ar slow -leak for 24 h (80ml/min) in c-1000
E. KAKO (KEK) 2009' Dec. 03 S1-G Webex meeting
Global Design Effort
13
Schedule of cavity assembly (4)
(Preparation by KEK)21 Thu; am Movement of #4 cavity from c-1000 to c-10 Alignment of cavity rotation of 4 cavities in c-10
Check of STF clean room by FNAL & DESY colleagues pm Meeting of Cavity Assembly Team at KEK Tug, Brian, Manuela, ?(DESY), Shuichi, Eiji, Norihito Confirmation of assembly procedure, tools & jigs
E. KAKO (KEK) 2009' Dec. 03 S1-G Webex meeting
Global Design Effort
14
Schedule of cavity assembly (4) (Cavity string assembly by DESY & FNAL, KEK)22 Fri ~ 26 Tue (5 days) (not correct order of works, ?? need discussion) . Cleaning of parts and jig . Setup of Ar gas flow . Attachment of a taper beam tube (#1 cavity) . Attachment of a gate-valve (#1 cavity) . Attachment of a blind flange (#4 cavity) . Connection of #1 and #2 cavities with bellows . Connection of #3 and #4 cavities with bellows . Connection of #2 and #3 cavities with bellows . etc.
E. KAKO (KEK) 2009' Dec. 03 S1-G Webex meeting
Global Design Effort
15
Schedule of cavity assembly (5)
(Leak check by DESY & FNAL, KEK)27 Wed ; . Movement of string cavities from c-10 to c-1000 . Vacuum pumping in c-1000 . Leak check in c-1000 . Start of Ar slow-leak
28 Thu – 29 Fri ; (Work by KEK) . Ar slow-leak for 4 ~ 2 days30 Sat – 31 Sun ; . Spare time (if something happen,)February 01 Mon ; . Movement of string cavities from c-1000 to outside
E. KAKO (KEK) 2009' Dec. 03 S1-G Webex meeting
Global Design Effort
16
Preparation status at KEK (1)
Ordered ; 4 jigs
2 jigs from FNALOrdered ;2 jigs for FNAL2 jigs for DESY
Ordered ; 4 jigsTo be attached with KEK support posts
E. KAKO (KEK) 2009' Dec. 03 S1-G Webex meeting
Global Design Effort
17
Preparation status at KEK (2)
Ordered ;Rotational alignment fixture
Use present 8 support posts for 4 cav.Ordered ;+ 1 support post for a gate-valve
Ordered ;8 support table with rollers
E. KAKO (KEK) 2009' Dec. 03 S1-G Webex meeting
Global Design Effort
18
Preparation status at KEK (3)
Ordered;. Taper beam tube between #1 cavity and a gate-valve . Bellows support jigs
Under design. .. etc.