Download - cAse stuDY Successful stage cementing operations using ... · PDF filesteel packer specially designed for stage cementing applications. SES ECP 7in is a robust, simple and cost-effective

Transcript
Page 1: cAse stuDY Successful stage cementing operations using ... · PDF filesteel packer specially designed for stage cementing applications. SES ECP 7in is a robust, simple and cost-effective

solution

7in SES ECP Expandable Stainless Steel 8.2in - 208.2mm RIH OD

4.1ft - 1.24m Sealing length

Up to 10in Expansion

www.saltel-industries.com

contextA 2-well campaign was conducted using Saltel Industries Expandable ECPs

Client encountered frequent losses zones while drilling and needed to perform one-stage and two-stage cementing operations

Packers had to be set either in Cased or OpenHole and needed to withstand difficult running conditions in deviated wells and under gauged holes. The possibility to rotate and put weight on the packer during RIH is therefore essential.

solutionSES ECP is a proprietary expandable steel packer specially designed for stage cementing applications. SES ECP 7in is a robust, simple and cost-effective barrier providing reliable ground for stage cementing operation.

•Simple setting process compatible with operator’s current string design and procedures •Quick installation time •Can be worked in doglegs or tight spots •Can be rotated while RIH •High sealing capability in cased hole or openhole

Successful stage cementing operations using Saltel Expandable Steel Packers run and worked in deviated well

cAse stuDY

siQ1187_AB - Mar2016

context

Coal Seam Gas Queensland, Australia

Shallow losses zones <800m / 2,600ft Depth

104°F (40°C) - 140°F (60°C) Downhole Temperature

7in casing cemented in •8-3/4in openhole •9-5/8in casing

operAtionAl chArActeristics

2,200psi / 15.2MPa Setting Pressure

2,400psi / 16.5MPa Opening of stage collar

15min Expansion duration

1st Well Two-stage cement job Expandable ECP set in 9-5/8in casing

total loss Zonetotal loss Zone

2nd Well One-stage cement job Expandable ECP set in 8-3/4in OH

results1st Well – Two-stage cement job

The 1st packer was successfully expanded in the vertical cased section of a deviated well at 300m - 984.2ft. Packer has been set in a 9-5/8in 36ppf casing (ID 8.921in). Cement has been pumped above the packer and circulated back to surface.

2nd Well – One Stage cement job

The 2nd packer was placed at the very bottom of the string for a one-stage cement job above a loss zone. The casing was worked for 6 hours attempting to go through under-gauge hole (String weight UP/SO, 70klbs/26klbs). When pulling the casing back to surface, the SES ECP showed no signs of deformation. It was run back and successfully set in nominal 8-3/4in Openhole (with potential washout).

Benefits

• Compatible with any stage cementing configuration • Robust design allows RIH in under-gauge hole • Simplified running & setting • No risk of premature expansion • Cement successfully pumped to surface