INLINE HOCKEY COLISEUM
ACTIVITIES % PROGRESS COMMENT
DIGGINGS 80 OK
FOUNDATIONS 40 OK
COVER METAL STRUCTURE 30UNDER CONSTRUCTION AT THE
METALWORK WORKSHOP
PERCENTAGE OF PROGRESS
PROGRAMMED
15%
PERCENTAGE OF PROGRESS EXECUTED
16%