Meeting with UniverCityJanuary 30, 2019
Burnaby Mountain District Energy Utility Expansion Project
Agenda
• Introductions
• Project Overview
• Project Impacts and Road Closures
• Project Timelines
• Questions and Answers
Slide 2
Burnaby Mountain DEU Overview
• The BMDEU is a regulated District Energy Utility (DEU) that currently provides energy for space heating and hot water to UniverCity.
• The Biomass Expansion Project provides:– Cost-effective, low carbon thermal energy to the SFU campus and UniverCity– An estimated 80% reduction in greenhouse gas emissions at SFU when
compared to fossil fuel and electricity use– 1.5 km expansion to existing network along Tower Rd and South Campus Rd– 23.5 MW Central Energy Plant (13.5 MW biomass + 10 MW Natural Gas)
Burnaby Mountain DEU Development
We are Here• 2 interim central energy plants
using NG (2.3 MW + 6.0 MW)• 1.8 km of piping installed• 10 buildings connected
Burnaby Mountain DEU• Biomass based central
energy plant - 13.5 MW• 10 MW natural gas peaking
and back-up for UniverCity• 22 buildings and SFU
Campus connected• Over 5 km of piping installed
January 31, 2019 Slide 4
Project Benefits and Opportunities
January 31, 2019 Slide 5
Benefits
• 11,600 tonnes of CO2 saved• Use of clean wood waste sourced locally• Increased efficiencies, economies of scale• Possibility to integrate a low carbon electricity generation• Price stability• Independent third party oversight
Opportunities• Educational - synergy with SFU Energy Systems
and Environmental Engineering Program • Integration with the SFU stainability plan• SFU environmental objectives
Environmental Considerations
Distribution Network
January 31, 2019 Slide 7
Distribution Network Extension
January 31, 2019 Slide 8
Tower Rd Closure:Feb – March 2019
South Campus Road Closure:March – August 2019
144 Bus Detour: February – April 2019
January 31, 2019 Slide 9
Bus Detours: February – August 2019
January 31, 2019 Slide 10
Tower Road Closure
January 31, 2019 Slide 11
Tower Rd Closure:Feb – Mar 2019
Tower Road Closure: Phase 1.1Estimated 4 weeks, starting Feb. 4
January 31, 2019 Slide 12
Tower Road Closure: Phase 1.2Estimated 1.5 weeks
January 31, 2019 Slide 13
Tower Road Closure: Phase 1.3Estimated 2.5 weeks
January 31, 2019 Slide 14
South Campus Road Closure
January 31, 2019 Slide 15
South Campus Road Closure:March – August 2019
Tower Rd Closure:Feb – March 2019
Greenhouse LanePermanent Intersection Closure: Feb. 4, 2019
Greenhouse LaneImprovements
February – April 2019• Greenhouse Lane permanently closed at South Campus Road (West int.)• Biomass Civil Works Start (Grading, Removals, Services)• Tower Rd Construction
March – August 2019– South Campus Road Construction– Foundations and Retaining Wall Construction
July 2019 – March 2020– Install process equipment– Building Installation– Pour concrete floors– Landscaping
Spring 2020– Biomass Commissioning
Timelines