Building for Learning ProjectPhoto Progress Report

Month of May 2010

Project commencement 21st September 2009

Page 2: Building for Learning Project Photo Progress Report  Month of May 2010

Lecture Theatre taking shape with multilevel ceiling and first layers of paint.

Page 3: Building for Learning Project Photo Progress Report  Month of May 2010

Upstairs entry area with ceiling panels ready to add.

Building front without scaffolding

April 2010.

Page 4: Building for Learning Project Photo Progress Report  Month of May 2010

Balcony rendered and stairway constructed.

Page 5: Building for Learning Project Photo Progress Report  Month of May 2010

Toilets, wet areas and kitchen completed.

Page 6: Building for Learning Project Photo Progress Report  Month of May 2010

Downstairs hallway ceiling panels returned

Page 7: Building for Learning Project Photo Progress Report  Month of May 2010

Last of outside Hebal added and service units commissioned and room 9 painted.

Page 8: Building for Learning Project Photo Progress Report  Month of May 2010

Outside rendering completed and prior to renewed streetscape with Wodonga Council.

Page 9: Building for Learning Project Photo Progress Report  Month of May 2010

Final Admin area being plastered and toilet basins and cubicles added.

Page 10: Building for Learning Project Photo Progress Report  Month of May 2010

Council partnership streetscape starts

Page 11: Building for Learning Project Photo Progress Report  Month of May 2010

Room 8 carpet and ceiling panels returned.

Page 12: Building for Learning Project Photo Progress Report  Month of May 2010