Bridges and StructuresCommitment: $261.5 million over five yearS
Manitoba Infrastructure and Transportation has a five-year plan to invest $2 billion in Manitoba’s road system. Of this, $1.2 billion is for capital construction and renewal. One part of the five-year plan addresses the bridges and structures which link the road system across the province.
Manitoba has 2400 bridges and structures on the provincial highway system, of which 1250 are bridges. The other structures include overpasses, large culverts and overhead sign structures throughout the province.
Structures designed before 1994 generally have a design life of 40 to 50 years. The use of new timber, concrete or steel technologies has advanced the design life of modern bridges to 75 years.
A large number of provincial bridges and structures were built in the 1960s and require or will require significant rehabilitation work. A lack of planning over previous decades has increased the need for more up-front investment to catch up on use and load carrying demand and to maintain safety.
To ensure the continued safety and efficiency of the network, Manitoba has substantially increased investment in structures on the highway system. There is also more funding to monitor and inspect bridges, providing the current information needed to make reasonable decisions for strategic investments.
P r o j e C t S C o P e
Over the next five years, $261.5 million is scheduled to be spent on bridges and structures across the province.
2007 2008 2009 2010 2011
$47.7 million $46.1 million $47.2 million $62.9 million $57.6 million
2
EASTErn rEgIOn
PTH 1 Rehabilitation at Symington Yard Overpass (East of Winnipeg)
PTH 1 Rehabilitation at Birch River (East of Prawda)
PTH 9 Replacement at Parks Creek (South of Selkirk)
PTH 11 Rehabilitation at Powerview Creek (Near Pine Falls)
PTH 12 Replacement at Rat River Diversion (Southwest of Zhoda)
PTH 12 Rehabilitation at PR 207 (Ste. Anne Overpass)
PTH 59 Replacement at La Rochelle Drain/Coulee de Naults (North of La Rochelle)
PTH 59 Rehabilitation at PTH 100
PTH 59 Rehabilitation at PTH 44 (East of Lockport)
PTH 59 Replacement at Indian Reserve Drain (In Brokenhead Ojibway Nation)
PTH 75 Rehabilitation at Plum River (N/B) (Vicinity of St. Jean Baptiste)
PTH 100 Rehabilitation at Assiniboine River (South Perimeter)
PTH 100 Rehabilitation at East Interchange of PTH 1 (South Perimeter)
PTH 100 Rehabilitation at Red River (South Perimeter)
PTH 101 Rehabilitation at PTH 8 Overpass
PTH 101 Rehabilitation at PTH 9 Overpass
PTH 101 Rehabilitation at PTH 59 Overpass (Northeast Perimeter)
PTH 101 Interchange Construction at PTH 59 Overpass
PR 201 Replacement at Red River (Letellier)
PR 211 Rehabilitation at Winnipeg River (West of Pinawa)
PR 307 Replacement at Picket Creek (Whiteshell Area)
PR 315 Replacement at Peterson Creek (South of Bird Lake Turnoff)
WR 710 Rice River Road: New Bridge at Bloodvein River
P r o j e C t l i S t i n g
�
4
Niverville
BonnetLac du
Ste. Anne
Morris
Carberry
Gimli
Oakbank
Teulon
Minnedosa
Killarney
StonewallBeausejour
Altona
Carman
Neepawa
LA PRAIRIEPORTAGE
STEINBACH
SELKIRK
WINNIPEG
WINKLERMORDEN
ANDON
29
19
9A
7
59
34
23
12
50
50
68
68
68
5
9
17
17
7
8
8
6
626
101
9
101
2767
4
59
44
12
12
12
11
11
1515
44
11
52
89
23
59
59
23
3A
3
3
2
2
2
3
13
14
75
75
32 30
31
34
34
5
5
5
18
18
3
350352
352
468464
464466
465
245
231
512
419
229
418
419
417
278
361
360480
221
248
248
430
430
240
424 334
411
227
227
242
567
569
575
265265
261
462
462
261
260
260
357
262
265
471
245
242
449305
338
240
432
201
244 432
243
420
332
306
524
428
201
421
422
205 330
336
247
332
247
305
334
424332
248
331
240
305
350
352
242
530
453
351
344
340
457
423
201
528242
253
342
442
440
342
342
245
532
253
458
458
341
238
509
410
300
241
521
334
332
209
218
405
217
203
203
200 218
302
201201
310
216
246 303
403
404
503
505
200
200
216
210
207
207
206
501
311
305
205
205210
210
311
302
302
319
500
304
504
304
304
520
433
408
507
506
211
502
313
313315
307
215
406
435
212206
213
214
317
317
508
320
202
230
322
220
321
204
409236
232
225
236
415
323
322
518
416
415
519
324 222
231
229
222
329
326
233
1A
16
100
1
1
1
1
1Assiniboine River Diversion
Assiniboine River
McCormans Coulee
Codner Drain
Gillespie Drain
Squirrel Creek
3 Drains
OverPass, CNR
Prepared by:Construction Support ServicesNovember 2006
LEGEND
WINTER ROADS
HIGHWAY NETWORK
Bridges in Year 2007/2008
Bridges in Year 2008/2009
Bridges in Year 2009/2010
Bridges in Year 2010/2011
Bridges in Year 2011/2012
PROVINCE OF MANITOBABRIDGE INFRASTRUCTURE CAPITAL PROGRAMSOUTH CENTRAL REGION2007/2008 - 2011/2012
0 10 20 30 40 50
Kilometers
SOuTh CEnTrAl rEgIOn
PTH 1 Rehabilitation at Assiniboine River (East of Portage la Prairie)
PTH 1 3 Replacements at Bowes Trailer Park: East of Portage la Prairie (W/B)
PTH 1 Replacement at First Creek (West of Headingley)
PTH 1 Rehabilitation at Portage Diversion (E/B)
PTH 1 Replacement at Third Creek (West of Headingley)
PTH 1 Rehabilitation of CNR Overpass – Portage la Prairie Bypass
PTH 2 Replacement at Codner Drain (Vicinity of Starbuck)
PTH 34 Replacement at Gillespie Drain (South of Gladstone)
PTH 34 Replacement at Squirrel Creek (Vicinity of Austin)
PR 248 Rehabilitation at Assiniboine River (North of St. Eustache)
PR 352 Replacement at McCorman’s Coulee (East of Eden)
5
SOuTh WEST rEgIOn
PTH 1 Rehabilitation at Assiniboine River (Vicinity of Brandon)
PTH 2 Rehabilitation at Souris River (Vicinity of Wawanesa)
PTH 2 Replacement at Cypress River (East of Cypress River)
PTH 10 In Brandon: New 18th Street Bridge over the Assiniboine River
PTH 16 Rehabilitation at Assiniboine River (West of Russell)
PR 250 Rehabilitation at Assiniboine River (North of Alexander)
PR 253 Replacement at Pembina River (West of Pilot Mound)
PR 264 2 Replacements at Arrow River (Vicinity of Decker)
6
WEST CEnTrAl rEgIOn
PTH 5 Replacement at Bield Overpass (East of Roblin)
PTH 5 Replacement at Drain (21-19-15W) (Vicinity of Kelwood)
PTH 5 Replacement at Drain (33-19-15W) (Vicinity of Kelwood)
PTH 5 Rehabilitation at Lake of the Prairies (West of Roblin)
PTH 6 Replacement at Burnt Lake Drain (North of Lundar)
PTH 6 Rehabilitation at Homebrook Drain (at St. Martin Junction)
PTH 68 Replacement at Hansen Drain (East of Ste. Rose du Lac)
PR 489 Replacement at Tributary to Garland River (South of Duck River)
PR 513 Replacement at Partridge Drain (Northeast of St. Martin)
7
du LacSte. Rose
Minnedosa
Roblin
Russell
RiverSwan
Stonewall
Neepawa
DAUPHIN
24
19
45
45
83
49
57
83
83
83
4242
41
50
50
68
68
68
20
20
5
5
520
5
5
10
10
20A
10A
10A
10
10
77
60
60
10
10
17
17
6
6
6
21
364
272
491
273
489
271
267
362
276
276
269
364
269
593
484
367
274
367
591
594
584
584 366
366
485
488
486
366
486
275
279
268
268
363
264
359
359
476
478
476
264
470
566
577
350352
352
464466
465
262
250
354
355
270
355
264
469
474
472
571
467
256
568
545
487
588
587
266
279
365
327
231
512
419
229
418
325
419
417
278
361
360480
582
248430
411
242
567
569
575
265265
261
462
462
261
260
260
357
262
265
471
262
250
270
354
547
482
549
584
592
583
366
274
579
478
233
483
475
322
236
415
323
322
518
416
415
233
32
325
233
224
513
237
237
513
239
328
481
481490
16A
16
16
16
Partridge Creek
Homebrook Drain
Tributary to Garland River
Drain
Drain
Burnt Lake Drain
Lake of the PrairiesBield OverPass
Hansen Drain
Prepared by:Construction Support ServicesNovember 2006
LEGEND
WINTER ROADS
HIGHWAY NETWORK
Bridges in Year 2007/2008
Bridges in Year 2008/2009
Bridges in Year 2009/2010
Bridges in Year 2010/2011
Bridges in Year 2011/2012
0.0 7.5 15.0 22.5 30.0 37.5
Kilometers
PROVINCE OF MANITOBABRIDGE INFRASTRUCTURE CAPITAL PROGRAMWEST CENTRAL REGION2007/2008 - 2011/2012
�
nOrThErn rEgIOn
PTH 6 Rehabilitation at North Three Rivers (49.3km South of Grand Rapids)
PTH 6 Rehabilitation at Centre Three Rivers (49.6km South of Grand Rapids)
PTH 6 Rehabilitation at South Three Rivers (52.6km South of Grand Rapids)
PTH 6 Replacement at North Morrison Creek (11.7km South of Grand Rapids)
PTH 6 Replacement at South Morrison Creek (18.2km South of Grand Rapids)
PTH 6 Rehabilitation at Minago River (57.2km South of Ponton)
PTH 6 Rehabilitation at Two Rivers Diversion (76.9km South of Grand Rapids)
PTH 6 Rehabilitation at William River (85.0km North of Grand Rapids)
PTH 10 Replacement at Big Island Lake (South of Flin Flon)
PR 283 Rehabilitation at Pasquia River (West of The Pas)
WR 730 New Modular Structure at God’s Lake Narrows
PR 800 Replacement at Mistik Creek (East of Flin Flon)
Top Related