www.imtfiber.com [email protected] 08039576767 Page 0
IMTFIBER NIGERIA
BIDDING FOR A FIBER PROJECT
PROJECT DOCUMENTATION TIPS
1/1/2016
ADEJOLA JOHNSON Msc. CEO Imt computers Nig. Ltd
FOA Representative in Nigeria #718
www.imtfiber.com [email protected] 08039576767 Page 1
BIDDING FOR FIBER PROJECT
Telecom infrastructure development business such as fiber optics implementation
and maintenance projects involve serious contest and bidding because of what is
involved in it.
Fiber project Bidding starts with document and documentation, some of which are
discussed bellow
1. RFP……………….. 'Request for Proposal
A type of bidding solicitation in which a company or organization announces that
funding is available for a particular project or program, and companies can place
bids for the project's completion. The Request for Proposal (RFP) outlines the
bidding process and contract terms, and provides guidance on how the bid should
be formatted and presented. A RFP is typically open to a wide range of bidders,
creating open competition between companies looking for work
It presents preliminary requirements for the commodity or service, and may dictate
to varying degrees the exact structure and format of the supplier's response.
Effective RFPs typically reflect the strategy and short/long-term business
objectives, providing detailed insight upon which suppliers will be able to offer a
matching perspective.
www.imtfiber.com [email protected] 08039576767 Page 2
The prospective contractor respond to this document and proceed to collect the
SOW (scope of work) document
2. SOW A statement of work (SOW) is a formal document that captures
and defines the work activities, deliverables, and timeline a vendor must
execute in performance of specified work for a client. The SOW usually
includes detailed requirements and pricing, with standard regulatory and
governance terms and conditions. It thus overlaps in concept with a contract,
and indeed SOWs are often legally equivalent to contracts. In Fiber
OSP/ELP projects, there are some key areas to understand if the project
contractor should deliver the mindset of the client
Areas addressed in SOW
Project topic…
Document (SOW) number
Executive summary: This reveals the company, the project and the
objective of the project, the project name, the total distance of the project
Technical specification: This explains the technical aspect of the project.
Which include information about the Site Specification such as the number
of sites to connect, the sites name, sites code, longitude and latitude of each
affected sites
Ducting and Fiber Specifications: This aspect contains what the client
wants about the depth of the trench, the laying of the ducts and sub-ducts,
www.imtfiber.com [email protected] 08039576767 Page 3
the fiber core number and enclosure configuration, This largely depends on
whether the project the Backbone or Metro fiber
RoW Strategy: Right of way strategy specifies how the permission from the
relevant authority should be taken.
Infrastructure Acceptance Process, inspection of all equipment elements
and performance of the network checking of the link, the various test to be
conducted, certificate of acceptance (CFA) which will qualify the contractor
to submit an invoice for payment.
Project management/ Project plan: project Organization ( this describes a
company profile with a personnel resources, detailed project plan, an
organization chart for the project with the name and function of the key
persons participating in the project organization and their experience in the
fielding, progress Reports, and As-Built Documentation
Conclusion
3. RFQ……. Request For Quote
A Request For Quote is a variation of a Request For Proposal (RFP), and typically
provides more information to the bidder about the project's requirements. It often
requires the bidder to break down costs for each phase of the project so as to allow
the soliciting company to compare different bids
The following document is an example of RFQ Template
www.imtfiber.com [email protected] 08039576767 Page 4
Item Information
RFQ reference number
Trading name
Company registration number
Company's physical address
Date
Company telephone and fax numbers
Contact name and telephone number
Description of goods and/or services
Unit of measure
Price per unit
Quantity of goods and/or services
Delivery basis
Other charges
Currency
Exchange rate used for conversion into
country currency
Total
Discounts
VAT amount for VAT)
Vat number
Payment terms 50% at Mobilization, 50% at PAT/FAC
Delivery period/schedule X days
Validity X days Validity
Other If any
www.imtfiber.com [email protected] 08039576767 Page 5
4. BOQ….Bill Of Quantity
As the name implies this document is an important document that requires
much details about the surveyed route. This document will spell out various
activities that will be carried out during the project implementation as well
as the cost implication or respective column.
Ducting Infrastructure-Section 1
Detailed Survey Documentation
Cutting and Restoration of Concrete road
Excavation of soil and Backfilling
o Trench sample S1/R1
o Trench sample S2/R2
o Trench sample S3/R3
Excavation of soil and Backfill including restoration of Lawns and flowers
Cutting and Restoration of Asphalt road
Bridge crossing route
Supply and Installation 110mm PVC Duct
Supply and Installation 110mm Steel Duct
Supply and Laying/Pulling of 40mm HDPE Sub-Duct
No. Description Unit Qty Unit Price Total Price
www.imtfiber.com [email protected] 08039576767 Page 6
Manhole -Street Type
Calibration of existing / new duct
Thrust boring of 110mm steel duct
Removal and Restoration of paving stones
Warning Tape
Ducting Infrastructure-Section 2
Detailed Survey Documentation
Supply and Laying/Pulling of 40mm HDPE Sub-Duct
Calibration of existing / new duct
Drilling of Existing Walls & Manhole and Reinstatement (For Joint existing
Manhole)
Ducting Infrastructure-Section 3 Carried to Summary
Detailed Survey Documentation
Cutting and Restoration of Concrete road
Excavation of soil and Backfill
Trench sample S1/R1
Trench sample S2/R2
Trench sample S3/R3
Cutting and Restoration of Asphalt road
Supply and Installation 2110mm PVC Duct
Supply and Installation 110mm Steel Duct
Supply and Laying/Pulling of 40mm HDPE Sub-Duct
Manhole -Street Type
Calibration of existing / new duct
www.imtfiber.com [email protected] 08039576767 Page 7
Thrust boring 110mm steel duct
Drilling of Existing Walls & Manhole and Reinstatement(For Joint existing
Manhole)
Removal and Restoration of paving stones
Warning Tape
Fibre Optic Cable Supply, Installation and Testing
Fibre Optic Cable (ITU-T standards
ODF Cabinet
Pigtails (of specified length)
96 Port FOC Patch Panel
Installation of 96 core OFC
Fibre Patch Cords(Duplex)-ITU-T G.652/SC-LC connectors(6m-10m
Fibre Patch Cords(Duplex)-ITU-T G.652/SC-SC connectors(6m-10m
Fibre Patch Cords Duplex)-ITU-T G.652/SC-FC connectors(6m-10m
Closure (96 core) (to include Optical splice point)
Splicing of 96 core OFC
Termination of 96 core OFC
Testing
Project Management, As-Built Documentation
As-Built Documentation
Ducting Civil works
Project Management
Summary
www.imtfiber.com [email protected] 08039576767 Page 8
Maintenance
One year maintenance (excludes Manhole or Hand hole, thrust boring, major
works and concrete )
5. PROJECT ORGANISATION CHART
Civil Site Managers
(FOC) Civil Site Managers
(FOC)
Trench
Supervisors Trench
Supervisors
Trench/Asphalt and
concrete Cutting Workmen
Trench/Asphalt and
concrete Cutting Workmen
Top Management
Project Manager (OFC)
OFC Site Manager Head Logistic
/Warehousing
OFC
Technicians Logistic Officers Drivers
www.imtfiber.com [email protected] 08039576767 Page 9
6. PROPOSED IMPLEMENTATION PLAN
This is a document that states the tasks to be performed, the duration of each task,
the start and finish date of each task. This document is very important to the client
for monitoring. Microsoft project software is mostly used to prepare this schedule.
The work flow is graphical displayed using GANNT Chart
ID TASK NAME DURATION START FINISH
PRE- FIBRE OPTIC CABLE
INSTALLATION
PO & ITP received 1 day
Project/Implementation plan approval 1 day
Fiber Optic cable drum testing 1 day
Mobilization of Personnel, Materials and
Equipment to site
3 days
SECTION 1 38 days
Excavation of Trench path(200/day) 38 days
Asphalt cutting 20 days
Concrete Cutting 18 days
www.imtfiber.com [email protected] 08039576767 Page 10
Excavation of Manhole pits 20 days
Planting of JBs 18 days
Crossing of bridge 2 days
Thrust boring of Asphalt road crossing 10 days
Laying of PVC ducts 27 days
Installation of HDPE duct 23 days
Backfilling/Laying of warning tape 27 days
Compaction of Normal soil 17 days
Reinstatement of concrete and Asphalt routes 20 days
Casting of Reinforced concrete envelope 5 days
ROW Clearing 22 days
Civil work acceptance 1 day
FIBRE OPTIC CABLE INSTALLATION,
TESTING AND DOCUMENTATION
37 days
As-Built Documentation 20 days
OFC blowing 19 days
OFC jointing and Splicing 3 days
OFC termination at BTS 3 days
Testing of OFC 3 days
www.imtfiber.com [email protected] 08039576767 Page 11
Final Acceptance Test 2 days
NOTE: the task and duration in the table above is just an example of template
7. METHOD STATEMENT DOCUMENT
This a project document that states the methodology of project
implementation. This document reveals Team composition, Mobilization to
site, Civil works (trenching), Cable installation, splicing and testing,
Maintenance Services and Equipment Schedule for Fiber Installation and
Maintenance. How each will be achieved are given below.
A. Team composition.
A good implementation team will include the following personalities
1. Team leader
2. Splicing Technician
3. Civil work Technician
4. OTDR Technician
5. Pick-up truck Driver
6. Splice van Driver
7. Casual Labour
B. Mobilization to site
The materials, equipment and personnel needed for the execution of the project in
the various cities shall be transported to the locations.
This will take a period of 1-3 days depending on the location
www.imtfiber.com [email protected] 08039576767 Page 12
C. Civil works (trenching)
Here the contractor needs to explain how the civil work of the project will be
carried out in succession. The depth of the trench, Duct installation, manhole
specification as stated by the client.
D. Cable installation, splicing and testing
Fiber Cable Installation method (Hand pulling, blowing…..)
Splicing: splicing techniques (fusion splicing, mechanical splicing or Ribbon
splicing) and testing of the installed cable
E. Maintenance Services
It is expected of the contractor to indicate the maintenance approach to be
adopted and the reason for the chosen one
1. Preventive Maintenance
2. Corrective Maintenance
3. Pre-scheduled Corrective Maintenance
F. Equipment Schedule for Fiber Installation and Maintenance
Apart from revealing the team composition (personnel) it is also expected of
the contractor equipment availability and readiness. Some of the basic
implementation equipment are stated below
Pre-cast manhole manufacturing and curing facility
www.imtfiber.com [email protected] 08039576767 Page 13
Nos of Delivery vans
1 No Self loader Truck (Hiab
Available Fibre Test Equipment
Available Splicing equipment
8. WORK FLOW
TEAM COMPOSITION
MOBILISATION TO SITE
CIVIL WORK (Trenching)
Cable installation,
Splicing, Testing
Maintenance services
Safety
Equipment Schedule
WORK FLOW
www.imtfiber.com [email protected] 08039576767 Page 14
www.imtfiber.com