Download - Automated Parameter Optimization of a Water Distribution

Transcript
  • 7/24/2019 Automated Parameter Optimization of a Water Distribution

    1/16

    71

    IWA Publishing 2013

    Journai of iHydroinformatics | 1 5 1 | 2013

    Automated parameter optimization of

    water distribution

    system

    Maikel Mndez, Jos A . Araya and Luis D. Snchez

    ABSTRACT

    The hydraulic model EPANET was applied and calibrated for the water distribution system (WDS) of La

    Sirena, Colombia. The Parameter ESTimator (PEST) was used for parameter optimization and

    sensitivity analysis. Observation data included levels at water storage tanks and pressures at

    monitoring nodes. Adjustable parameters were grouped into different classes according to two

    different scenarios identified as constrained and unconstrained. These scenarios were established to

    evaluate the effect of parameter space size and compensating errors over the calibration process.

    Results from the unconstrained scenario, where 723 adjustable parameters were declared, showed

    that considerable compen sating errors are introduced into the optimization process if all parameters

    wer e open to ad justment. The constrained scenario on the other h and, represented a more properly

    discretized scheme as parameters were grouped into classes of similar characteristics and

    Insensitive parameters w ere fixed . This had a profound impact on th e param eter space as adjustable

    parameters we re reduced to 24. The constrained solution, even whe n it is valid only for the system s

    normal operating conditions, clearly demonstrates that Parallel PEST (PPEST) has the potential to be

    used in the calibration of WDS models. Nevertheless, further investigation is needed to determine

    PPEST s perfo rman ce in complex WDS models.

    Key words

    | calibration, EPANET, model, optimization, parameter, sensitivity

    iVlaikel Mndez

    (corresponding author)

    Jos A Araya

    Centro de Investigaciones en Vivienda y

    construccin (CIVCO), Escuela de ingeniera en

    Construccin,

    Instituto Tecnolgico de Costa Rica,

    APDO 159-7050,

    Cartago,

    Costa Rica

    E-mail:

    mamendez@itcr ac cr

    Luis D S nciiez

    Instituto Cinara,

    universidad del Valle - Facultad de Ingeniera,

    Cali,

    Colombia

    INTRODUCTION

    W ater distribution system (WDS) models canbeused foravar-

    iety of purposes including design, managem ent, m aintenance,

    planning and scenario studies. Nevertheless, in order to be

    reliable

    a model must adequately predict the behavior of the

    actual system under a wide range of conditions and for an

    extended period of time (Machell

    et al

    2010). This can b e

    accom plished by calibrating th e m odel using a set of field

    measurements or observations, mainly water storage tanit

    (WST) levels, nodal pressures and flow rates. The calibration

    ofa W Smodeliscarried out by optimizingthevalues of

    phys-

    ical and conceptual parameters involved in the model,

    including pipe roughness-coefficients, minor losses, demand

    pattern factors, nodal demands, control valves and pump

    characteristics (USEPA2005; Koppel Vassiljevaoog).

    Calibration is also referred to as an inverse problem,

    since observed values are quantitatively compared to

    doi: 10.2166/hydro.2012.028

    model predictions until the optimum set of parameters is

    found (Gallagher Doh erty 2007). A mo del is considered

    to be calibrated for one set of operating conditions if it

    can predict outcomes

    with

    reasonable agreement. Neverthe-

    less, this does not necessarily imply calibration in general.

    Models should be calibrated over a wide range of operating

    conditions so that the modeler can rely on model predic-

    tions (Walski 1986). As models are only approximations of

    the actual systems

    that are

    being represen ted, the reliability

    of model predictions depends on how weU the model struc-

    ture is deflned and how well the model is parameterized

    (Hogue et al 2006).

    A critical step in m odel calibration relates to the quality

    and density of observation data which may contain

    significant measurement errors. Even small measurement

    errors can lead to large errors in estimated parameters

  • 7/24/2019 Automated Parameter Optimization of a Water Distribution

    2/16

    72 M Mndez eta l Automated parameter optimization of a water distr ibution system

    Journal of Hydroinformatics | 15 1 { 2013

    (Goegebeur Pauwels 2007). As observation data accuracy

    migbt be in tbe same order of magnitude of tbe measure-

    ment errors, including this kind of data in tbe calibration

    process will most likely produce misleading results. Only

    accurate observation data sbould be used for calibration.

    Walski

    et al

    (2004) suggest tbat very high quality field

    data (e.g. pressure and elevation data) would be accurate

    to 0.1 m. Good quality field data are considered accurate

    to m. Model predictions would significantly deteriorate

    wb en field data are accurate to 3 m, whicb reflects po orly

    collected data. On the other hand, sufficient observation

    data may be infrequent an d only collected at select locations

    (Kang Lansey 2009). Tbis is particularly true in develop-

    ing countries wbere severe limitations constrain the scope

    and success of public sector projects, particularly water

    supply and water quality (Lee Scbwab 2005).

    Calibration by param eter optim ization is a bigbly under-

    determined problem as the number of unlaiowns is greater

    than the number of observations (Walski

    et al

    2006). In a

    real system, tbere can be hundreds of unlmowns and only

    a relatively small number of observations. As tbe number

    of unknowns greatly exceeds the number of observations,

    tbere is little confidence in the model predictions. Tbere

    can be too many solutions tbat yield equally good results

    in terms of a predefined objective function witbin the

    model's parameter space (Duan

    et al

    1992). Tbis situation

    has resulted in tbe development of tbe concept of 'equifinal-

    ity' which recognizes that alternative sets of control

    parameters within a model are capable of producing reason-

    able estimates of the system response as measured by

    objective functions defining tbe goodness of fit (Beven

    Binley 1992; Fang Ball 2007). Tbis ambiguity bas serious

    impacts on parameter and predictive uncertainty and conse-

    quently limits tbe applicability of a model. To reduce tbe

    number of unlcnowns and improve reliability on model pre-

    dictions, the parameter space must be constrained (Walski

    et al 2004).

    An obvious constraint for any model would be grouping

    param eters into classes of similar cbaracteristics (e.g. groups

    of same internal diameter, m aterial, demand sector, etc.). If

    all parameters witbin a model are open to adjustment,

    mo delers m igbt end u p d oing wb at Walsld (1986) calls 'Cali-

    bration by compensating errors'. An error in tbe estimated

    roughness can be compensated for by an error in demand.

    Compensating errors can take over tbe calibration process

    and produce numerically correct, but pbysically meaning-

    less, solutions. Under these circumstances, a model would

    be matcbing observations rather than determining the sys-

    tem's optimal parameters. On the other hand, only those

    parameters sensitive to field observations sbould be

    included in the calibration p rocess. If insensitive para meters

    are included, the parameter space would increase and

    model predictions will have littie chance of improving tbe

    goo dne ss of fit (Zagblou l Abu Iefa 2001).

    Model calibration b as traditionally been a trial-and-error

    process. In tbis approach, values of selected parameters are

    individually adjusted in a systematic manner until corre-

    lation between observed and modeled values no longer

    improves. Calibration by trial-and-error is a time-consuming

    and difficult task, as tbe large number of potential

    unlinowns makes it impossible to analytically solve all cali-

    bration parameters (Walski et al 2006). Wben a trial-and-

    error optimization approacb is followed, tbe goodness of

    fit of tbe optimized model is essentially based on tbe mode-

    ler's judgmen ts and experience (Ibrabim Liong 1992; Kbu

    et al

    2006). Since the judgment involved is subjective, it is

    difficult to explicitiy assess tbe confidence of tbe model pre-

    dictions (Kumar et al 2009). As deviations between

    observed and modeled values migbt be outside tbe accepta-

    ble tolerance range, a mucb more 'tuned' optimization may

    be required. In tbis case an automated optimization

    approacb may be used.

    In an automated optimization app roacb, parameters are

    adjusted automatically according to a specified search

    scheme and quantitative numerical measures of tbe good-

    ness of fit (Skahill Dob erty 2006). Tbe development of

    automated optimization procedures bas mainly focused on

    using a series of objective functions to evaluate the goodness

    of fit of the o ptimized m odel. Algorithms try to minim ize tbe

    deviations between the observed and modeled values in

    order to find the global minimum of tbe selected objective

    function (Savic

    et al

    2009). Nevertbeless, as calibration is

    a bighly underdetermined problem, it is impossible to

    know whether any automated or manual calibration

    approach is actually correct. This situation migbt worsen if

    an automated calibration approach is followed, as cali-

    bration algorithms might contain little knowledge of the

    physical laws that govern a model's structure.

  • 7/24/2019 Automated Parameter Optimization of a Water Distribution

    3/16

    73 M Mndez e al Automated parameter optimization of a water distr ibution system

    Journai of Hydroinforma tics | 15 1 | 2013

    Several automated techniques have been used to cali-

    brate WDS models including genefic algorithms (Jamasb

    et

    al

    2oo8; Nicklow et

    al

    2009; Kovalenkoe t

    al

    2010), B aye-

    sian-type procedures (Kapelan et al 2007) and Markov

    Chain Monte Carlo simulations (Peng

    et al

    2009). V arious

    calibration tools have been incorporated into commercially

    available software packages including WaterGEMS's

    Darwin-Calibrator (Wu

    et al

    2002; Walski

    et al

    2006),

    H2ONET Calibrator (Wu et al 2000) and InfoWafer Cali-

    brator (de Schaetzen et al 2010). Although these

    applications are robust and well proven, little attention has

    been paid to end-user applications and product development

    (Abe & C heung 2010). This is particularly true in the context

    of free and open source software applicafions. Water ufilifies

    in developing countries might not have access to commer-

    cial packages due to budget restricfions. Still the use and

    proper calibrafion of WDS models is a necessity.

    The parameter estimator package PEST; an acronym for

    Parameter ESTimation (Doherty 2005) might eventually be

    used to calibrate a WDS model such as EPANET (Rossman

    2000).

    PEST offers several strategic advantages to m odelers.

    Firstly, PEST is a model-independent application. This

    avoids changes to the original code as it communicates

    with a model through its own input and output files. Sec-

    ondly, PEST has successfully been used to calibrate

    numerous types of models including, groundwater models

    (Doherty 2005; Christensen & Doherty 2008), hydroiogicai

    models (Arabi

    et al

    2007; Immerzeel & Droogers

    2008;

    Bah-

    remand & de Smedt 2010), soil layer and soil moisture

    analysis (Tischler

    et al

    2007) and hydraulic models

    (Koppel & Vassiljev 2009; Maslia

    et al

    2009). Thirdly,

    PEST can be used to carry out various predictive and

    exploratory tasks including sensitivity, correlation and

    uncertainty analysis. Fourthly, PEST is freely available fo

    the public and is user-oriented. As modeling of WDSs is

    just emerging in developing regions, particularly in small

    water supply systems (municipalifies and rural commu-

    nifies), it would be of great importance to explore the

    possibility of using available free and open source software

    applications in this context. This would gradually promote

    a 'modeling culture' which may generate demand for more

    comprehensive, commercially available tools.

    The aim of this study is to determine if model indepen-

    dent parameter estimator PEST can be used to develop a

    fully calibrated extended-period model for a WDS using

    the public domain model EPANET.

    METHODOLOGY

    La Sirena's WDS was used as a case study to examine the

    advantages of using a fully automated optimization

    approach versus a trial-and-error opfimization. La Sirena is

    a rural community located in the department of Valle del

    Cauca, Municipality of Cali, Colombia (Figure 1).

    The system is served by a single mulfi-stage filtrafion

    (MSF) water treatment plant which produces approximately

    0.012 m'' s ^ and consists of small diameter PVC pipes, ran-

    ging from 20 to 85 mm (Table 1). The system contains four

    ground WSTs that create four different pressure zones

    (Figure 1). Each WST is equipped with a Float Actuated

    Valve (FAV) that co ntrols flow admission an d p revents over-

    flow. Isolation valves prevent flows among pressure zones.

    A comp lete topographic survey of the system was performed

    using a total station which allowed elevation data to be accu-

    rate to 0.02 m.

    Since the system co nsists mainly of small diameter pipes

    and minor losses could have a significant impact, the

    number of fitfings for each individual pipe was carefully

    identified. The types of fittings included tees, elbows,

    bends, contracfions, expansions and fully open isolafion

    valves. Mino r loss coefficients (K) we re assigned to thes e fit-

    tings based on typical values found in the literature (Mays

    2000

    Observation data for the calibration process included

    water levels in the four storage tardes and nodal pressures

    in seven nodes (Figure 1). A period of 7 consecutive days

    (168 hr) was used for observafions recording. Observafions

    were taken during normal operafing conditions and there-

    fore,

    considered highly representative. Pressure gauges

    used to record nodal pressures were accurate to

    m while

    pressure sensors at WSTs were accurate to 0.1 m. The fime

    interval of water level and nodal pressure observafions

    was 60 min, sparsely distributed through out the enfire

    recording period. In most cases, these observations rep-

    resent discrete values recorded at the top of the hour. As

    recommended by Walski

    et al

    (2001), when possible, nodal

    pressure observafions were performed at maximum head

  • 7/24/2019 Automated Parameter Optimization of a Water Distribution

    4/16

    74 M. Mndez eta i Automated parameter optimization of a water distribution system

    Journal of Hydroin fortnatics | 15 1

    2013

    /

    y il

    ^

    >v II

    \

    y

    Legend:

    isolation Vaiv es

    Monitoring Node s

    A Wate r Storage

    Tanks

    Pressure Zone 1

    i Pressure Zone 2

    1 Pressure Zone 3

    , I

    i ; Pressure Zone 4

    0 75 150 225 300

    1 , 1 , 1

    Scaie in Meters

    Figure 1 I La Sirena s water distribution s ystem mod el.

    Tabie 1 I Town of La sirena s water d istribution system characteristics

    C o m p o n e n t Quanti ty

    Number of nodes

    Number of pipelines

    Float Actuated Valves (FAVs)

    Internal pipe diameter range (mm)

    Total pipeline lengtb (m)

    Water storage tank, elevation ( MASL)

    and capacity (m'^)

    Tank 1

    Tank 2

    Tank 3

    Tank 4

    325

    27 9

    5

    20-85

    9,554

    1 178;56

    1,113; 79

    1 112;200

    1 097;54

    Meters above sea level.

    loss,

    which also corresponded to the system's highest water

    demand.

    At the time the field data were collected, there was a

    total of 851 consumers registered in the Water Utility

    records. Each consumer was supplied with a flow meter

    which was read once a month. This information was used

    to estimate and allocate water demand per consumer.

    A period of 12 months between 2009 and 2010 was ana-

    lyzed for this purpose. Nearly 96% of water demand was

    classified as residential. The remaining 4% was classified

    as commercial and/or industrial. A point-based method

    was used for nodal demand allocation. This required a

    detailed field survey to determine the precise number of

    households that were connected to the WDS.

    As actual

    flow

    meter locations were k now n, a spatial func-

    tion was used to assign each meter to the closest demand node

    (Cabreraet l 1996). To include u nacc oun ted for water, field

    measurements of production and metered consumption were

    recorded and compared during a period of 24 hr and then

    added proportionally to nodal demands. Estimations of leak-

    age for each pressure zone were prepared from night flow

    and water level measurements. Nevertheless, severe inconsis-

    tencies regarding consum ption records an d tmaccounted-for-

    water estimations were detected. Therefore, nodal demand

    exhibits the highest input data uncertainty for this case study.

    This situation has been identified in the literature

    (Lansey & Basnet 1991; Kenw ard & H ow ard 1999; Zho u

    et l

    2000) and solutions such as on-line implementation

    of Supervisory Control and Data Acquisition (SCADA) sys-

    tems have been suggested to improve knowledge of water

  • 7/24/2019 Automated Parameter Optimization of a Water Distribution

    5/16

    75 M Mndez et

    a l \

    Automated parameter optimization of a water distr ibution system

    Journai of Hydroinformatics | 15 1 | 20 13

    dem and temp oral variation (Kang Lansey 2009; Machell

    et al.

    2010). However, SCADA systems are beyond the

    reach of most water utilities in developing countries. In

    recent years, researchers have identified the necessity to

    include uncertainty in the calibration of WDS models

    including pipe roughness coefficients and nodal demands

    (Alvisi Fran chini 2010; Giustolisi Berard i 2on ). Uncer-

    tainty quantification of model parameters such as nodal

    demands implies a profound knowledge of the system and

    the availability of sufficiently long time series data. Again,

    this might not be the case for many water utilities.

    Demand patterns for each WST and their respective

    pressure zones were constructed by analyzing diurnal

    dynamics of water demand. These temporal variations

    were measured for various consumers of each pressure

    zone. The effect of the day of the week on the demand pat-

    tern s wa s also analyzed . Since significant differences

    between weekday and weekend consumption w ere detected,

    two 24-hr diurnal demand patterns (with a temporal resol-

    ution of

    hr) were constructed for each pressure zone;

    one known as weekday demand pattern (Monday to

    Friday) and the other known as weekend demand pattern

    (Saturday and Sunday). In total, eight 24-hr demand patterns

    for the entire system w ere con structed. As this project faced

    budget limitations, it was not possible to obtain an indepen-

    dent set of data that could have been used for model

    validation.

    Parameter o ptimization

    Calibration and sensitivity analysis of EPANET were per-

    formed using PEST, a nonlinear parameter estimation and

    optimization package, which offers model independent

    optimization routines (Doherty 2005). PEST is based on

    the Gauss-Marquardt-Levenberg algorithm (GML) which

    searches for the optimum values of the model parameters

    by minimizing the deviations between field measurements

    (observations) and modeled values (predictions). PEST

    uses the sum of the squared deviations PHI (0) as its objec-

    tive function (Skahill 2009) and can be mathematically

    expressed as:

    (1)

    where n equals the total number of observations, O, the

    observed value on timestep i. Mi is the modeled value on

    timestep i an d w is the relative weight attached to each

    observed value.

    At the beginning of each iteration timestep, the relation-

    ship between model parameters and modeled output values

    is evaluated for the current set of parameters. For instance,

    the derivatives of all observations with respect to all adjusta-

    ble parameters must be calculated. These derivatives are

    stored as the elements of a Jacobian matrix used for sensi-

    tivity an alysis.

    During each iteration timestep, PEST varies each adjus-

    table parameter incrementally from its currently estimated

    value and re-runs the model. The ratio of modeled output

    differences to parameter differences approximates the

    derivative. For greater accuracy in derivatives' calculation,

    parameter values can be both increased or decreased until

    the objective function PHI is minimized. PEST determines

    whether additional iterations are required by comparing

    the parameter change and objective function improvement

    achieved through the current and previous iterations

    (Skahill Do herty 2006).

    PEST also calculates a composite relative sensitivity for

    each adjustable param eter wh ich me asures the sensitivity of

    all observations with respect to a relative change in the

    value of that specific parameter. The sensitivity of a par-

    ameter describes the effect that a variation on that specific

    parameter has over the whole model generated values. Sen-

    sitivity is a useful indicator for assessing the degree to which

    a parameter is capable of estimating the variables on the

    basis of the o bservation dataset available for mo del optimiz-

    ation (Doherty 2005).

    PEST communicates with a model through the

    model's own input and output files. For PEST to be able

    to take control of the model, the model itself must be

    executable from the command line. Hence, the optimiz-

    ation of a model can be carried out without the

    requirement for the model to undergo any changes in its

    original structure.

    To couple EPANET with PEST, several input files must

    be prepared (Figure 2). In the case of EPANET, the model's

    master input file has a suffix 'inp' (Rossman 2000). This

    ASCII-file contains all the necessary information to run

    EPANET from the command line using the EPANET2D.EXE

  • 7/24/2019 Automated Parameter Optimization of a Water Distribution

    6/16

    76 M. Mndez et

    al \

    Automated parameter optimization of a water distribution system

    Journal of Hydroinformatics | 15 1 | 20 13

    f

    Model liiput:

    EPANET AS CII file

    MNP)

    >

    f

    Read m odel input and

    replace input

    parameters on

    PPESTtemplate files

    *. TPL; MN S)

    Define objectives:

    Model parameters +

    observations series

    Model:

    EPANET2D.EXE

    >

    PPEST.exe

    Programa modules

    control over EPANET

    Analysis *. PST)

    >

    >

    >

    f

    Reads and compare

    mode l simulations

    againts observed

    values *. INP)

    Figure 2

    I Coupling schematics of EPANET and PEST.

    extension. After EPAN ET is run, ASCII and binary files with

    the suffixes txt and grd are respectively created. For PEST,

    three types of input files must be created; a template files

    (with suffix tpl ) wh ich is basically a copy of the inp

    input-file, a con trol file (with suffix pst ) w hich con tains

    all the PEST S control an d nu meric param eters, and finally

    an instruction file (with suffix ins ), which allows PEST to

    properly read observations from the E PAN ET s txt

    output-files. In the course of the optimization process,

    PEST creates several output files which are stored for later

    inspection (Doherfy 2005).

    In mo st cases, the bulk of PEST s run time is consum ed

    in running the model

    itself

    Therefore, a special version of

    PEST lmown as Parallel PEST (PPEST) was used instead.

    PPEST does not only have all the functionalities of PEST

    but also facilitates a dramatic enhancement in the optimiz-

    ation performance by allowing PEST to run in parallel.

    This is particularly useful when the amount of adjustable

    parameters and the model run-times are large. It also

    allows modelers to take full advantage of the most recent

    and powerful multi-core processors, significantly reducing

    the time needed to achieve convergence.

  • 7/24/2019 Automated Parameter Optimization of a Water Distribution

    7/16

    77 M Mndez et a/ Automated parameter optimization of a water distribution system

    Journal of Hydroinformatics | 15 1 | 2013

    Model setup

    Model optimization for the La Sirena's WDS was achieved

    in two steps. In the first step, a trial-and-error approach

    was followed. Values of the selected p aram eters were indivi-

    dually modified in a systematic manner until correlation

    between observations and modeled values no longer

    improved. Three groups of parameters were taken into

    account for tbis step: demand pattern factors [-], nodal

    demands (L/s) and (C-factors) [-].

    In the second step, an automated parameter optimiz-

    ation process was executed by linking EPANET with

    PPEST. Two different scenarios identified as 'constrained'

    and 'unconstrained' were establisbed to evaluate tbe effects

    of parameter space size and compensating errors over tbe

    PPEST calibration process. In botb scenarios, 12 parameter

    groups were created and tbey included: demand pattern fac-

    tors [-], nodal demands (L/s), local losses [-], (FAVs) [-] and

    C-factors [-] (Table 2).

    For tbe constrained scenario, a total of 24 adjustable

    parameters were declared. Demand pattern factors were

    fixed to their original values as sufficient confidence was

    obtained during their derivation. Nodal demands were

    aggregated into four different demand groups, one for each

    pressure zone. The same demand multiplier was assigned

    to each node witbin eacb demand group. Tberefore, all

    nodes experienced a proportionally equal cbange in

    demand witbin each specific pressure zone. Minor loss

    Tab ie 2 I Set of control settings used for ppEST

    coefficients (K) for fittings were not adjusted either. FAVs

    loss coefficients w ere adjusted as significant differences

    between manufacturer's curves and field bebavior were

    detected. Tbrottle Control Valves (TCVs) were used in

    EPANET to simulate FAVs. TCVs are commonly used to

    simulate a partially closed valve by adjusting tbe minor

    head loss coefficient of the valve (Rossman 2000). C-factors

    were classified into groups of tbe same pipe diameter. No

    distinction was made regarding the age of tbe pipes as tbe

    entire system w as co nstructed of relatively yotmg PVC.

    For tbe uncon strained scenario, a total of 723 adjustable

    parameters were declared, which accounted for the 12

    parameter groups mentioned above. Each parameter within

    these groups w as individually adjusted by PPEST. Nevertbe-

    less, a unique C-factor was used for all pipes in the system.

    Observations in botb scenarios, wbicb included water

    levels and no dal pressures, were group ed in five observation

    groups, four for WSTs and one for monitoring nodes. Since

    observations were of two different types, the objective func-

    tion relative weight attached to each observation, varied

    according to its relative impo rtance in tbe overall pa rame ter

    estimation process. Consequently, greater weigbts were

    assigned to water level observations since tbey were con-

    sidered more reliable tban tbose of tbe nodal pressures.

    Concerning tbe ranges for parameter adjustments, a

    30%

    variation for demand patterns factors was allowed

    for tbe un constrain ed scenario (Table 3). As severe inconsis-

    tencies regarding consumption records and unaccounted-

    for-water estimations were detected, a 30% and 50%

    variation in nodal demands multipliers were assigned to

    item

    Number of adjustable parameters

    Num ber of fixed parameters

    Number of tied parameters

    Number

    of observation groups

    Num ber and type of parameter groups

    Demand patterns factors

    Nodal demands

    Minor loss coefficients (Ks)

    Float Actuated Valves (FAVs) loss

    coefficients

    C-factors

    Scenario

    Constrained

    723

    0

    0

    5

    8

    1

    1

    1

    1

    Unconstrained

    24

    192

    5 7

    5

    8

    1

    1

    1

    1

    Table 3

    Ranges for param eters adjustments

    Parametergroup

    Demand patterns factors (%)

    Nodal demands multiplier (%)

    Minor loss coefficients (Ks) (-)

    Float Actuated Valves (FAVs)

    loss coefficients (-)

    C-factors (-)

    'Walski e t

    al

    (2001).

    Mays (2000).

    Ranges of parameters vaiues per

    scenario

    Constrained

    Not applicable

    30%

    Not applicable

    0-350

    130-150='

    Unconstrained

    30%

    50%

    0-20''

    0-350

    130-150

  • 7/24/2019 Automated Parameter Optimization of a Water Distribution

    8/16

    78 M Mndeztal Automated parameter optimization of a water distr ibution system

    Journai of Hydroinformatics | 15.1 | 2013

    the constrained and unconstrained scenarios, respectively.

    Minor loss coefficients {K ) for pipe fittings were allowed

    to vary from 0 to 20 based o n typical values found in the lit-

    eratu re (Mays 2000). FAVs loss coefficients (K) were

    allowed to vary from 0 to 350 based on manufacturer's

    pressure drop curves and field measurements. Two fiow

    tests con ducted in 69 mm PVC showed C-factor values of

    130 and 134 correspondingly. For instance, a lower value

    of 130 was selected for C-factors in each scenario while a

    feasible upper value of 150 was obfained from the literature

    (Walskiet al.2001).

    Even when observations were recorded every 60 min a

    hydraulic timestep of

    min was used for the entire 168-hr

    simulation period regardless of the optimization approach

    (trial-and-error or PPEST). This is due to the fact that

    many observations (mainly nodal pressures) were sparsely

    and manually recorded throughout the enfire recording

    period and no specific timing for field measurements was

    possible.

    An Intel Core 7-930, 2.80 GHz multi-core processor

    with 24 GB of RAM mem ory was used to run PPEST by con-

    trolling one master and eight slaves (two for each of the four

    cores of the i-7 processor). PPEST was run in esfimation

    mode which means that PPEST confinued with the iteration

    procedure until the global minimum was found. All other

    PPEST numerical parameters were assigned typical values

    as noted in the PEST manual (Doherty 2005).

    Efficiency of the model opfimizafion process was

    assessed according to two indicators (Maslia et al. 2009):

    the Pearson correlation coefficient R),

    .ti OiMi) - [nM ]

    U m) - (Of))] [Er=i

    and the root mean square error (RMSE),

    2)

    2

    3)

    where n equals the total number of observations, O, is the

    observed-value on timestep i, is the average of the

    observed values, M,- is the modeled-value on timestep ian d

    M is the average of the modeled values.

    R

    serves as an indicator of the correlation degree

    between observed and modeled values. A value of 1 yields

    perfect correlation whereas a value of 0 indicates that data

    are uncorrelated. The RMSE provides information on the

    average error between observed and modeled values.

    RESULTS AN D DISCUSSION

    RMSE and R for modeled values of water levels and nodal

    pressures were obtained from the two opfimization

    approaches: trial-and-error and PPEST. Overall, both PPEST

    optimization scenarios resulted in lower RMSE and higher R

    than those ob tained by trial-and-error. Nevertheless, little vari-

    ation in RMSE andRbetween PPES T scenarios can be seen

    (Table 4).

    This is more evident for water levels in WSTs as RMSE

    remains within the 0.1 m accuracy expected for pressure

    sensors. In the trial-and-error approach, RMSE for water

    levels remains over the 0.1 m accuracy except for WST 2

    (0.06 m). Sfill, RMSE values obtained by trial-and-error are

    considered acceptable if limitations in observation data

    acquisition are taken into account.

    WSTs 1, 3 and 4 experienced the highest RMSE

    reductions, 54.8, 31.2 and 32.8%, respectively for the

    PPEST constrained scenario. Very similar values (57.6,

    41.4 and 36.7%) were obtained for the PPEST uncon-

    strained scenario. WST 2 is the excepfion for both PPEST

    scenarios since its RMSE increased rather than decreased

    with respect to the trial-and-error approach.

    As mentioned, PPEST attempts to globally m inimize the

    objective function PHI taking into consideration the contri-

    bufions of the available observation groups. Since the

    relative weight of the water level observation group was

    the same for all tanks, it appears that PPEST allowed for

    higher deviations in WST 2 in order to compensate for

    errors in the remaining WSTs and pressure monitoring

    nodes. Maslia et al. (2009) obtained similar results in their

    EPANET-PEST analysis of the Holcomb Boulevard WDS,

    with RMSE reducfions between 26.5 and 91.4%. Their

    study included four WSTs, one of which experienced an

    increase in RMSE after fhe optimization with PEST.

    In our case, correlation coefficients increased in both

    PPEST scenarios, with WST 1 presenfing the highest R

  • 7/24/2019 Automated Parameter Optimization of a Water Distribution

    9/16

    79

    M

    Mndez

    et

    a i Automated parameter optimization

    of a

    water distribution system

    Journaiof ydroinformatics | 15 1 | 2013

    Tab ie4 RMSE

    and i?

    modeled values

    of

    water levels

    and

    nodal pressures

    for the

    town

    of La

    Sirena s wa ter distribution system model

    Optimization approach

    Component

    Water levelsinTank1

    Water levels

    in

    Tank

    2

    Water levels

    in

    Tank

    3

    Water levelsinTank4

    Nodal pressures

    Triai-and-error

    Objective function

    RMSE (m)

    0.134

    0.064

    0.116

    0.158

    4.678

    R(-)

    0.821

    0.895

    0.946

    0.879

    0.981

    Constrained PPEST scenario

    Objective function

    RMSE (m)

    0.061

    0.068

    0.080

    0.106

    1.852

    0.965

    0.917

    0.982

    0.940

    0.998

    Percentage change

    R S m)

    -54.781

    6.438

    -31.194

    -32.825

    -60.407

    R(-)

    17.548

    2.429

    3.733

    6.979

    1.732

    unconstrained PPEST scenario

    Objective function

    RMSE (m)

    0.057

    0.073

    0.068

    0.100

    1.545

    0.975

    0.911

    0.987

    0.947

    0.999

    Percentage change

    RMSE (m)

    -57.617

    13.633

    -41.437

    -36.713

    -66.976

    18.707

    1.796

    4.252

    7.777

    1.776

    increase,

    17.6 and 18.7 for the

    constrained

    and

    uncon-

    strained scenarios, respectively.

    In the

    case

    of

    nodal

    pressures, PPEST significantly reduced RMSE with respect

    to

    the

    trial-and-error approach

    as it

    passed from

    4.7 to

    1.9 m for the

    constrained scenario

    and 1.5 m for the

    uncon-

    strained scenario.

    In all

    cases, RMSE

    for

    nodal pressures

    weis higher than

    the m

    accuracy expected

    for

    pressure

    gauges.

    The

    difference

    of

    roughly

    0.4 m in

    RMSE between

    th e

    two

    PPEST scenarios might seem trivial,

    but it

    does

    have profound implications

    in the

    optimization process.

    As

    the

    method used

    in

    EPANET

    to

    solve

    the now

    conti-

    nuity

    and

    headloss equations

    is

    driven

    by

    nodal demands

    and energy losses (Rossman 2000), small measurement

    errors

    and

    large parameter spaces

    can

    lead

    to

    large errors

    in estimated parameters. This

    is

    clearly

    the

    case

    of the

    PPEST unconstrained scenario, where every single

    par-

    ameter

    was

    declared adjustable

    in

    PPEST (Table

    3).

    These

    conditions defined

    an

    unmanageable parameter space

    of

    723 parameters, which implied

    the

    optimization

    of

    every

    single nodal demand, dem and pattern

    and

    minor loss coeffi-

    cient

    in the

    system.

    The

    conditions stated

    for

    this scenario

    evidently forced PPESTtocalibratethemodelbycompen-

    sating

    for

    errors

    as

    suggested

    by

    Walsld (1986). Errors

    in

    nodal demands were most likely compensated

    by

    errors

    in

    demand patterns, minor loss coefficients, C-factors

    and

    pretty much

    any

    other adjustable parameter.

    The

    problem

    is aggravated

    by the

    fact that nodal demand

    is

    still

    the

    most uncertain

    and

    variable parameter

    in

    this case study.

    The large parameter space

    and

    considerable compensating

    errors resulted

    in a 1.5 m

    RMSE

    for

    nodal pressures,

    but

    also required considerable change

    in the

    individual nodal

    demands.

    After

    the

    PPEST optimization,

    all

    nodes experienced

    some level

    of

    change

    in

    demand (Figure

    3)

    with

    an

    absolute

    average change

    of

    34.2%. Several nodes were pushed

    towards

    the

    predefined upper

    and

    lower demand bounds

    (Table

    3).

    Over

    40

    nodes exhibited

    a -50

    change

    i

    demand

    and

    over

    50

    nodes experienced

    a -f50

    change

    in

    demand.

    The

    parameter space

    was too big for

    PPEST

    t

    search effectively.

    Total water demand

    for the

    system changed only

    slightly,

    as it

    passed from

    10.58 to

    10.471s ' after

    th

    PPEST unconstrained optimization. This represents

    a per

    centage change

    in

    total water demand

    of

    around

    1 .

    This

    reaffirms once more

    the

    presence

    of

    considerable compen-

    sating errors.

    In

    this respect, PPEST

    is

    most likely

    producing

    a

    numerically correct

    but

    physically meaningless

    solution. Furthermore, PPEST

    is

    possibly matching obser-

    vations rather than determining

    the

    system's optimal

    parameters

    as

    there

    is an

    excessive number

    of

    parameter

    groups

    and

    insufficient observation data. Baranowski

    (2007) encountered similar conditions when calibrating

    nodal demands

    in two

    experimental EPANET networks

    using PEST and Newton-Raphson algorithms. Both methods

    maximized hydraulic

    and

    water quality standards

    but

    also

    required significant change

    in the

    nodal demands. C-factors

    had little chance

    to

    actively participate

    in the

    optimization

    process

    as one

    unique parameter

    was

    defined

    for all

    pipes.

    An optimized C-factor value

    of 137 was

    found

    for al

    pipes that remain close

    to the

    C-factor values found

    fo

    th e

    two

    fiow tests conducted

    in 69 mm PVC (130 and 13

    correspondingly).

    At the end of the

    optimization process,

    the percentage change between trial-and-error

    and

    PPEST

    optimized values

    was

    2.1%

    for

    local losses

    and 8.5 fo

  • 7/24/2019 Automated Parameter Optimization of a Water Distribution

    10/16

    8

    M Mndez t

    al

    | Automated parameter optimizationofa water distribution system

    JournaiofHydroinformatics | 15.1 | 2013

    -50-40 -40-30 -30-20 -20-10 -10-0 0-10 10-20

    Difference in nodal demand

    Figure3

    I

    Percent change

    for

    nodal demand after PPEST unconstrained optimization scenario.

    20-30 30-40 40-50

    FAVs. These percentages could seem small compared to

    those experienced by nodal demands or demand pattern fac-

    tors; however,it isrelativetothe overall sensitivityofeach

    adjustable parameter.

    In the case

    of

    the PPE ST constrained scenario, only

    24

    adjustable parameters were declared (Table 3). The remain-

    ing parameters were either fixedortiedtoother param eters.

    In PEST,a tied parameter represents a parameter thatis

    linkedto amaster parameter.Inthis case, only the master

    parameteris optimized andthe tied parametersaresimply

    varied with this parameter, maintaining a constant ratio,

    through the calibration process.

    This representsamuch smaller parameter space. Nodal

    demands were aggregated into four different demand

    groups, one

    for

    each pressure zo ne. Since demand pattern

    and minor loss coefficients were fixed,thesolution of the

    parameter space was limited tofour noda l dem ands (four

    parameters), four FAV valves 12parameters) and eight

    C-factors (eight parameters). In this case, the absolute

    average changeofnodal demand w as 13.4 , much lower

    than the 34.2 found for the unconstrained scenario.

    None of thenodes w ere pushed towards the predefined

    upper and lower demand bounds. This would appearto be

    the resultof compensating errors from theC-factors group

    (Table 5).

    Table5

    I

    Optimized C-fac tor vaiues after PPEST constra ined optimiz ation sc enario

    Pipe internal diameter mm) initial c-factor

    PEST optimized C-factor

    84

    69

    57

    45

    40

    31

    25

    19

    36

    36

    36

    36

    36

    36

    36

    36

    36

    37

    36

    4

    4

    36

    4

    Nevertheless, almost all diameter groups remainedin

    the lower bound

    of

    130. Only pipes with internal diameters

    of 69 and 45 mm w ere moved to higher values (138 and 150,

    respectively). Since demand patterns and minor loss coeffi-

    cients were fixed, compensating errors for this scenario

    are considerably lower than those of the unconstrained

    scenario. For instance, this solutionis more physically cor-

    rect asPPESThad a higher chance to findtheoptimum

    setofparam eter v alues. Still, no validation data exist to sus-

    tain this statement. Maslia et al (2009) experienced

    comparable resultsintheir analysisofHolcomb Boulevard

    WD S as PVC C-factor change from its original 145 proposed

  • 7/24/2019 Automated Parameter Optimization of a Water Distribution

    11/16

    81 M. Mndez et

    al \

    Autom ated parameter optimization of a water distribution system

    Journal of Hydroinformatics | 15 1 | 201 3

    value to an optimized range of 147-151 optimized values.

    This is more likely to be a consequence of the inherent

    smoothness of plastic materials and low relative sensibility

    as compared to other materials such as cast iron or steel

    which are greatly affected by age, corrosion and deposition

    processes (Koppel & Vassiljev 2009).

    Total system water demand also changed only slightly,

    as it passed from 10.58 to 10.50 ls ^ for th e PPE ST con-

    strained scenario. Regarding temporal variation of water

    levels at WSTs, a closer match between observed and mod-

    eled values can be appreciated for the PPEST scenarios

    (Figure 4). This is particularly true for WSTs 1 and 3

    (Figure 4(a),(c)), whereas little difference can be seen for

    tank s 2 and 4 (Figure 4(b),(d)) regardless of the optimization

    approach. The PPEST unconstrained scenario was partly

    based on the adjustment of the demand pattem factors

    (Table 3).

    PPEST optimized weekday demand factors are gener-

    ally in good agreement with those initially obtained by

    analyzing diurnal dynamics of water demand, particularly

    for WSTs 1 and 3 (Figure 5(a),(c)).

    There are, however, local differences that show a

    larger variation around the hours of higher water

    demand , betw een 0900 and 1400 hr, p rincipally for

    WSTs 2 and 4 (Figure 5(b),(d)). This could be attributed

    to the relative sensitivity of those pattern factors. None-

    theless, little confidence can be attributed to these

    patterns as compensating errors are very high for the

    PPEST unconstrained scenario.

    Parameter sensitivity

    As calculated by PPEST, the WDS model is mostly

    sensitive to nodal demands since this group of

    parameters exhibits the highest average composite sensi-

    tivities for both constrained and unconstrained

    scenarios, 2.86 and 2. 2 6 x lO \ respectively (Table 6).

    As discussed above, EPANET is controlled by water

    12 24 36 48 6

    0.5

    12

    24 36

    Time hrs)

    48 60

    12 24 36 48

    Time hrs)

    60 72

    EXPLANATION Obs ervations - PPEST Con strained PPEST Unco nstraine d Trial-and-Error

    Figure 4

    I PPEST optim ized wa ter-lev el values for a time lapse of 72-hr.

  • 7/24/2019 Automated Parameter Optimization of a Water Distribution

    12/16

    82

    Mndez

    et

    s/ Automa ted parameter optimization

    of

    a water distribution system

    JournalofHydroinformatics | 15.1 | 2013

    10 12 14 16 18 20 22 24

    Time iirs)

    6 8

    1 12 14

    Time iirs)

    16 18 20 22 24

    EXPLANATION

    Initial Estimation

    PPEST Unconstrained

    igure

    5I

    Initially estimated versus PPEST unconstrained optimized weei

  • 7/24/2019 Automated Parameter Optimization of a Water Distribution

    13/16

    83 M Mndez eta l | Automated parameter optimization of a water distribution system

    Journai of Hydroinformatics | 15 1 | 2013

    are only determinant if sufficient head loss is experienced

    across the WDS. This is clearly not our case, as velocities

    and head losses are quite small most of the fime.

    Objective function

    From a practical standpoint, it is essenfial to assess the

    number of model calls that PPEST required to minimize

    its objective funcfion PHI {0 . For the unconstrained scen-

    ario,

    PPEST needed to run EPANET 6507 fimes in order

    to find what PPEST considers to be the global minimum .

    This global min imu m w as found after the fifth iterafion,

    achieving a PHI reduction of nearly 77%, as its initial value

    was reduced from 7.77 to 1.817 m^. As stated by G oegebeur

    & Pauwels (2007), even when PHI differs from RMSE, the

    minimization of this function also leads to a minimization

    of the RMSE (Table 4).

    After running in estimafion-mode, PPEST executed four

    addifional iterafions after the global minimum was found,

    just to ensure that it did not encounter a local minimum.

    A total of 10,845 EPANET calls were needed to complete

    the optimization process, wh ich lasted for 13.2 hr, clearly

    indicafing a high computational burden. If PEST instead

    of PPEST had been used in this case, an estimated 90.4 hr

    run would have been needed to accomplish the same

    result. This is quite predictable as PEST's final report

    states how long it needs to complete one EPANET's run.

    For the m ore realistic and physically correct co nstrained

    scenario, PPEST com pleted the who le opfimizafion process

    in 0.74 hr, almost 18 times faster th an the unco nstrained

    scenario and with similar outcomes as PHI was reduced

    from its original trial-and-error value of 7.77-2.065 m^.

    The most fime consuming part of PPEST's operafions is

    related to the calculation of the Jacobian matrix through par-

    tial derivatives, which requires two model calls for each

    adjustable parameter. Nonetheless, the calculation of the

    Jacobian matrix permits PPEST to derive important by-

    products such as relative and absolute sensitivity, corre-

    lation, uncertainty and Eigenvectors which are of great

    importance in post-optimization analysis.

    On the other hand, PPEST is capable of fixing par-

    ameters based on a given sensitivity threshold. This could

    help improve PPEST's performance through modeler inter-

    venfion (Doherty 2005). Finally, it is important to note that

    EPANET is a fully distributed complex hydraulic solver

    which demands a great deal of computafional resources by

    its lf

    This clearly increases the time lapse needed for

    PPEST to achieve convergence.

    CONCLUSIONS

    The feasibility of using the model independent parameter

    esfimator PPE ST to develop a fully-calibrated extend ed

    period model for a WDS using EPANET was investigated.

    It was found that the results from a fully automated cali-

    brafion technique like PPEST should be used with caufion.

    As calibration is a highly underdetermined problem,

    PPEST may produce numerically correct but physically

    meaningless solutions if insufficient restrictions are applied.

    The two PPEST scenarios analyzed in this study further

    emphasize this situation.

    The uncon strained scenario show ed that if all parameters

    are open to adjustment, considerable com pensating errors are

    introduced into the optimization process. Under these cir-

    cumstances, PPEST was capable of matching observations

    but incapable of determining the opfimtim set of param eters

    for the system. As the number of unknown s was mu ch greater

    than the number of observafions, the parameter space was

    simply too large for PPEST to find a proper solufion. It was

    demonstrated that including insensitive parameters signifi-

    cantly deteriorates model's solufions and imposed a heavy

    computational burden on the whole optimization process.

    On the other hand, the constrained scenario represents

    a more properly discretized and therefore, more reliable

    scheme as parameters were grouped in classes of similar

    characteristics and insensitive parameters were fixed. This

    had a profound impact on the parameter space as adjustable

    parameters were reduced from 723 in the unconstrained

    scenario to 24 in the constrained scenario. In this regard,

    the computational requirements were much lower as the

    whole opfimization process took 0.74 hr as com pared to

    the 13.2 hr needed for the uncons trained scenario.

    The model was mainly sensitive to nodal demands as

    average composite sensitivities for both constrained and

    unco nstrained PPEST scenarios reache d 2.86 and 2.26 x

    10 \ respectively. The FAVs loss coefficients r epre sente d

    the second most sensitive group of parameters as their

  • 7/24/2019 Automated Parameter Optimization of a Water Distribution

    14/16

    8 M Mndez et

    ai

    | Automated parameter optimizationof awater distr ibution system

    Journai

    of

    Hydroinformatics

    | 15 1 | 2013

    average composite sensitivity reached values of

    1.8080

    x

    10 ^ and 2.5980 x 10 for the constrained and uncon-

    strained PEST scenarios, respectively. The remaining

    groups of parameters, including C-factors, showed very low

    sensitivities, two to three orders in magnitude lower than

    that of nodal demands. A considerable RMSE reduction

    was obtained for the constrained scenario, particularly for

    nodal pressures as its value decreased from 4.68 to 1.85 m.

    The constrained solution, even when it is valid only for

    the system's normal operating conditions, clearly demon-

    strates that PPEST has the potential to be used in the

    calibration of WDS models.

    FUTURE WORK

    Further investigation is needed to determine PPEST's per-

    formance in complex WDS models over a wide range of

    operating conditions. This may include the evaluation of

    control valves, pump curves, control rules and water quality

    issues.

    An EPANET-PEST utility software could be devel-

    oped to facilitate communication between both packages.

    This would allow users to run PEST directly in a graphical

    environment, where many of the variables and outcomes

    of the calibration process could be viewed and externally

    manipulated.

    C K N O W L E D G M E N T S

    The authors wish to thank Junta Administradora del

    Acueducto La Sirena, La comunidad de la Sirena,

    Estacin de Investigacin y Transferencia de Tecnologa

    de Puerto Mallarino and Cinara-Universidad del Valle for

    their help and guidance in the development of this project.

    REFERENCES

    Abe,

    N. &

    Cheung,

    P.

    B. 2010 E panet Calibrator

    - an

    integrated

    computational toolto calibrate hydraulic models.Int. Water

    Syst.V,

    129-133.

    Alvisi,

    S. &

    Franchini, M. 2010 Pipe roughness calibration

    in

    water distribution systems using grey numbers.

    /.

    Hydroinf

    12

    424-445.

    Arabi,

    M.,

    Govindaraju,

    R. S. &

    Hantush, M. M. 2007 A

    probabilistic approach

    for

    analysis

    of

    uncertainty

    in the

    evaluation of watershed management practice. /.

    Hydrol

    333

    459-471.

    Bahremand, A.& deSmedt, F. 2010 Predictive analysisand

    simulation uncertainty

    of a

    distributed hydrological model.

    /. Water Res. Manage.24 2869-2880.

    Baranowski, T. 2007 Development

    of

    Consequence Management

    Strategiesfor Water Distribution Systems. Doctoral

    Dissertation, Graduate School

    of

    Vanderbilt University,

    Nashville, Tennessee, USA.

    Beven,

    K. &

    Binley, A. 1992 Tbe future

    of

    distributed models:

    model calibrationand uncertainty prediction.Hydrol.

    Process.

    6,

    279-298.

    Cabrera,E.,Espert, V., Garcia-Serra,J. &Martinez, F. 1996

    Ingenierahidrulica.Aplicada

    a

    los sistemas de d istribuein

    de agua. Universidad PolitcnicadeValencia, Spain.

    Cbristensen,

    S. &

    Doherty, B. 2008 Predictive error dependencies

    when using pilot points

    and

    singular value decomposition

    in groundwater model calibration. Adv. WaterResour

    31

    674-700.

    de Sch aetzen, W ., Hung, J., Clark, S., Gottfred,C,Acosta, B.&

    Reynolds, P. 2010 How mu eb is your uncalibrated model

    costing your utility? Ten lessons learned from calibrating th e

    CRD Water M odel. In

    Proc.WaterD istribution System

    Anlisis(A. Z. Tucson,

    ed.).

    USA, Sept.

    12-15, pp.

    1053-1065.

    Doberty, J. 2005 PEST:Model IndependentParameterEstimation

    Users

    Manual.

    Watermark Numerical Computing, Brisbane.

    Duan,

    Q.,

    Soroosbian,

    S. &

    Gupta, V.

    K.

    1992 Effective

    and

    efficient global optimization

    for

    conceptual rainfall runoff

    models.WaterResour Res.24 1163-1173.

    Fang, T.&Ball, J. E. 2007 Evaluationofspatially variable control

    parameters

    in a

    complex catchment modelling system:

    a

    genetic algorithm ap plication./.Hydroinf 9,163-174.

    Gallagher, M.

    R. &

    Doherty, ]. 2007 Parameter interdependence

    and uncertainty inducedbylumpingin a hydrologie model.

    Water Resour Res.

    43

    1-18.

    Giustolisi,

    O. &

    Berardi, L. 2on Water distribution network

    calibration using enhanced GGA

    and

    topological analysis.

    /. Hydroinf 13 621-641.

    Goegebeur,M. &Pauwels,R. N. 2007 Improvementofthe PEST

    parameter estimation algorithm through Extended Kaiman

    Filtering.

    /.

    Hydrol 337

    436-451.

    Hogue,

    T.,

    Gupta,

    H. &

    Soroosbianc,

    S.

    2006

    A

    'User-Friendly'

    approach

    to

    parameter estimation

    in

    hydrologie models.

    /.

    ydroL

    320 202-217.

    Ibrahim, Y.

    &

    Liong,

    S.

    Y. 1992 Calibration strategy

    for

    urban

    eatebment parameters. ASCE . Hydraul Eng.

    118

    1550-1570.

    Immerzeel, W. W.&Droogers, P. 2008 Calibration of a distributed

    bydrologieal model based

    on

    satellite evapotranspiration.

    /. Hydro/.349 411-424.

    Jamasb, M., Tabesh,M. &Rahimi, M. 2008 C alibrationof

    EPANET using Genetie Algorithm.

    In

    Proc. 10 th Annu al

    Water Distribution Systems Analysis Conference Kruger

  • 7/24/2019 Automated Parameter Optimization of a Water Distribution

    15/16

    85 M Mndez et

    a l

    Automated parameter optimization of a water distr ibution system

    Journal of Hydroinformatics | 15 1 | 201 3

    National Park, South Africa, August 17-20th, 2008,

    pp. 881-889.

    Kang, D. Lansey, K. 2009 Real-time dem and estimation and

    confidence limit analysis for water distribution systems.

    ASCE ]. Hydraul. Eng.135 825-837.

    Kapelan, Z., Savie, D. A. Walters, G. A. 2007 Calibration of

    water distribution hydraulic models using a Bayesian-Type

    procedure.

    ASCE

    /.

    Hydraul. Eng.

    133, 927-936.

    Kenward,

    T.

    C. How ard, C. D. 1999 Forecasting for urban water

    demand management. In Proe.

    Annual Water Resources

    Planning and ManagementConf. ASCE, Tempe, A rizona,

    USA. June6-9th 1999, ch. 9A188, pp. 1-15.

    Kliu, S. T., di Pierro, F., Savic, D., Djordjevic, S. W alters, G. A.

    2006 Incorporating sp atial and tempo ral information for urban

    drainage model calibration: an approach using preference

    ordering genetic algorithm.Adv.

    Water

    Res.29,1168-1181.

    Kopp el, A. Vassiljev, A. 2009 Calibration of a model of an

    operational water distribution system containing pipes of

    different age.Adv. Eng. Softw.40, 659-664.

    Kovalenko , Y., Gorev, N . B., Kodzhespirova, I. F., Alvarez, R.,

    Prokho rov, E. Ramos, A. 2010 Experim ental analysis of

    hydraulic solver convergence with Genetic Algorithms.

    ASCE]. Hydraul. Eng. 136 331-335.

    Kum ar, S. M., Nara simh an, S. Bhallamudi, S. M. 2009

    Parameter estimation in water distribution networks. /.

    Water

    Res. Manage.24, 1251-1272.

    Lansey, K. E. Basnet, C. 1991 Param eter estimation for water

    distribution networks. ASCE

    J.

    Water Res. Plann. Manage.

    117,

    126-144.

    Lee, E. J. Schwab , K. J. 2005 Deficiencies in drinking water

    distribution systems in developing countries. /. Water Health

    3, 109-127.

    Machell, J., Mo unce, S. R. Boxall, J.B.2010 Online modelling of

    water distribution systems: a UK case study.Drink.

    Water

    Eng. Sei 3, 21-27.

    Maslia, M. L., Surez-Soto,R.] .,Wang, J., Aral, M. M., Faye, R. E.,

    Sautner, J. B., Valenzuela, C. Graym an, W. M. 2009

    Analysis of Groundwater

    Flow

    Contaminant

    Fate

    an d

    Transport and Distribution of Drinking Water at

    Tarawa

    Terrace

    an d

    Vieinity U.S.

    Marine

    Corps

    Base Camp Lejeune

    North Carolina: Historieal Reeonstruetion and

    Present Day

    Conditions.

    Agency for Toxic Substances and Disease

    Registry. US Department of Health and Human Services,

    Atlanta, Georgia.

    Mays, L. W. 2000 Water Distribution Systems Handbook.

    McGraw-Hill, New York.

    Nicklow,J.W., Reed, P., Savic, D. A., Dessalegne, T., Harrell, L.,

    Chan-Hilton, A., Karamouz, M., Minsker,

    B.,

    Ostfeld, A., Singh,

    A. Zechm an, A. 2009 State of the art for genetic algorithms

    and beyond in water resources planning and management.

    ASCEJ.

    Water

    Res.

    Plann. Manage. 136 412-432.

    Peng, S., Wu, Q. Zhu ang, B. 2009 Param eter identification by

    MCMC method for water quality model of distribution

    system. In Proe. 3th Intemational

    Conferenee

    on

    Bioinformaties and Biomdical

    Engineering Beijing, China,

    June ll-13th, 2009, pp. 1-5.

    Rossman, L. A. 2000 EPANET 2

    Users

    Manual. National Risk

    Management Research Laboratory, Office of Research and

    Development. US E nvironmental Protection Agency,

    Cincinnati, Ohio, USA.

    Savic, D. A., Kapelan, Z. Jonkergouw , P. 2009 Quo vadis wa ter

    distribution model calibration?

    Urban

    WaterJ. 6, 3-22.

    Skahill, B. E. 2009 More efficient PEST com patible m odel

    independent model calibration. /.

    Environ. Model. Softw.

    24,

    517-529.

    Skahill, B. E. Doherty, J. 2006 An advanced regularization

    methodology for use in watershed model calibration. /.

    Hydrol.327, 564-577.

    Tischler, M., Garcia, M., Peters-Lidard, C, Moran, M. S., Miller, S.,

    Thoma, D., Kumar, S. Geiger,

    J.

    2007 A G IS framework for

    surface-layer soil moisture estimation combining satellite radar

    measurem ents and land surface m odeling with soil physical

    property estimation. /.

    Environ. Model. Softw.

    22, 891-898.

    USEPA 2005

    W ater Distribution System Ana lysis: Field Studies

    Modeling and Management: A Reference Guide for Utilities.

    Office of Research and Development. National Risk

    Management Research Laboratory, Water Supply and W ater

    Resources Division, Cincinnati, Ohio, USA.

    Walski, T. M. 1986 Case study: pipe network model calibration

    issues. ASCE f. Water Res. Plann. Manage. 112 238-249.

    Walski, T., DeF rank, N., Voglino, T., Wood , R. Wh itman, B. E.

    2006 Determining the accuracy of automated calibration of

    pipe network models. In Proe. 8th Annual Water

    Distribution Systems Analysis Symposium Cincinnati, O hio,

    USA, August 27-30th, 2006, pp. 1-18.

    Walski, T., Wu, Z. Hartell, W. 2004 Performance of automated

    calibration for water distribution systems. In Proe. World

    Water and Environmental Resources Congress

    Salt Lake

    City, Utah, USA, June 27th-July 1st, 2004, pp. 1-10.

    Walski, T. M., Chase, D. V. Savic, D. A.

    2 1

    Water Distribution

    Modeling. Haestad Press, Waterbury.

    Wu, Z. Y, B oulos,P. F.,Orr,C.H. Ro,J. J.

    2

    An efficient g enetic

    algorithms approach to an intelligent decision supp ort system

    for water distribution networks. InProe. H ydroinformaties 2000

    Conference Iowa, IW, USA, July 23-27 th, 2000.

    Wu, Z. Y, Walski, T. M., Mankowski, R., Herrin, G., Gurrieri, R.

    Tryby, M. 2002 Calibrating water distribution model via

    genetic algorithms. In Proe. AWWA IMTech Conference

    Kansas City, Missouri, USA, April 14-17th, 2002, pp. 1-10.

    Zaghloul, N. A. Abu Kiefa, M. A.

    2 1

    Neural network solution

    of inverse parameters used in the sensitivity-calibration

    analyses of the SWMM model simulations. Adv. Eng. Softw.

    32,587-595.

    Zhou, S. L., McMahon,T.A. Lewis, W.J.2000 Forecasting d aily

    urban water demand: a case study of Melbourne. /. Hydrol.

    236,

    153-164.

    First received 8 February 2012; accepted in revised form 19 May 2012. Available online 11 September 2012

  • 7/24/2019 Automated Parameter Optimization of a Water Distribution

    16/16

    Copyright of Journal of Hydroinformatics is the property of IWA Publishing and its content may not be copied

    or emailed to multiple sites or posted to a listserv without the copyright holder's express written permission.

    However, users may print, download, or email articles for individual use.